Contract No: HK/2015/01 Wanchai
Development Phase II and Central Wanchai Bypass Sampling, Field
Measurement and Testing Work (Stage 3) Environmental Permit no. EP-364/2009/E, Further Evironmental
permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B
and FEP-11/364/2009/E, FEP-12/364/2009/D Monthly Environmental Monitoring & Audit Report
- January 2017 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185
Gloucester Road, Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
13 February 2017 |
2.2 Scope of the Project
and Site Description
2.3 Division of the Project
Responsibility
2.4 Project Organization
and Contact Personnel
3 status of regulatory
compliance
3.1 Status of Environmental
Licensing and Permitting under the Project
5.2 Real Time Noise
Monitoring Results
5.3 Air Quality Monitoring
Results
6.3 Review of the Reasons
for and the Implications of Non-compliance
6.4 Summary of action taken
in the event of and follow-up on non-compliance
7 Cumulative Construction
Impact due to the Concurrent Projects
9 Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule
2 Designated Projects under this Project
Table
2.2 Details of Individual Contracts under the Project
Table
2.3 Contact Details of Key Personnel
Table
3.1 Summary of the current status on licences and/or
permits on environmental
protection pertinent to the Project
Table
3.2 Cumulative Summary of Valid Licences and Permits under
Contract no.
Table
3.3 Summary of submission status under FEP-02/364/2009
Table
3.4 Cumulative Summary of Valid Licences and Permits under
Contract no.
Table
3.5 Summary of submission status under FEP-01/364/2009
Table
3.6 Cumulative Summary of Valid Licences and Permits under
Contract no.
Table
3.7 Summary of submission status under FEP-05/364/2009/A
Table
3.8 Cumulative Summary of Valid Licences and Permits under
Contract no.
Table
3.9 Summary of submission status under FEP-06/364/2009/A
Table 3.10 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.11 Summary of submission status under
FEP-07/364/2009/D
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.13 Summary of
submission status under FEP-12/364/2009/D
Table 3.14 Cumulative Summary of Valid
License and Permits under Contract no. HY/2010/08
Table 3.15
Summary of submission status
under FEP-10/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HY/2011/08
Table 3.17 Summary
of submission status under FEP-11/364/2009/E
Table 4.1 Noise
Monitoring Stations
Table
4.2 Real Time Noise Monitoring Stations
Table
4.3 Air Quality Monitoring Stations
Table
5.1 Noise Monitoring Stations for Contract no. HY/2009/18
Table
5.2 Noise Monitoring Station for Contract no HK/2009/01
and HK/2009/02
Table
5.3 Noise Monitoring Stations for Contract no. HY/2009/15
Table
5.4 Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table 5.6 Noise Monitoring Stations for Contract no.
HY/2011/08
Table
5.7 Real Time Noise Monitoring Stations for Contract no.
HY/2009/19
Table
5.8 Real Time Noise Monitoring Stations for Contract no.
HY/2011/08
Table
5.9 Air Quality Monitoring Station for Contract no.
HY/2009/18
Table
5.10 Air
Quality Monitoring Station for Contract no. HK/2009/01
Table
5.11 Air
Quality Monitoring Station for Contract no. HK/2009/02
Table
5.12 Air
Quality Monitoring Stations for Contract no. HY/2009/15
Table 5.13 Air Quality Monitoring Station for Contract no.
