Contract
No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and
Testing Work (Stage 2) Environmental
Permit no. EP-364/2009/C, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEp-07/364/2009/a,
FEp-08/364/2009/a , FEP-09/364/2009/B, fep-10/364/2009/B and
fep-11/364/2009/B Quarterly Environmental Monitoring
and Audit Report
- september
2014 to november 2014 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
19 December
2014 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
2.5 Principal Work and Activities
4.2. Real Time Noise Monitoring Results
5.4. Review of the Reasons for and the Implications of
Non-compliance
5.5. Summary of action taken in the event of and follow-up
on non-compliance
6. Complaints, Notification of Summons
and Prosecution
7. Cumulative Construction Impact due to
the Concurrent Projects
lIST
OF TABLES
Table I Principal Work Activities for Contract no.
HY/2009/18
Table II Principal Work Activities for Contract no. HK/2009/01
Table III Principal Work Activities for Contract no. HK/2009/02
Table IV Principal
Work Activities for Contract no. HY/2009/15
Table V Principal Work Activities for Contract no. HY/2009/19
Table VI Principal Work Activities for Contract
no. HK/2010/06
Table VII Principal Work Activities for Contract
no. HK/2012/08
Table VIII Principal Work Activities for Contract
no. HY/2010/08
Table IV Principal Work Activities for Contract no. HY/2011/08
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 2.4 Principal
Work Activities for Contract no. HY/2009/18
Table 2.5 Principal
Work Activities for Contract no. HK/2009/01
Table 2.6 Principal
Work Activities for Contract no. HK/2009/02
Table 2.7 Principal
Work Activities for Contract no. HY/2009/15
Table 2.8 Principal
Work Activities for Contract no. HY/2009/19
Table 2.9 Principal Work Activities for Contract
no. HK/2010/06
Table 2.10 Principal Work Activities for Contract
no. HK/2012/08
Table 2.11 Principal
Work Activities for Contract no. HY/2010/08
Table 2.12 Principal
Work Activities for Contract no. HY/2011/08
Table 3.1 Noise
Monitoring Station
Table 3.2 Real
Time Noise Monitoring Station
Table 3.3 Air
Monitoring Stations
Table 4.1
Noise
Monitoring Station for Contract no. HY/2009/18
Table 4.2
Noise
Monitoring Stations for Contract nos. HK/2009/01 and HK/2009/02
Table 4.3
Noise
Monitoring Station for Contract nos. HY/2009/15
Table 4.4 Noise Monitoring
Stations for Contract no. HY/2009/19
Table 4.5 Real
Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.6 Air
Monitoring Stations for Contract no. HY/2009/18
Table 4.7 Air
Monitoring Stations for Contract no. HK/2009/01
Table 4.8 Air
Monitoring Station for Contract no. HK/2009/02
Table 4.9 Air
Monitoring Station for Contract no. HY/2009/15
Table 4.10 Air
Monitoring Stations for Contract no. HY/2009/19
Table 4.11 Details
of Waste Disposal for Contract no. HK/2009/01
Table 4.12 Details
of Waste Disposal for Contract no. HK/2009/02
Table 4.13 Details
of Waste Disposal for Contract no. HY/2009/18
Table 4.14 Details
of Waste Disposal for Contract no. HY/2009/15
Table 4.15 Details
of Waste Disposal for Contract no. HY/2009/19
Table
4.16 Details of Waste Disposal for Contract no.
HK/2010/06
Table 4.17 Details of Waste
Disposal for Contract no. HK/2012/08
Table
4.18 Details of Waste Disposal for
Contract no. HY/2012/08
Table 4.19 Details of Waste Disposal for Contract no. HY/2011/08
Table 6.1 Cumulative
Statistics on Complaints
Table 6.2 Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 3.1 Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix
2.1 Environmental
Mitigation Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix 4.1 Noise Monitoring Results and
Graphical Presentations
Appendix 4.2 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 4.3 Air Quality Monitoring Results
and Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 6.2 Notification of Exceedance
Appendix 8.1 Construction Programme of
Individual Contracts
EXECUTIVE
SUMMARY
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB)
- Central Interchange under FEP-05/364/2009/
Major construction activities for Contract no. HY/2009/18 have been
commenced on 21
Table I Principal Work
Activities for Contract no. HY/2009/18
September 2014 |
October 2014 |
November 2014 |
Excavation of trial pit Transplanting of trees Drainage works Tunnel works including scaffolding
erection, excavation, OHVD installation, roadside barriers, top and base slab
construction Trough structure construction and
associated drilling and grouting Road works Bridges construction |
Excavation of trial pit Transplanting of trees Drainage works Tunnel works including scaffolding
erection, excavation, OHVD installation, roadside barriers, top and base slab
construction Trough structure construction and
associated drilling and grouting Road works Bridges construction |
Excavation of trial pit Transplanting of trees Drainage works Tunnel works including scaffolding
erection, excavation, Roadside barriers, top and base slab
construction Trough structure construction and
associated drilling and grouting Road works Bridges construction |
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
Major construction activities
for Contract no. HK/2009/01 have been commenced on 25 August 2011. During this
reporting period, the principal work activities are summarized as below:
Table II Principal Work Activities for Contract no.
