Contract No: HK/2011/07

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 2)

 

Environmental Permit no. EP-364/2009/C,

Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/A, FEP-08/364/2009/A, FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B

 

Monthly Environmental Monitoring & Audit Report

 

-  september 2014 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

13 October 2014


Table of contents         

 

EXECUTIVE SUMMARY. 4

1            Introduction. 12

1.1        Scope of the Report 12

1.2        Structure of the Report 12

2      Project Background. 14

2.1        Background. 14

2.2        Scope of the Project and Site Description. 14

2.3        Division of the Project Responsibility. 15

2.4        Project Organization and Contact Personnel 16

3         status of regulatory compliance. 23

3.1        Status of Environmental Licensing and Permitting under the Project 25

4          Monitoring Requirements. 40

4.1        Noise Monitoring. 40

4.2        Air Monitoring. 42

5.0        Monitoring Results. 44

5.1        Noise Monitoring Results. 45

5.2        Real Time Noise Monitoring Results. 47

5.3        Air Monitoring Results. 49

5.4       Waste Monitoring Results. 51

6.0        Compliance Audit. 56

6.1        Noise Monitoring. 56

6.2        Air Monitoring. 57

6.3        Review of the Reasons for and the Implications of Non-compliance. 58

6.4        Summary of action taken in the event of and follow-up on non-compliance. 58

7.0        Cumulative Construction Impact due to the Concurrent Projects. 58

8.0        Enviromental site audit. 60

9.0        Complaints, Notification of Summons and Prosecution. 64

10         Conclusion. 65


lIST OF TABLES

Table 2.1      Schedule 2 Designated Projects under this Project

Table 2.2      Details of Individual Contracts under the Project

Table 2.3      Contact Details of Key Personnel

Table 3.1      Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.4      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.5      Summary of submission status under FEP-02/364/2009

Table 3.6      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.7      Summary of submission status under FEP-01/364/2009

Table 3.8      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/18

Table 3.9      Summary of submission status under FEP-05/364/2009/A

Table 3.10    Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Table 3.11    Summary of submission status under FEP-06/364/2009/A

Table 3.12    Cumulative Summary of Valid License and Permits under Contract no. HY/2009/19

Table 3.13   Summary of submission status under FEP-07/364/2009/A

Table 3.14    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2010/06

Table 3.15    Summary of submission status under FEP-08/364/2009/B

Table 3.16    Cumulative Summary of Valid License and Permits under Contract no. HK/2012/08

Table 3.17    Summary of submission status under FEP-09/364/2009/B

Table 3.18    Cumulative Summary of Valid License and Permits under Contract no. HY/2010/08

Table 3.19    Summary of submission status under FEP-10/364/2009/B

Table 3.20    Cumulative Summary of Valid License and Permits under Contract no. HY/2011/08

Table 3.21   Summary of submission status under FEP-11/364/2009

Table 4.1      Noise Monitoring Stations

Table 4.2      Real Time Noise Monitoring Stations

Table 4.3      Air Monitoring Stations

Table 5.1      Noise Monitoring Stations for Contract no. HY/2009/18

Table 5.2      Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02

Table 5.3      Noise Monitoring Stations for Contract no. HY/2009/15

Table 5.4      Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.5      Noise Monitoring Stations for Contract no. HY/2010/08

Table 5.7      Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.9      Air Monitoring Stations for Contract no. HY/2009/18

Table 5.10    Air Monitoring Station for Contract no. HK/2009/01

Table 5.11    Air Monitoring Station for Contract no. HK/2009/02

Table 5.12    Air Monitoring Station for Contract no. HY/2009/15

Table 5.13    Air Monitoring Stations for Contract no. HY/2009/19

Table 5.15    Details of Waste Disposal for Contract no. HK/2009/01

Table 5.16    Details of Waste Disposal for Contract no. HK/2009/02

Table 5.17    Details of Waste Disposal for Contract no. HY/2009/18

Table 5.18    Details of Waste Disposal for Contract no. HY/2009/15

Table 5.19    Details of Waste Disposal for Contract no. HY/2009/19

Table 5.20    Details of Waste Disposal for Contract no. HK/2010/06

Table 5.21    Details of Waste Disposal for Contract no. HK/2012/08

Table 5.22    Details of Waste Disposal for Contract no. HY/2010/08

Table 5.23    Details of Waste Disposal for Contract no. HY/2011/08

Table 8.1      Summary of Environmental Inspections for Contract no. HY/2009/15

Table 8.4      Summary of Environmental Inspections for Contract no. HK/2009/01

Table 8.5      Summary of Environmental Inspections for Contract no. HK/2009/02

Table 8.7      Summary of Enviromental Inspections for Contract no. HK/2012/08

Table 8.8      Summary of Environmental Inspections for Contract no. HY/2010/08

Table 9.1      Cumulative Statistics on Complaints

Table 9.2      Cumulative Statistics on Successful Prosecutions

Table 10.1    Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

 