HY/2009/19
Table 5.14 Air Quality Monitoring Station for Contract no. HK/2012/08
Table 5.15 Air Quality Monitoring Stations for
Contract no. HY/2010/08
Table
5.16 Air Quality Monitoring Stations for Contract no.
HY/2011/08
Table
5.17 Details of Waste Disposal for Contract no. HK/2009/01
Table
5.18 Details of Waste Disposal for Contract no. HK/2009/02
Table
5.19 Details of Waste Disposal for Contract no. HY/2009/18
Table 5.20 Details of Waste Disposal for Contract no. HY/2009/15
Table 5.21 Details of Waste Disposal
for Contract no. HY/2009/19
Table 5.22 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.23 Details of Waste Disposal
for Contract no. HY/2010/08
Table 5.24
Details of Waste Disposal for Contract
no. HY/2011/08
Table 8.1 Summary of
Environmental Inspections for Contract no. HY/2009/15
Table 8.2 Summary
of Environmental Inspections for Contract no. HY/2009/18
Table 8.3 Summary of
Environmental Inspections for Contract no. HY/2009/19
Table 8.4 Summary of
Environmental Inspections for Contract no. HK/2009/01
Table
8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.6 Summary of
Environmental Inspections for Contract no. HK/2012/08
Table 8.7 Summary of Environmental Inspections for
Contract no. HY/2010/08
Table 8.8 Summary of
Environmental Inspections for Contract no. HY/2011/08 (NOT USED)
Table
9.1 Cumulative Statistics on Complaints
Table
9.2 Cumulative Statistics on Successful Prosecutions
Table
10.1 Summary of Key Construction Activities of Individual
Contract(s) to be
commenced in Coming Reporting Month
LIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit
Level
Appendix 4.2 Copies of
Calibration Certificates
Appendix
5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix
5.2 Noise
Monitoring Results and Graphical Presentations
Appendix
5.3 Air
Quality Monitoring Results and Graphical Presentations
Appendix 5.4 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of
Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction
Programme of Individual Contracts
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
·
Drainage
works
·
Road
works
·
Landscaping
works
·
Modification
and Construction of Sign Gantries / Traffic Signs
·
Maintenance
works
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre - Tunnel Works under FEP-02/364/2009
·
Reinstatement
of amenity area
·
Road
and Drain works
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Rectification
works for cross road ducts
·
Rectification
works for cracks/joints with water leakage inside OHVD cells
·
Removal
works for ELS S2
·
Demolition
works for HHR flyover abutment
·
Backfilling
works
·
Gabion
wall was constructed.
·
Cleaning
of cross road duct & carrier drain
·
Rectification
works against water leakage and remedial works against concrete defects of the
tunnel structure
·
Excavation
of formation level.
·
Bulkhead
wall C2E breakthrough
·
Breakthrough
of bulkhead wall BW1.
·
Blinding
layer
·
Waterproofing
laying work
·
Concreting
for base slab
Removal of ELS layer
S2 & S3
·
Tunnel
wall structure
·
Demolition
of the sub-structure for Ex-WSD Salt Water Pumping Station
·
Reinstatement
works for EVA
·
Remedial
works for marine deposit at Portion 1&2
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
·
Remedial
works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and TPCWAW
·
Reinstatement
of drainage pipes and manhole at TPCWAE
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
·
Approach
ramp sheet piling, pre-bored piling
and top soil removal works
·
Hing
Fat Street modification works
·
Bridge
Demolition
·
Hotel
Carpark Reinstatement
·
Bridge
E noise barrier installation
·
IEC
noise enclosure/barrier installation
Contract no.
HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan
Chai West under FEP-12/364/2009/D
·
Grouting
·
Construction
of MVB and CWB Tunnel and Slip Road 1
·
Construction
of concrete plug
·
Excavation
and lateral support installation for CWB tunnel, Slip Road 1, Plant Room and
Exhaust Duct
·
Bulkhead
removal
·
Back-filling
at CWB tunnel
Contract no.
HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009/B
·
Tree
protection works next to existing BGO,
·
Drainage
improvement works,
·
Excavation
and Lateral Support for U-structure,
·
Utility
diversion works,
·
Retaining
wall works
·
ELS
works,
·
Construction
works for subway extension
Contract no. HY/2011/08
–Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and
Works Associated with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction
of Ventilation Buildings, inclusive of Administration Building, East
Ventilation Shaft/Building, West Ventilation Building
·
Construction
of Tunnel Thermal Barrier
·
Installation
of Electricals and Mechanicals
·
Installation
of Tunnel Features
Noise Monitoring
Air Quality Monitoring
The 24hr TSP monitoring at CMA1b were rescheduled
from 03 and 26 January to 04 and 27 January 2017 respectively
The 24hr TSP monitoring at CMA4a were rescheduled
from 09 and 20 January 2017 to 10 and 21 January 2017 respectively
The 24hr TSP monitoring at MA1e were rescheduled
from 09 and 20 January 2017 to 11 and 21 January 2017 respectively.