HK/2009/01
September 2014 |
October 2014 |
November 2014 |
Stage 1 construction of tunnel structures
Stage 2 installation of pre-bored
H-piles Stage 2 installation of sheet pile at exhaust
duct area Stage 2 installation of dewatering
well Stage 2 excavation and ELS works Stage 2 tunnel structure works Demolition of HKCEC pump house (Kiu
Lok Portion) Demolition of 10 nos. of pump cells at
Convention Avenue Stage 3 construction of D-wall. Stage 3 installation of pre-bored
H-piles. Discharge cooling main laying works
for BI, BG & B S8B and S9 saltwater main laying works
Sewage works along Fenwick Pier Street
Construction of proposed box culvert |
Stage 1 construction of tunnel
structures was continued. Stage 2 excavation and ELS
installation works was continued. Stage 2 preparation works of pumping
test was continued. Stage 2 tunnel structure works was in
progress. Demolition of HKCEC pump house (Kiu
Lok Portion) was continued. Demolition of 10 nos. of pump cells at
Convention Avenue was continued. Stage 3 installation of pre-bored
H-piles and excavation works was continued. East Bridge demolition was completed,
sheet piling and excavation works was continued. Sheet piling for Cooling Main outfall
construction zone C3-1 Enhancement Works for Multi-part
Covers P1, P3 and P4. Capping for P9 abandoned cooling main. |
Stage 1 construction of tunnel
structures was continued. Stage 2 excavation and ELS works for
construction of exhaust duct was continued. Stage 2 pumping test was completed. Demolition works at HKCEC pump house
Kiu Lok portion was completed. Demolition of 10 nos. of pump cells at
Convention Avenue was substantially completed. Stage 3 installation of pre-bored
H-piles was continued. The demolition of bulkhead wall at
Stage 2 and 3 interface was completed. Discharge cooling mainlaying works for
BI, BG & BF were continued. Construction of box culvert was
continued. Blinding layer of Bay 1 fabrication yard was cast and formwork was
subsequently carried out. 8 nos. of pile heads at Bay 1 were removed. |
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
Major construction activities
for Contract no. HK/2009/02 have been commenced on 26
Table III Principal Work
Activities for Contract no. HK/2009/02
September 2014 |
October 2014 |
November 2014 |
The backfilling work for tunnel
portion 1 Loading transfer of all utility
bridges Dismantling of ELS D-Wall trimming works Excavation for Tunnel Portion 2 Installation of dewatering system Bored pile PS30, PC31 and PS32 Excavation of PS31 Preparation works for resuming D-Wall
construction |
Backfilling work for tunnel portion 1 Excavation for Tunnel Portion 2 ELS installation at Strut Level S1 Installation of dewatering system Predrilling for bored pile
construction at the abandoned HHR Flyover Approach Ramp Bored pile Excavation of PS34 Preparation works for resuming D-Wall
construction |
Excavation & installation of ELS
at Strut S2 Level Excavation to Strut S3 Level Bored pile construction PS34, PS35,
PS36, PS37 D-Wall construction. Demolition of HHR Flyover Approach
Ramp |
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
Major construction activities
for Contract no. HY/2009/15 has been commenced on 13 July 2011. During this
reporting period, the principal work activities are summarized as below:
Table IV Principal Work
Activities for Contract no. HY/2009/15
October
2014 |
November
2014 |
|
Post tunnel construction at TS1 and
TS2 Mined Tunnel drill-and-break works at
East and West Portal Underwater Cutting of Temporary
Diaphragm Walls at TS4 and TPCWAE Permanent lining structure at West
Portal of Mined Tunnel |
Post tunnel construction at TS1 and
TS2 Mined Tunnel drill-and-break works at
East and West Portal Permanent lining structure at West
Portal of Mined Tunnel |
Mined Tunnel drill-and-break works at
East and West Portal Permanent lining structure at Mined
Tunnel |
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
Major construction activities
for Contract no. HY/2009/19 have been commenced on March 2011. During this
reporting period, the principal work activities are summarized as below:
Table V Principal Work Activities for Contract no.