LIST OF FIGUREs

 

Figure 2.1         Project Layout

Figure 2.2         Project Organization Chart

Figure 4.1         Locations of Environmental Monitoring Stations

 

 

lIST OF APPENDIces

 

Appendix 3.1    Environmental Mitigation Implementation Schedule

Appendix 4.1    Action and Limit Level

Appendix 4.2    Copies of Calibration Certificates

Appendix 5.1    Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2    Noise Monitoring Results and Graphical Presentations

Appendix 5.3    Air Quality Monitoring Results and Graphical Presentations

Appendix 5.4    Real-time Noise Monitoring Results and Graphical Presentations

Appendix 6.1    Event Action Plans

Appendix 6.2    Notification of Exceedance

Appendix 9.1    Complaint Log

Appendix 10.1   Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Monthly Report íV September 2014 specific for Environmental Permit no. EP-364/2009/C, Further Environmental Permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/A, FEP-08/364/2009/A, FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B. The EM&A report is prepared by the Environmental Team (ET) employed under Contract No. HK/2011/07 íV Wan Chai Development Phase II and Central Wanchai Bypass íV Sampling, Field Measurement and Testing Works (Stage 2). This report presents the environmental monitoring findings and information recorded during the period of September 2014. The cut-off date of reporting is at 27th of each reporting month.

 

  1. In the reporting month, the principal work activities of individual contracts are included as follows:

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A

íP          Excavation of trial pit

íP          Transplanting of trees

íP          Drainage works

íP          Tunnel works including scaffolding erection, excavation, OHVD installation, roadside barriers, top and base slab construction

íP          Trough structure construction and associated drilling and grouting

íP          Road works

íP          Bridges construction

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

íP          Stage 1 construction of tunnel structures

íP          Stage 2 installation of pre-bored H-piles

íP          Stage 2 installation of sheet pile at exhaust duct area

íP          Stage 2 installation of dewatering well

íP          Stage 2 excavation and ELS works

íP          Stage 2 tunnel structure works

íP          Demolition of HKCEC pump house (Kiu Lok Portion)

íP          Demolition of 10 nos. of pump cells at Convention Avenue

íP          Stage 3 construction of D-wall.

íP          Stage 3 installation of pre-bored H-piles. 

íP          Discharge cooling main laying works for BI, BG & B

íP          S8B and S9 saltwater main laying works

íP          Sewage works along Fenwick Pier Street

íP          Construction of proposed box culvert

 

 

 

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009                                     

íP          The backfilling work for tunnel portion 1

íP          Loading transfer of all utility bridges

íP          Dismantling of  ELS

íP          D-Wall trimming works

íP          Excavation for Tunnel Portion 2

íP          Installation of dewatering system

íP          Bored pile PS30, PC31 and PS32

íP          Excavation of PS31

íP          Preparation works for resuming D-Wall construction

 

Contract no. HY/2009/15 - Central-Wanchai Bypass íV Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

 

íP          Post tunnel construction at TS1 and TS2

íP          Mined Tunnel drill-and-break works at East and West Portal

íP          Underwater Cutting of Temporary Diaphragm Walls at TS4 and TPCWAE

íP          Permanent lining structure at West Portal of Mined Tunnel

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

íP          Road works at Watson Road

íP          Bored piling (Land)

íP          Removal/ Installation of strut at ELS

íP          Construction of Dolphin Cap

íP          ELS for Cut &Cover Tunnel and EVB

íP          Excavation of ELS continue

íP          Laying of 1350f pipe

íP          Pre-bored H-pile for Admin. Building continue

íP          Parapet construction continue

íP          Construction of Bridge E

íP          Construction of Bride F4 and F5

íP          Construction of Pump Sump E

íP          Installation of Noise Barrier/enclosure

íP          Modification of existing crosshead at Pier 17-18

íP          IECL Road modification and removal of Median Barrier

íP          Construction of Column F2B

íP          Construction of Pile Cap F1B

íP          Laying of asphalt on Bridge Deck

 

 

 

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

íP          Cross wall sealing

íP          Concreting of turret openings

íP          Sealing of turrets

 

Contract no. HK/2012/08 íV Wan Chai Development Phase II íV Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009B

íP          Diaphragm wall construction

íP          Bored Pile Construction

 

Contract no. HY/2010/08 íVCentral - Wan Chai Bypass (CWB) íVTunnel (Slip Road 8) under FEP-10/364/2009B

íP          Tree & root pruning works

íP          Tree transplanting works,

íP          Tree works within off-site nursery compound,

íP          Drainage improvement works,

íP          Sheet piling works,

íP          Excavation and Lateral Support for U-structure,

íP          Erection of noise absorption sheetings,

íP          Pipe piling, ground pre-treatment, pre-boring works & jet grouting works,

íP          Utility diversion,

íP          Construction of Bowling Green Office &

íP          Temporary Traffic Arrangement & paving works for Victoria Park Road.