Complaints, Notifications of Summons and Successful
Prosecutions
ET confirmed with the Resident Site Staff that
concreting of tunnel structure was conducted under Contract HY/2010/08 at
Temporary Reclamation Area TS3 between 1900hrs and 2000hrs on 10 January 2017.
Total 3 nos. of Lorry Mounted Concrete Pumps and 6
nos. of Concrete Lorry Mixers were operated at TS3 while temporary noise
barrier was provided for 2 nos. of the operating Lorry Mounted Concrete Pumps
and 4 nos. of the operating Concrete Lorry Mixers. Total 1 no. of Concrete
Lorry Mixer was at stand-by within TS3 Works area.
Concreting of tunnel structure was conducted under
Contract HY/2010/08 at Temporary Reclamation Area TS3 between 2000hrs and
2030hrs 10 January 2017.Total 2 nos. of Lorry Mounted Concrete Pump and 4 nos.
of Concrete Lorry Mixers were operated at TS3 while temporary noise barrier was
provided for 1 no. of the operating Lorry Mounted Concrete Pumps and 2 nos. of
the operating Concrete Lorry Mixers. Total 1 no. of Concrete Lorry Mixer was at
stand-by within TS3 Works area.
Concreting of tunnel structure was conducted under
Contract HY/2010/08 at Temporary Reclamation Area TS3 between 2030hrs and
2300hrs 10 January 2017. Total 1 no. of Lorry Mounted Concrete Pump and 2 nos.
of Concrete Lorry Mixers were operated at TS3.
Based on the site records confirmed by RSS,
concreting of tunnel structure was conducted under Contract HY/2010/08 at
Temporary Reclamation Area TS3 between 1900hrs and 2300hrs on 10 January 2017.
From 1900hrs to 2000hrs, total 3 nos. of Lorry Mounted Concrete Pumps and 6
nos. of Concrete Lorry Mixers while temporary noise barrier was provided for 2
nos. of the operating Lorry Mounted Concrete Pumps and 4 nos. of the operating
Concrete Lorry Mixers. Total 1 no. of Concrete Lorry Mixer was at stand-by
within TS3 Works area.
From 2000hrs to 2030hrs, total 2 nos. of Lorry
Mounted Concrete Pump and 4 nos. of Concrete Lorry Mixers were operated at TS3
while temporary noise barrier was provided for 1 no. of the operating Lorry
Mounted Concrete Pumps and 2 nos. of the operating Concrete Lorry Mixers. Total
1 no. of Concrete Lorry Mixer was at stand-by within TS3 Works area.
From 2030hrs to 2300hrs, total 1 no. of Lorry
Mounted Concrete Pump and 2 nos. of Concrete Lorry Mixers were operated at TS3.
Relevant Construction Noise Permit GW-RS1232-16
(Corresponding PME Groups operated include Group M, Group K and Group H) was in
place for the construction works conducted during the above concerned periods
and based on RSS information, a designated personnel on-site was responsible
for controlling and supervising the switching between PME Groups. Meanwhile,
there is no sufficient information to conclude if the concerned PME(s)
(Concrete Lorry Mixer and Lorry Mounted Concrete Pump) deployed behind the
temporary noise barrier provided were not visible to nearby sensitive
receivers.
As multiple PME grouping under the Construction
Noise Permit are involved, the Contractor of HY/2010/08 was reminded to
strictly follow the site control system for construction works carried out
during restricted hours to ensure the PMEs deployed are in strict compliance
with relevant Construction Noise Permit. The Contractor of HY/2010/08 was also
reminded to maintain regular maintenance of the plant and equipment deployed to
avoid potential nuisance to the nearby public.