HY/2009/19
September 2014 |
October 2014 |
November 2014 |
Road works at Watson Road Bored piling (Land) Removal/ Installation of strut at ELS Construction of Dolphin Cap ELS for Cut &Cover Tunnel and EVB Excavation of ELS continue Laying of 1350f pipe Pre-bored H-pile for Admin. Building
continue Parapet construction continue Construction of Bridge E Construction of Bride F4 and F5 Construction of Pump Sump E Installation of Noise
Barrier/enclosure Modification of existing crosshead at
Pier 17-18 IECL Road modification and removal of
Median Barrier Construction of Column F2B Construction of Pile Cap F1B Laying of asphalt on Bridge Deck |
Bored piling (Land) Removal/ Installation of strut at ELS Construction of Dolphin Cap ELS for Cut &Cover Tunnel and EVB Excavation of EVB continue Laying of 1350f pipe Pre-bored H-pile for Admin. Building
continue Construction of Bridge E Construction of Pump Sump E Construction of Bridge F4 and F5 Wing
Extension Installation of Noise Barrier/enclosure Modification of existing crosshead at
Pier 17-18 IECL Road modification and removal of
Median Barrier Construction of Column F2B Construction of Pile Cap F1B Abutment D12 construction |
Bored piling (Land) ELS for Cut &Cover Tunnel and EVB Excavation of EVB continue Laying of 1350 pipe Pre-bored H-pile for Admin. Building
continue Construction of Bridge E Construction of Pump Sump Construction of Bridge F4 and F5 Wing
Extension Installation of Noise
Barrier/enclosure Modification of existing crosshead at
Pier 17-18 IECL Road modification and removal of
Median Barrier Construction of Pile Cap F1B Abutment D12 construction Demolition of Hing Fat Street Slip
Road Saw cut of parapet at IEC west bound Mini-pile construction for TA2 bridge |
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
Table VI Principal Work
Activities for Contract no. HK/2010/06
September 2014 |
October 2014 |
November 2014 |
Cross wall sealing Concreting of turret openings Sealing of turrets |
Nil |
Nil |
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
Table VII Principal
Work Activities for Contract no. HK/2012/08
September 2014 |
October 2014 |
November 2014 |
Diaphragm wall construction Bored Pile Construction |
Diaphragm wall construction Bored Pile Construction |
Diaphragm wall construction Bored Pile Construction |
Contract
no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 section under
FEP-10/364/2009B
Table VIII Principal Work
Activities for Contract no. HY/2010/08
September 2014 |
October 2014 |
November 2014 |
Tree & root pruning works Tree transplanting works, Tree works within off-site nursery
compound, Drainage improvement works, Sheet piling works, Excavation and Lateral Support for
U-structure, Erection of noise absorption
sheetings, Pipe piling, ground pre-treatment,
pre-boring works & jet grouting works, Utility diversion, Construction of Bowling Green Office
& Temporary Traffic Arrangement &
paving works for Victoria Park Road. |
Tree thinning works Tree works within off-site nursery
compound, Drainage improvement works, Sheet piling works, Excavation and Lateral Support for
U-structure, Erection of noise absorption sheetings, Pipe piling & grouting works, Utility diversion works, Waterproofing works, Construction of Bowling Green Office
& Temporary Traffic Arrangement &
paving works for Victoria Park Road. |
Tree thinning works, Tree works within off-site nursery
compound, Tree transplant works, Shurbs planting works, Drainage improvement works, Sheet piling works, Excavation and Lateral Support for
U-structure, Erection of noise absorption sheeting, Pipe piling & grouting works, Utility diversion works, Waterproofing works & Construction of Bowling Green Office. |
Contract
no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
Table IV Principal Work
Activities for Contract no. HY/2011/08
September 2014 |
October 2014 |
November 2014 |
No physical construction activity on
site |
Preparation works for starter bar
installation on West Ventilation Building tunnel slab |
Drill and fix starter bars on West
Ventilation Building tunnel slab for building wall |
Noise Monitoring
Real
time Noise Monitoring
Air Quality Monitoring
No action level and no limit level
exceedances were recorded in this reporting quarter.
Complaints, Notifications of
Summons and Successful Prosecutions
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009/B to
implement the Environmental Monitoring and Audit (EM&A) programme as stipulated
in the EM&A Manual of the approved Environmental Impact Assessment (EIA)
Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register
No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of
EM&A Manual and “Environmental Monitoring and Audit Requirements”
under Particular Specification Section 27.
1.1.3. This report documents the finding of EM&A
works during the period from September 2014 to November 2014.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements – summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results – summarizes the monitoring results
obtained in the reporting period.
Section 5 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be developed
as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB)
and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately 4.5 km
in length, and tunnel approximately 3.7 km in length defined from the connection
with the existing Rumsey Street Flyover in Central, through to a connection
with the existing Island Eastern Corridor to the east of the Causeway Bay
Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street
Flyover to provide road connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road
system in the Wan Chai North and
·
Associated road lighting, road signing, traffic
control and surveillance system; and
·
Other associated works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
In
the reporting period, all the contracts were commenced and contract no.
04/HY/2006 had been completed. The details of individual contracts are
summarized in Table2.2.