 

Contract no. HY/2011/08 íVCentral - Wan Chai Bypass (CWB) íVTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

íP          No physical construction activity on site

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Noise Monitoring

  1. Noise monitoring during daytime was conducted at M1a - Harbour Road Sports Center; M2b - Noon-day gun area; M3a - Tung Lo Wan Fire Station; M4b - Victoria Center; M5b - City Garden, M6 - HK Baptist Church Henrietta Secondary School, M7e and M7w íV International
  2. 24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot for construction activities at IEC bridge deck. No limit level exceedance was recorded in the reporting month.
  3. 24-hour real time noise monitoring was conducted at RTN2a íV Hong Kong Electric Centre. No project related exceedance was recorded in the reporting month.
  4. 24-hour real time noise monitoring was conducted at RTN3 íV Yu Lee Mo Fan Memorial School. No project related exceedance was recorded in the reporting month.
  5. 24-hour real time noise monitoring was conducted at RTN4 íV Causeway Bay Community Centre. No limit level exceedance was recorded in the reporting month.
  6. Liaison was conducted with HK Baptist Church Henrietta Secondary School and Po Leung Kuk Yu Lee Mo Fan Memorial School regarding the set up of RTN3 real time noise monitoring station.  Po Leung Kuk Yu Lee Mo Fan Memorial School grant permission for set up on 4 Sep 2012 and station set up was performed on 14 Sep 2012.
  7. Real time noise monitoring station at Oil Street Community Liaison Centre (RTN2- Oil Street Community Centre) was relocated from Oil Street Community Liaison Centre to Hong Kong Electric (RTN2a- Electric Centre) on 5 Oct 2012 which is a representative of the noise sensitive receiver City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.
  8. Real-time noise baseline capturing was conducted from 21 Sep 2012 to 04 Oct 2012 at RTN3-Po Leung Kuk Yu Lee Mo Fan Memorial School.
  9. Real-time Noise Monitoring at RTN3- Po Leung Kuk Yu Lee Mo Fan Memorial School was commenced since 06 Oct 2012.
  10. Causeway Bay Community Centre has granted permission for set up of real time noise monitoring station on 21 Dec 2012 and station set up was performed on 27 Dec 2012.  The Baseline noise level of RTN4- Causeway Bay Community Centre will adopt the results from the baseline noise monitoring report for EP/364/2009 in 22 April 2010 in which approved by EPD.
  11. According to clause 3.1 stated in EP-364/2009/B, ížthe real-time monitoring system shall be in place no later than two weeks before the commencement date of demolition works of the existing Island Eastern CorridoríĘ. IEC demolition associated construction works was commenced on 3 Feb 2013 and Real time noise monitoring at RTN4-Causeway Bay Community Centre was commenced on 13 Jan 2013.
  12. Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with respect to the commencement of advance works for IEC parapet demolition.
  13. With respect to the completion of Victoria Car Park refurbishment, the noise monitoring at M4b-Victora Center was reverted from 3/F to 2/F since 24 June 2014.

 

 

Air Monitoring

  1. Due to electricity interruption, the following 24hr TSP and 1hr TSP monitoring events were rescheduled in the reporting month,

24hr TSP monitoring at CMA5a was rescheduled from 24 September 2014 to 25 September 2014.

24hr TSP monitoring at MA1e were rescheduled from 1 and 18 September 2014 to 3 and 19 September 2014 respectively.

1hr TSP monitoring at MA1e were rescheduled from 2 September 2014 to 3 September 2014.

1hr TSP monitoring at MA1e were rescheduled from 25 September 2014 to 25 and 26 September 2014.

  1. Due to extension of site boundary by contractor of HY/2009/19, location of air monitoring station CMA1b íV Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.
  2. The location ID of air monitoring station CMA1b was updated as Oil Street Site Office in April 2013.
  3. 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b íV Oil Street Site Office; CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site Office Area; CMA4a íV Society for the Prevention of Cruelty to Animals; CMA5a - Children Garden opposite to Pedestrian Plaza; MA1e and MA1w íV International Finance Centre eastern and western podium on every six days basis.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. No environmental complaint was received in the reporting month.