ET confirmed with the Resident Site Staff that the
concerned location was Site Exit Gate No. 6 at Expo Drive East operated and
maintained under HK/2009/02 on 22 December 2016. Site measures including
provision of wheel washing facility was implemented by the Contractor of
HK/2009/02 on the concerned date.
According to information provided by RSS, the
concerned location was Site Exit Gate No. 6 at Expo Drive East operated and
maintained under HK/2009/02 on 22 December 2016. In view of the environmental
concern, remedial measures including i) instructing all workers to conduct wheel
washing within the designated location with collection pit to prevent overflow
of washing effluent and ii) manual removal of dirt/silt by worker instead of
water flushing in case of dirt/muddy trail found on road were implemented by
the Contractor on 28 December 2016. Also, the Contractor of HK/2009/02 was
further reminded by the WDII RSS to maintain proper wheel washing facilities at
Gate No.6 and inspect regularly to ensure that all vehicles leaving the site to
public roads are free of mud.
Nevertheless, the Environmental Team further
reminded the Contractor on 04 January 2017 that site measures including i)
wheel washing operation shall be conducted at the designated location behind
the backfall to avoid overflow of washing effluent onto public road ii) any
silt/ soil deposited of the public road shall be cleared manually shall be
strictly followed and relevant remedial actions were taken by the Contractor of
HK/2009/02 on 04 January 2017.
According to site inspection conducted on 17
January 2017, the concerned site exit Gate No.6 was maintained in proper
condition, no silt/ mud deposition was observed on the public road and wheel
washing was conducted by the Contractor of HK/2009/02 at the designated
location within the construction site to avoid overflow of washing effluent
onto nearby public road.
Site Inspections and Audit
Contract no. HY/2009/18 – Central – Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
·
Drainage
works
·
Road
works
·
Landscaping
works
·
Maintenance
works
Contract
no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009
·
Reinstatement
of amenity area
·
Road
and Drain works
Contract
no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Outstanding
/defective works in Expo Drive East
·
Defective
works against water leakage to the hollow sections of the steel members and the
covers of the covered walkway at Expo Drive East
·
Rectification
works for cross road ducts
·
Rectification
works for cracks/joints with water leakage inside OHVD cells
·
Rectification
works for out of tolerance cross passage CP22
·
Removal
works for ELS S2 layer.
·
Tunnel
backfilling & construction of seawall foundation with Grade 400 rock fill.
·
Construction
of gabion wall.
·
Demolition
works for HHR flyover abutment.
·
Remedial
works of tunnel wall, base slab and OHVD.
·
General
cleaning and rectification works of OHVD, tunnel base slab, carrier drain,
cross road duct and manhole gully.
·
Rectification
works for out of tolerance cross passage CP23
·
Rebar
fixing and concreting of base slab and walls.
·
Waterproofing
membrane laying works for side walls.
·
Removal
works for ELS S2 & S3 layer.
·
Rebar
fixing and concreting of roadside barrier.
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
·
Remedial
works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and TPCWAW
·
Reinstatement
of drainage pipes and manhole at TPCWAE
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
·
Approach
ramp sheet piling, pre-bored piling
and top soil removal works
·
Hing
Fat Street modification works
·
Bridge
Demolition / Construction
·
Hotel
Carpark Reinstatement
·
Oil
Street drainage works
·
Bridge
E noise barrier installation
·
IEC
noise enclosure/barrier installation
·
Excavation
/ Construction of retaining wall
Contract no. HK/2012/08 – Wan Chai Development
Phase II – Central- Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D
·
Grouting
·
Construction
of MVB and CWB Tunnel and Slip Road 1
·
Construction
of concrete plug
·
Excavation
and lateral support installation for CWB tunnel, Slip Road 1, Plant Room and
Exhaust Duct
·
Bulkhead
removal
·
Back-filling
at CWB tunnel
Contract no. HY/2010/08 –Central - Wan Chai Bypass
(CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009
·
Tree
protection works next to existing BGO,
·
Drainage
improvement works,
·
Excavation
and Lateral Support for U-structure,
·
Utility
diversion works,
·
Retaining
wall works
·
ELS
works,
·
Construction
works for subway extension
Contract no. HY/2011/08 – Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009/E
·
Construction
of Ventilation Buildings, inclusive of Administration Building, East Ventilation
Shaft/Building, West Ventilation Building
·
Construction
of Tunnel Thermal Barrier
·
Installation
of Electricals and Mechanicals
·
Installation
of Tunnel Features
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/E and
Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/D,
FEP-12/364/2009/D, FEP-10/364/2009/B and FEP-11/364/2009/E to implement the Environmental Monitoring and Audit (EM&A)
programme as stipulated in the EM&A Manual of the approved Environmental
Impact Assessment (EIA) Report for Wan Chai Development phase II and
Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the
Section 10.3 of EM&A Manual and “Environmental
Monitoring and Audit Requirements” under
Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no.
EP-364/2009/E, Further Environmental Permit (FEP) nos. FEP-01-364/2009,
FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/D, FEP-12/364/2009/D,
FEP-10/364/2009/B and FEP-11/364/2009/E during
the period 27 December
2016 to 26 January 2017.
Section 1 Introduction – details the scope and structure of the report.
Section 2 Project
Background – summarizes background and
scope of the project, site description, project organization and contact
details of key personnel during the reporting period.
Section 3 Status of Regulatory Compliance – summarizes the status of valid Environmental Permits /
Licenses during the reporting period.
Section 4 Monitoring
Requirements – summarizes all monitoring
parameters, monitoring methodology and equipment, monitoring locations,
monitoring frequency, criteria and respective event and action plan and
monitoring programmes.
Section 5 Monitoring
Results – summarizes the monitoring
results obtained in the reporting period.
Section 6 Compliance Audit – summarizes
the auditing of monitoring results, all
exceedances environmental parameters.
Section 7 Cumulative Construction Impact due
to the Concurrent Projects – summarizes the relevant cumulative
construction impact due to the concurrent activities of the concurrent Projects.
Section 8 Environmental Site Audit – summarizes the findings of weekly site inspections
undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of
summons and Prosecution – summarizes the cumulative statistics on
complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1.
“Wan Chai Development phase II and Central-Wan Chai Bypass” and
“Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called
“the Project”) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested east-west Connaught Road Central/Harcourt Road / Gloucester
Road Corridor (the Corridor) which is currently operating beyond its capacity.
The CWB will provide relief to the existing congestion along the Corridor and
cater for the anticipated growth of traffic on Hong Kong Island. Without the
CWB and its access roads, there will not be sufficient capacity to serve the
heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai
Bypass (CWB) and
Island Eastern Corridor Link (IECL) includes:
·
A
dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
·
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
·
Tunnel
control buildings and ventilation buildings;
·
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
Causeway Bay area;
·
Associated
road lighting, road signing, traffic control and surveillance system; and
·
Other
associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be
either constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further
Environmental Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre – Tunnel Works |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1,DP3 |
13 July 2011 |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai Bypass at Wan Chai
West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel – Tunnel (Slip Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars
are summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
Chun Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Manager |
Mr. Simon Liu |
2162 9909 |
2634 1626 |
Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction Manager |
Mr. Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Terry
Tsang |
6683 9394 |
|||
Environmental
Officer |
Ms. Wendy Ng
|
9803 0057 |
|||
Assistant Environmental
Engineer |
Ms. Connie Chan |
6157 7057 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827 9996 |
Project Manager |
Mr. Paul Yu |
3658 3085 |
|||
Environmental Officer |
Mr. C.P. Ho |
9191 8856 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Deputy Project Manager |
Mr. William Luk |
9456 9819 |
|||
Site Agent |
Mr. David Lau |
3758 8879 |
|||
Deputy Site Agent |
Mr. Eric Fong |
6191 9337 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
3757 8218 |
|||
Assistant Environmental Officer |
Mr. Tom Ding |
3757 8217 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214 7700 |
|
Environmental Officer |
Mr. Chris Chan |
3973 1065 |
|||
Environmental Supervisor |
Ms. Christy So |
3973 1065 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2865 5229 |
Site Manager |
Mr. Y. Huo |
3557 6368 |
2566 2192 |
||
Contractor’s
Representative |
Mr. Rex Chan |
3557 6371 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Mr. Harry Wong |
3557 6348 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N. Lai |
9137 1811 |
2877 1522 |