Site Inspections and Audit

  1. The Environmental Team (ET) conducted weekly site inspections for Contract no. HY/2009/15, HY/2009/18, HY/2009/19, HY/2010/08, HK/2009/01, HK/2009/02, HK/2012/08 and HK/2010/06 in this reporting period.
  2. Construction of bored pile E3B under HY/2009/17 was confirmed completed and the respective work area under FEP-03/364/2009 was handover and inspected under HY/2009/19 from 19 Dec 2012 onwards.
  3. Construction works under HK/2010/06 was confirmed completed and the respective work area under FEP-08/364/2009/A was handover and inspected under HK/2012/08 from 22 Sep 2014 onwards.
  4. The Contractors rectified major observations and recommendations made during the audit sessions. No non-conformance was identified during the site inspections.

 

 

 

 

 

 

Future Key Issues

  1. In the coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HY/2009/18 íV Central íV Wan Chai Bypass (CWB) íV Central Interchange under FEP-05/364/2009/A

íP          Excavation of trial pit

íP          Transplanting of trees

íP          Drainage works

íP          Tunnel works including scaffolding erection, excavation, OHVD installation, roadside barriers, top and base slab construction, extract sheet pile, waterproofing and backfill

íP          Trough structure construction and associated drilling and grouting

íP          Road works

íP          Bridges construction

 

Contract no. HK/2009/01 íV Wan Chai Development Phase II íV Central íV Wan Chai Bypass at Hong Kong Convention and Exhibition Centre íV Tunnel Works under FEP-02/364/2009

íP          Stage 1 construction of tunnel structures

íP          Stage 2 excavation works 

íP          Stage 3 excavation works

íP          Waterworks

 

Contract no. HK/2009/02 íV Wan Chai Development Phase II íV Central íV Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

íP          Backfilling works to Tunnel Portion 1.

íP          Piezometer installation and commence pump test

íP          Installation of ELS at Strut S1 Level.

íP          Excavation to Strut S2 Level

íP          Bored pile construction.

íP          D-Wall construction works.

íP          Demolition of HHR Flyover Approach Ramp

 

Contract no. HY/2009/15 íV Central-Wanchai Bypass íV Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

íP          Post tunnel construction at TS1 and TS2

íP          Mined Tunnel drill-and-break works at East and West Portal

íP          Underwater cutting of Temporary Diaphragm Walls at TS4 and TPCWAE

íP          Permanent lining structure at West Portal of Mined Tunnel

 

 

 

 

 

Contract no. HY/2009/19 íV Central íV Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

íP          Road works at Watson Road

íP          Bored piling (Land)

íP          Removal/ Installation of strut at ELS

íP          Construction of Dolphin Cap

íP          ELS for Cut &Cover Tunnel and EVB

íP          Excavation of ELS continue

íP          Laying of 1350f pipe

íP          Pre-bored H-pile for Admin. Building continue

íP          Construction of Bridge E

íP          Construction of Bride F4 and F5

íP          Construction of Pump Sump E

íP          Installation of Noise Barrier/enclosure

íP          Modification of existing crosshead at Pier 17-18

íP          IECL Road modification and removal of Median Barrier

íP          Construction of TB Bridge

 

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

íP          Nil

 

Contract no. HK/2012/08 íV Wan Chai Development Phase II íV Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B

íP          Diaphragm wall construction

íP          Bored Pile Construction

 

Contract no. HY/2010/08 íVCentral - Wan Chai Bypass (CWB) íVTunnel (Slip Road 8) under FEP-10/364/2009B

íP          Tree & root pruning works

íP          Tree works within off-site nursery compound

íP          Drainage improvement works

íP          Sheet piling works

íP          Excavation and Lateral Support for U-structure

íP          Erection of noise absorption sheetings

íP          Pipe piling, ground pre-treatment, pre-boring works & jet grouting works

íP          Utility diversion

íP          Construction of Bowling Green Office and

íP          Waterproofing works.

 

Contract no. HY/2011/08 íV Central - Wan Chai Bypass (CWB) íVTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

íP      Installation of starter bar on West Ventilation Building for wall construction

1            Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009/C and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A, FEP-09/364/2009/B, FEP-10/364/2009B and FEP-11/364/2009B to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.     This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and ížEnvironmental Monitoring and Audit RequirementsíĘ under Particular Specification Section 27.

1.1.3.     This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/B, Further Environmental Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A, FEP-09/364/2009B, FEP-10/364/2009B and FEP-11/364/2009B during the period August 2014 to September 2014. The cut-off date of reporting is at 27th of each reporting month

 

1.2          Structure of the Report

 

Section 1          Introduction íV details the scope and structure of the report.

 

Section 2          Project Background íV summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3          Status of Regulatory Compliance íV summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4          Monitoring Requirements íV summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5          Monitoring Results íV summarizes the monitoring results obtained in the reporting period.

 

Section 6          Compliance Audit íV summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7          Cumulative Construction Impact due to the Concurrent Projects íV summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8          Site Inspection íV summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9          Complaints, Notification of summons and Prosecution íV summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10        Conclusion

2      Project Background

2.1          Background

2.1.1.     ížWan Chai Development phase II and Central-Wan Chai BypassíĘ and ížCentral-Wan Chai Bypass and Island Eastern Corridor LinkíĘ (hereafter called ížthe ProjectíĘ) are Designated Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.     The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.     There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2          Scope of the Project and Site Description

2.2.1.     Design and Construction of Central íV Wan Chai Bypass and Island Eastern Corridor Link under the Project involves the construction and operation of a trunk road and its road tunnel more than 800m in length between portals that is shown at Figure 2.1.

2.2.2.     The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:

íP      A dual three-lane trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length defined from the connection with the existing Rumsey Street Flyover in Central, through to a connection with the existing Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);

íP      The Central Interchange near the Rumsey Street Flyover to provide road connections to the Central area;

íP      Tunnel control buildings and ventilation buildings;

íP      Slip roads to connect the CWB to the local road system in the Wan Chai North and Causeway Bay area;

íP      Associated road lighting, road signing, traffic control and surveillance system; and

íP      Other associated works.

 

2.2.3.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1    Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3          Division of the Project Responsibility

2.3.1.     Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.     The details of individual contracts are summarized in Table2.2.

Table 2.2    Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HY/2009/17

Central íV Wan Chai Bypass (CWB) at FEHD Whitfield Depot íV Advanced piling works.

DP1

5 October 2010

HY/2009/18

Central íV Wan Chai Bypass (CWB) íV Central Interchange

DP1

21 April 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010 (Completed)

HK/2009/01

Wan Chai Development Phase II íV Central íV Wan Chai Bypass at Hong Kong Convention and Exhibition Centre íV Tunnel Works

 

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II íV Central íV Wan Chai Bypass at Wan Chai East(CWB Tunnel)

DP1

26 April 2011

HY/2009/15

Central-Wanchai Bypass íV Tunnel (Causeway Bay Typhoon Shelter Section)

DP1,DP3

13 July 2011

HY/2009/19

Central íV Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

HK/2012/08

Wan Chai Development Phase II- Central-Wan Chai Bypass at Wan Chai West

DP1,DP2, DP3

10 March 2014

HY/2010/08

Central- Wanchai Bypass Tunnel íV Tunnel (Slip Road 8)

DP1, DP2, DP3

21 March 2013

HY/2011/08

Central - Wan Chai Bypass (CWB) íVTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

DP1

To be commenced tentatively on 4th quarter in 2014.

 

2.4          Project Organization and Contact Personnel

2.4.1.     Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.     The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

EngineeríŽs Representative for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

EngineeríŽs Representative for CWB

Principal Resident Engineer

Mr. Peter Poon

3922 3388

3912 3010

Lam Woo & CO., LTD.

Contractor under Contract no. HY/2009/17

General Manager

Mr. Thomas Tang

6111 5351

2566 7522

ContractoríŽs Representative

Mr. Chung Man Shek

2566 4866

Site Agent

Mr. Tong Au

9725 5874

Environmental Officer

Dr. Priscilla Choy

9161 7287

Environmental Supervisor

Mr. Tam Chun Pong

6461 3062

Chun Wo íV Leader Joint Venture

Contractor under Contract no. HK/2009/01

Site Agent

Mr. Simon Liu

2162 9909

2634 1626

Construction  Manager

Mr. Terry Wong

9757 9846

Deputy Site Agent

Mr. Andy Yu

9648 4896

Construction Manager

Mr. Wyman Wong

9627 2467

Construction Manager

Mr. Jack Chu

9775 2467

Environmental Officer

Ms. Wendy Ng

9103 2370

Assistant Environmental Engineer

Ms. Connie Chan

9047 6148

Chun Wo íV CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Site Agent

Mr. K.K. Yuen

3658-3002

2827 9996

Project Manager

Mr. Alfred Leung

3658-3022

Quality & Environmental Manager

(Environmental Officer)