Project
Manager |
Mr. Eddie Chung |
9193 8871 |
|||
Site Agent |
Mr. Keith Tse |
9095 7922 |
|||
Environmental
Officer |
Mr. James MA |
9130 9549 |
|||
Environmental
Supervisor |
Mr. Y.L. Ho |
6050 4919 |
|||
China State |
Contractor under Contract no.HY/2010/08 |
Project
Director |
Chris Leung |
3467 4299 |
2566 8061 |
Site Agent |
Mr. Francis
Suen |
3467 4277 |
|||
Environmental
Officer |
Mr. Gabriel
Wong |
3557 6464 |
|||
Environmental
Supervisor |
Mr. Desmond Ho |
3557 6470 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Site Agent |
Mr. Colman Wong |
2823 1410 |
21406799 |
Environmental
Officer |
Mr. Malcolm
Leung |
3973 0850 |
|||
Environmental
Supervisor |
Ms. Christy So |
3973 1065 |
|||
Ramboll Environ Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3. In this
reporting month, the principal work activities of individual contracts are
included as follows:
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) - Central Interchange under FEP-05/364/2009/A
·
Drainage
works
·
Road
works
·
Landscaping
works
·
Modification
and Construction of Sign Gantries / Traffic Signs
·
Maintenance
works
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre - Tunnel Works under FEP-02/364/2009
·
Reinstatement
of amenity area
·
Road
and Drain works
Contract
no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Wan Chai
East (CWB Tunnel) under FEP-01/364/2009
·
Rectification
works for cross road ducts
·
Rectification
works for cracks/joints with water leakage inside OHVD cells
·
Removal
works for ELS S2
·
Demolition
works for HHR flyover abutment
·
Backfilling
works
·
Gabion
wall was constructed.
·
Cleaning
of cross road duct & carrier drain
·
Rectification
works against water leakage and remedial works against concrete defects of the
tunnel structure
·
Excavation
of formation level.
·
Bulkhead
wall C2E breakthrough
·
Breakthrough
of bulkhead wall BW1.
·
Blinding
layer
·
Waterproofing
laying work
·
Concreting
for base slab
Removal of ELS layer S2 & S3
·
Tunnel
wall structure
·
Demolition
of the sub-structure for Ex-WSD Salt Water Pumping Station
·
Reinstatement
works for EVA
·
Remedial
works for marine deposit at Portion 1&2
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
·
Remedial
works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and TPCWAW
·
Reinstatement
of drainage pipes and manhole at TPCWAE
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/D
·
Approach
ramp sheet piling, pre-bored piling
and top soil removal works
·
Hing
Fat Street modification works
·
Bridge
Demolition
·
Hotel
Carpark Reinstatement
·
Bridge
E noise barrier installation
·
IEC
noise enclosure/barrier installation
Contract no. HK/2012/08 – Wan Chai Development
Phase II – Central- Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D
·
Grouting
·
Construction
of MVB and CWB Tunnel and Slip Road 1
·
Construction
of concrete plug
·
Excavation
and lateral support installation for CWB tunnel, Slip Road 1, Plant Room and
Exhaust Duct
·
Bulkhead
removal
·
Back-filling
at CWB tunnel
Contract no. HY/2010/08 –Central - Wan Chai Bypass
(CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009/B
·
Tree
protection works next to existing BGO,
·
Drainage
improvement works,
·
Excavation
and Lateral Support for U-structure,
·
Utility
diversion works,
·
Retaining
wall works
·
ELS
works,
·
Construction
works for subway extension
Contract no. HY/2011/08 –Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009/E
·
Construction
of Ventilation Buildings, inclusive of Administration Building, East
Ventilation Shaft/Building, West Ventilation Building
·
Construction
of Tunnel Thermal Barrier
·
Installation
of Electricals and Mechanicals
·
Installation
of Tunnel Features
2.4.4. In coming
reporting month, the principal work activities of individual contracts are
anticipated as follows:
·
Drainage
works
·
Road
works
·
Landscaping
works
·
Maintenance
works
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre – Tunnel Works under FEP-02/364/2009
·
Reinstatement
of amenity area
·
Road
and Drain works
Contract no. HK/2009/02 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
·
Outstanding
/defective works in Expo Drive East
·
Defective
works against water leakage to the hollow sections of the steel members and the
covers of the covered walkway at Expo Drive East
·
Rectification
works for cross road ducts
·
Rectification
works for cracks/joints with water leakage inside OHVD cells
·
Rectification
works for out of tolerance cross passage CP22
·
Removal
works for ELS S2 layer.