Mr. C.P. Ho

3658-3000

Chun Wo - CRGL - MBEC Joint Venture

 

Contractor under Contract no. HY/2009/19

Project Manager

Mr. David Lau

3758 8879

2570 8013

Site Agent

Mr. Paul Yu

9456 9819

Environmental Manager /

Environmental Officer

Mr. M.H. Isa

9884 0810

Environmental Engineer

Mr. Calvin Leung

9286 9208

Construction Manager (Marine)

Mr. William Luk

9610 1101

Construction Manager

(Land)

Mr. Patrick Cheung

9643 3012

Construction Manager

(Land)

Mr. Eric Fong

6191 9337

Operation Manager (Land)

Mr. Yung Kwok Wah

9834 1010

Leighton Contractors (Asia) Limited

Contractor under Contract no. HY/2009/18

Site Agent

Mr. Desmond Sze

2214 7700

2140 6799

Deputy Site Agent

Mr. Roger Wong

2214 7703

Environmental Officer

Ms. Lighting Chan

2823 1161

Environmental Engineer

Mr. David Hung

2214 7721

Assistant Environmental Engineer

Mr. Penny Yiu

2214 7738

Environmental Supervisor

Mr. K. P. Lai

6461 4660

Environmental Supervisor

Mr. Ray Cheng

2214 7742

Environmental Supervisor

Mr. K. W. Lee

6461 4623

Environmental Supervisor

Mr. Dorothy Shing

2214 7705

Environmental Supervisor

Mr. C. Y. Au Yeung

6461 8631

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

Mr. K C Cheung

2823 7813

2865 5229

Site Manager

Mr. J.H. Chen

3557 6368

2566 2192

ContractoríŽs Representative

Mr. Gene Cheung

3557 6395

Head of construction

Mr. Roger Cheung

3557 6371

Environmental Officer

Mr. Andy Mak

3557 6215

Environmental Supervisor

Ms. Esther Choi

35576348

Gammon -Leader JV

Contractor under Contract no. HK/2010/06

Project Manager

Mr. Paul Lui

9095 7922

2529 2880

Site Agent

Mr. Eric Yip

2529 2068

Environmental Officer

Mr. Clement Pang

9481 6024

Environmental Supervisor

Mr. Jacky Cheung

9735 9200

China State- Leader JV

Contractor under Contract no. HK/2012/08

Project Director

Mr. Andrew TSE

9137 1811

2877 1522

Project Manager

Mr. Victor WU

9193 8871

Deputy Project Manager

Mr. George CHEUNG

9268 1918

Site Agent

Mr. Paul LUI

9095 7922

Environmental Officer

Mr. James MA

9130 9549

Environmental Supervisor

Mr. Ching Man, CHAN

6050 4919

China State

Contractor under Contract no.HY/2010/08

Project Director

Cheung Kit Cheung

3557 6399

 

2566 8061

Project Manager

Chan Ying Lun

9812 0592

Deputy Project Manager

Chris Leung

3467 4299

Site Agent

Dr. Dave Chan

3467 4277

Environmental Officer

Mr. C.M. Wong

3557 6464

Environmental Supervisor

Mr. Louis Lam Tsz Kwan

3557 6470

Leighton Joint Venture

Contractor under Contract no. HY/2011/08

Project Manager

Paul Evans

2823 1111

21406799

Site Agent

Colman Wong

9730 0806

Environmental Officer

David Hung

9765 6151

Environmental Supervisor

Penny Yiu

2214 7738

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3465 2888

3465 2899

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

 

 

 

 

 

 

 

 

 

 

2.4.3.     In this reporting month, the principal work activities of individual contracts are included as follows:

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A

íP          Excavation of trial pit

íP          Transplanting of trees

íP          Drainage works

íP          Tunnel works including scaffolding erection, excavation, OHVD installation, roadside barriers, top and base slab construction

íP          Trough structure construction and associated drilling and grouting

íP          Road works

íP          Bridges construction

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

íP          Stage 1 construction of tunnel structures

íP          Stage 2 installation of pre-bored H-piles

íP          Stage 2 installation of sheet pile at exhaust duct area

íP          Stage 2 installation of dewatering well

íP          Stage 2 excavation and ELS works

íP          Stage 2 tunnel structure works

íP          Demolition of HKCEC pump house (Kiu Lok Portion)

íP          Demolition of 10 nos. of pump cells at Convention Avenue

íP          Stage 3 construction of D-wall.

íP          Stage 3 installation of pre-bored H-piles. 

íP          Discharge cooling main laying works for BI, BG & B

íP          S8B and S9 saltwater main laying works

íP          Sewage works along Fenwick Pier Street

íP          Construction of proposed box culvert

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009                                     

íP          The backfilling work for tunnel portion 1

íP          Loading transfer of all utility bridges

íP          Dismantling of  ELS

íP          D-Wall trimming works

íP          Excavation for Tunnel Portion 2

íP          Installation of dewatering system

íP          Bored pile PS30, PC31 and PS32

íP          Excavation of PS31

íP          Preparation works for resuming D-Wall construction

 

 

 

Contract no. HY/2009/15 - Central-Wanchai Bypass íV Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

 

íP          Post tunnel construction at TS1 and TS2

íP          Mined Tunnel drill-and-break works at East and West Portal

íP          Underwater Cutting of Temporary Diaphragm Walls at TS4 and TPCWAE

íP          Permanent lining structure at West Portal of Mined Tunnel

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

íP          Road works at Watson Road

íP          Bored piling (Land)

íP          Removal/ Installation of strut at ELS

íP          Construction of Dolphin Cap

íP          ELS for Cut &Cover Tunnel and EVB

íP          Excavation of ELS continue

íP          Laying of 1350f pipe

íP          Pre-bored H-pile for Admin. Building continue

íP          Parapet construction continue

íP          Construction of Bridge E

íP          Construction of Bride F4 and F5

íP          Construction of Pump Sump E

íP          Installation of Noise Barrier/enclosure

íP          Modification of existing crosshead at Pier 17-18

íP          IECL Road modification and removal of Median Barrier

íP          Construction of Column F2B

íP          Construction of Pile Cap F1B

íP          Laying of asphalt on Bridge Deck

 

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

íP          Cross wall sealing

íP          Concreting of turret openings

íP          Sealing of turrets

 

Contract no. HK/2012/08 íV Wan Chai Development Phase II íV Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009B

íP          Diaphragm wall construction

íP          Bored Pile Construction

 

 

 

 

 

 

 

Contract no. HY/2010/08 íVCentral - Wan Chai Bypass (CWB) íVTunnel (Slip Road 8) under FEP-10/364/2009B

íP          Tree & root pruning works

íP          Tree transplanting works,

íP          Tree works within off-site nursery compound,

íP          Drainage improvement works,

íP          Sheet piling works,

íP          Excavation and Lateral Support for U-structure,

íP          Erection of noise absorption sheetings,

íP          Pipe piling, ground pre-treatment, pre-boring works & jet grouting works,

íP          Utility diversion,

íP          Construction of Bowling Green Office &

íP          Temporary Traffic Arrangement & paving works for Victoria Park Road.

 

Contract no. HY/2011/08 íVCentral - Wan Chai Bypass (CWB) íVTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

íP          No physical construction activity on site

 

 


2.4.4.     In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

Contract no. HY/2009/18 íV Central íV Wan Chai Bypass (CWB) íV Central Interchange under FEP-05/364/2009/A

íP          Excavation of trial pit

íP          Transplanting of trees

íP          Drainage works

íP          Tunnel works including scaffolding erection, excavation, OHVD installation, roadside barriers, top and base slab construction, extract sheet pile, waterproofing and backfill

íP          Trough structure construction and associated drilling and grouting

íP          Road works

íP          Bridges construction

 

Contract no. HK/2009/01 íV Wan Chai Development Phase II íV Central íV Wan Chai Bypass at Hong Kong Convention and Exhibition Centre íV Tunnel Works under FEP-02/364/2009

íP          Stage 1 construction of tunnel structures

íP          Stage 2 excavation works 

íP          Stage 3 excavation works

íP          Waterworks

 

Contract no. HK/2009/02 íV Wan Chai Development Phase II íV Central íV Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

íP          Backfilling works to Tunnel Portion 1.

íP          Piezometer installation and commence pump test

íP          Installation of ELS at Strut S1 Level.

íP          Excavation to Strut S2 Level

íP          Bored pile construction.

íP          D-Wall construction works.