·
Tunnel
backfilling & construction of seawall foundation with Grade 400 rock fill.
·
Construction
of gabion wall.
·
Demolition
works for HHR flyover abutment.
·
Remedial
works of tunnel wall, base slab and OHVD.
·
General
cleaning and rectification works of OHVD, tunnel base slab, carrier drain,
cross road duct and manhole gully.
·
Rectification
works for out of tolerance cross passage CP23
·
Rebar
fixing and concreting of base slab and walls.
·
Waterproofing
membrane laying works for side walls.
·
Removal
works for ELS S2 & S3 layer.
·
Rebar
fixing and concreting of roadside barrier.
Contract no.
HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
·
Remedial
works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and TPCWAW
·
Reinstatement
of drainage pipes and manhole at TPCWAE
Contract no. HY/2009/19 – Central – Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/D
·
Approach
ramp sheet piling, pre-bored piling
and top soil removal works
·
Hing
Fat Street modification works
·
Bridge
Demolition / Construction
·
Hotel
Carpark Reinstatement
·
Oil
Street drainage works
·
Bridge
E noise barrier installation
·
IEC
noise enclosure/barrier installation
·
Excavation
/ Construction of retaining wall
Contract no. HK/2012/08 – Wan Chai Development
Phase II – Central- Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D
·
Grouting
·
Construction
of MVB and CWB Tunnel and Slip Road 1
·
Construction
of concrete plug
·
Excavation
and lateral support installation for CWB tunnel, Slip Road 1, Plant Room and
Exhaust Duct
·
Bulkhead
removal
·
Back-filling
at CWB tunnel
Contract no. HY/2010/08 –Central - Wan Chai Bypass
(CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009
·
Tree
protection works next to existing BGO,
·
Drainage
improvement works,
·
Excavation
and Lateral Support for U-structure,
·
Utility
diversion works,
·
Retaining
wall works
·
ELS
works,
·
Construction
works for subway extension
Contract no. HY/2011/08 – Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009/E
·
Construction
of Ventilation Buildings, inclusive of Administration Building, East
Ventilation Shaft/Building, West Ventilation Building
·
Construction
of Tunnel Thermal Barrier
·
Installation
of Electricals and Mechanicals
·
Installation
of Tunnel Features
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary of the current status
on licences and/or permits on environmental protection pertinent to the Project
Permits and/or
Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Superseded |
Environmental Permit |
EP-364/2009/C |
11 Jul 2014 |
Superseded |
Environmental Permit |
EP-364/2009/D |
24 Nov 2015 |
Superseded |
Environmental Permit |
EP-364/2009/E |
22 Dec 2016 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further Environmental
Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Surrendered |
Further Environmental
Permit |
FEP-06/356/2009 |
5 March 2013 |
Valid |
Further Environmental
Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Surrendered |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Superseded |
|
Further Environmental Permit |
24 Nov 2015 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Surrendered |
|
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
Superseded |
Further Environmental Permit |
FEP-11/364/2009/E |
22 Dec 2016 |
Valid |
Further Environmental Permit |
FEP-12/364/2009/D |
01 Aug 2016 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 – Central – Wan Chai
Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP-04/HY/2006 was
surrendered by the Contractor on 11 February 2011.
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
3.1.5. The construction works was completed, and the FEP-08/364/2009/A was
surrendered by the Contractor on 3 October 2014.