íP          Demolition of HHR Flyover Approach Ramp

 

Contract no. HY/2009/15 íV Central-Wanchai Bypass íV Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

íP          Post tunnel construction at TS1 and TS2

íP          Mined Tunnel drill-and-break works at East and West Portal

íP          Underwater cutting of Temporary Diaphragm Walls at TS4 and TPCWAE

íP          Permanent lining structure at West Portal of Mined Tunnel

 

 

 

 

 

 

Contract no. HY/2009/19 íV Central íV Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

íP          Road works at Watson Road

íP          Bored piling (Land)

íP          Removal/ Installation of strut at ELS

íP          Construction of Dolphin Cap

íP          ELS for Cut &Cover Tunnel and EVB

íP          Excavation of ELS continue

íP          Laying of 1350f pipe

íP          Pre-bored H-pile for Admin. Building continue

íP          Construction of Bridge E

íP          Construction of Bride F4 and F5

íP          Construction of Pump Sump E

íP          Installation of Noise Barrier/enclosure

íP          Modification of existing crosshead at Pier 17-18

íP          IECL Road modification and removal of Median Barrier

íP          Construction of TB Bridge

 

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

íP          Nil

 

Contract no. HK/2012/08 íV Wan Chai Development Phase II íV Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B

íP          Diaphragm wall construction

íP          Bored Pile Construction

 

Contract no. HY/2010/08 íVCentral - Wan Chai Bypass (CWB) íVTunnel (Slip Road 8) under FEP-10/364/2009B

íP          Tree & root pruning works

íP          Tree works within off-site nursery compound

íP          Drainage improvement works

íP          Sheet piling works

íP          Excavation and Lateral Support for U-structure

íP          Erection of noise absorption sheetings

íP          Pipe piling, ground pre-treatment, pre-boring works & jet grouting works

íP          Utility diversion

íP          Construction of Bowling Green Office and

íP          Waterproofing works.

 

Contract no. HY/2011/08 íV Central - Wan Chai Bypass (CWB) íVTunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

íP      Installation of starter bar on West Ventilation Building for wall construction

3         status of regulatory compliance

3.1          Status of Environmental Licensing and Permitting under the Project

3.1.1.     A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1    Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009

17 Aug 2009

Superseded

Environmental Permit

EP-364/2009/A

4 Aug 2010

Superseded

Environmental Permit

EP-364/2009/B

20 Sep 2012

Superseded

Environmental Permit

EP-364/2009/C

11 Jul 2014

Valid

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Surrendered

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

15 Nov 2010

Valid

Further Environmental Permit

FEP-05/356/2009

24 Mar 2011

Valid

Further Environmental Permit

FEP-06/356/2009

5 March 2013

Valid

Further Environmental Permit

FEP-07/356/2009

26 July 2013

Valid

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 July 2010

Surrendered

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Surrendered

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

Valid

Further Environmental Permit

FEP-08/364/2009/A

15 June 2012

Valid

Further Environmental Permit

FEP-09/364/2009/B

5 March 2013

Valid

Further Environmental Permit

FEP-10/364/2009/B

26 July 2013

Valid

Further Environmental Permit

FEP-11/364/2009/B

2 May 2014

Valid

3.1.2.     Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HY/2009/17 íV Central íV Wan Chai Bypass (CWB) at FEHD Whitfield Depot íV Advanced piling works under FEP-03/364/2009

3.1.3.     The construction works was completed and the FEP-03/364/2009 was surrendered by the Contractor on 25 April 2013.

Contract no. 04/HY/2006 íV Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

3.1.4.     The construction works was completed, and the FEP-04/HY/2006 was surrendered by the Contractor on 11 February 2011.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HK/2009/01 íV Wan Chai Development Phase II íV Central íV Wan Chai Bypass at Hong Kong Convention and Exhibition Centre íV Tunnel Works under FEP-02/364/2009

3.1.5.     Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5

Table 3.4    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

N/A

Valid

FEP-02/364/2009

21 Apr 2010

N/A

Valid

Notification of Works Under APCO

313088

06 Jan 2010

N/A

Valid

Construction Noise Permit (CNP) for non-pilling equipment

GW-RS0200-14

18 Mar 2014

21 Mar 2014 to
15 Sept 2014

Expired

GW-RS0317-14

7 Apr 2014

8 Apr 2014 to
7 Oct 2014

Valid

GW-RS0362-14

17 Apr 2014

20 Apr 2014 to 8 Oct 2014

Valid

GW-RS0381-14

 

8 Apr 2014

9 May 2014 to 11 Nov 2014

Valid

GW-RS0435-14

30 Apr 2014

13 May 2014 to 12 Nov 2014

 

Valid

GW-RS0437-14

7 May 2014

8 May 2014 to
7 Nov 2014

 

Valid

 

GW-RS0451-14

5 May 2014

12 May 2014 to 11 Nov 2014

 

Valid

 

GW-RS0462-14

17 Apr 2014

18 Apr 2014 to 17 Oct 2014

 

Valid

 

GW-RS0498-14

22 May 2014

24 May 2014 to 22 Nov 2014

 

Cancelled

 

GW-RS0875-14

21 Aug 2014

23 Aug 2014 to 21 Feb 2015

Valid