Contract
no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009
3.1.6. Summary of the current status on
licences and/or permits on environmental protection pertinent and
submission under FEP-02/364/2009 for contract no.
HK/2009/01 are shown in Table 3.2 and Table 3.3.
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits
and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling equipment |
GW-RS0822-16 |
28 Jul 2016 |
7 Aug 2016 to 31 Jan 2017 |
Cancelled |
GW-RS1004-16 |
28 Sep 2016 |
29 Sep 2016 to 27 Mar 2017 |
Valid |
|
GW-RS1079-16 |
27 Oct 2016 |
27 Oct 2016 to 20 Apr 2017 |
Valid |
|
GW-RS1241-16 |
12 Dec 2016 |
15 Dec 2016 to 06 Jun 2017 |
Valid |
|
GW-RS1240-16 |
12 Dec 2016 |
13 Dec 2016 to 06 Jun 2017 |
Valid |
|
GW-RS1233-16 |
12 Dec 2016 |
14 Dec 2016 to 06 Jun 2017 |
Valid |
|
GW-RS1234-16 |
12 Dec 2016 |
20 Dec 2016 to 19 Jun 2017 |
Valid |
|
Discharge License |
WT00024952-2016 |
06 Jul 2016 |
31 Jul 2021 |
Valid |
WT00021138-2015 |
17 Mar 2014 |
31 Mar 2020 |
Valid |
|
Billing account under Waste Disposal
Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.3 Summary of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May 2011 |
Condition 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Condition 1.12 |
Commencement Date of Works |
20 Jun 2011 |
Condition 2.9 |
Noise Management Plan |
10 Jun 2011 |
Condition 2.11 |
Landscape Plan (Rev.4) |
8 July 2015 |
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.7. Summary of the current status on
licences and/or permits on environmental protection pertinent and
submission under FEP-01/364/2009 for contract no.
HK/2009/02 are shown in Table 3.4 and Table 3.5.
Table 3.4 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of
Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-pilling equipment |
GW-RS0803-16 |
28 Jul 2016 |
30 Jul 2016 to 27 Jan 2017 |
Cancelled |
GW-RS0926-16 |
05 Sep 2016 |
07 Sep 2016 to 04 Mar 2017 |
Cancelled |
|
GW-RS0985-16 |
19 Sep 2016 |
20 Sep 2016 to 18 Mar 2017 |
Cancelled |
|
GW-RS1047-16 |
13 Oct 2016 |
26 Oct 2016 to 25 Apr 2017 |
Valid |
|
GW-RS1140-16 |
11 Nov 2016 |
14 Nov 2016 to 09 May 2017 |
Valid |
|
GW-RS1153-16 |
17 Nov 2016 |
18 Nov 2016 to 13 May 2017 |
Cancelled |
|
GW-RS1297-16 |
15 Dec 2016 |
16 Dec 2016 to 14 June 2017 |
Valid |
|
GW-RS1305-16 |
22 Dec 2016 |
24 Dec 2016 to 13 Jun 2017 |
Valid |
|
Water Discharge
License |
WT00022295-2015 |
12 Aug 2015 |
31 July 2020 |
Valid |
WT00025276-2016 |
19 Sep 2016 |
31 July 2021 |
Valid |
|
Billing Account
under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration as
Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as
Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Dumping Permit (Type
1 – Open Sea Disposal) |
EP/MD/17-041 |
23 Jun 2016 |
01 Jul 2016 to 31 Dec 2016 |
Expired |
Table 3.5 Summary of submission status under FEP-01/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.7 and 2.8 |
Works
Schedule and Location Plan |
14 Jun 2011 |
Condition 2.6 |
Environmental
Management Organization Chart |
14 Jun 2011 |
Condition 1.12 |
Commencement
Date of Works |
21 Jun 2011 |
Condition
2.11 |
Landscape Plan (Revision B) |
20 Nov 2012 |
Condition 2.9 |
Noise Management Plan (Revision B) |
13 Jan 2012 |
Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
3.1.8. Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18