Table
2.2 Details of Individual Contracts
under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel ( |
DP1 |
13 July 2011 |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
DP works under |
HY/2010/08 |
Central- Wanchai Bypass Tunnel – Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning |
DP1 |
8 October 2014 |
2.3.3.
The construction works of Contract no.
04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street under FEP-04/364/2009/A was completed, and the FEP was surrendered by
the Contractor on 11 February 2011.
2.3.4.
Construction of bored pile E3B under HY/2009/17 was confirmed
completed and the respective work area under FEP-03/364/2009 was handover and inspected
under HY/2009/19 from 19 Dec 2012 onwards.
2.3.5.
Construction works under HK/2010/06 was confirmed completed and the
respective work area under FEP-08/364/2009/A was handover and inspected under
HK/2012/08 from 22 Sep 2014 onwards.
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3.
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Chun
Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Mr. Simon Liu |
2162 9909 |
2634 1626 |
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack
Chu |
9775 2467 |
|||
Environmental
Officer |
Mr. Wendy
Ng |
9803 0057 |
|||
Environmental
Supervisor |
Mr. Connie Chan |
2162 9935 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827 9996 |
Project Manager |
Mr. Alfred Leung |
3658-3022 |
|||
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
|
9286 9208 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Desmond Sze |
2214
7700 |
2140 6799 |
Deputy Site Agent |
Mr Roger Wong |
2214
7703 |
|||
Environmental Officer |
Ms. |
2823
1161 |
|||
Environmental Engineer |
Mr. David Hung |
2214 7721 |
|||
Assistant Environmental Engineer |
Mr. Penny Yiu |
2214
7738 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ray Cheng |
22147742 |
|||
Environmental Supervisor |
Bosco Lee |
22147711 |
|||
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. K C Cheung |
2823 7813 |
2566 2192 |
Site Manager |
Mr. J.H. Chen |
3557 6368 |
|||
Contractor’s
Representative |
Mr. Gene Cheung |
3557
6395 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Ms Esther Choi |
35576348 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529
2880 |
Site
Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Clement Pang |
9481 6024 |
|||
Environmental
Supervisor |
Mr.
Jacky Cheung |
9735 9200 |
|||
|
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung
Kit Cheung |
3557
6399 |
3465 2899 |
Project
Manager |
Chan
Ying Lun |
9812
0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467
4299 |
|||
Site
Agent |
Dave
Chan |
3467
4277 |
|||
Environmental
Officer |
C.M.
Wong |
3557
6464 |
|||
Environmental
Supervisor |
Louis
Lam Tsz Kwan |
3557
6470 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Project
Manager |
Paul
Evans |
2823
1111 |
21406799 |
Site
Agent |
Colman Wong |
9730
0806 |
|||
Environmental
Officer |
David Hung |
6461
8635 |
|||
Environmental
Supervisor |
Penny Yiu |
2214
7738 |
|||
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
2.5.1.
Major construction activities for Contract no.
HY/2009/18 have been commenced on 21
Table 2.4 Principal Work Activities
for Contract no. HY/2009/18
September
2014 |
October
2014 |
November
2014 |
Excavation of trial pit
Transplanting of trees
Drainage works
Tunnel works including scaffolding erection, excavation, OHVD
installation, roadside barriers, top and base slab construction
Trough structure construction and associated drilling and grouting
Road works
Bridges construction |
Excavation of trial pit
Transplanting of trees
Drainage works
Tunnel works including scaffolding erection, excavation, OHVD
installation, roadside barriers, top and base slab construction
Trough structure construction and associated drilling and grouting
Road works
Bridges construction |
Excavation of trial pit
Transplanting of trees
Drainage works
Tunnel works including scaffolding erection, excavation,
Roadside barriers, top and base slab construction
Trough structure construction and associated drilling and grouting
Road works
Bridges construction |
2.5.2. Major
construction activities for Contract no. HK/2009/01 have been commenced on 25
August 2011. During this reporting period, the principal work activities are
summarized in Table2.5:
Table 2.5 Principal Work Activities for Contract no. HK/2009/01
September
2014 |
October
2014 |
November
2014 |
Stage 1 construction of tunnel structures
Stage 2 installation of pre-bored H-piles
Stage 2 installation of sheet pile at exhaust duct area
Stage 2 installation of dewatering well
Stage 2 excavation and ELS works
Stage 2 tunnel structure works
Demolition of HKCEC pump house (Kiu Lok Portion)
Demolition of 10 nos. of pump cells at Convention Avenue
Stage 3 construction of D-wall.
Stage 3 installation of pre-bored H-piles.
Discharge cooling main laying works for BI, BG & B
S8B and S9 saltwater main laying works
Sewage works along Fenwick Pier Street
Construction of proposed box culvert |
Stage 1 construction of tunnel structures was continued.
Stage 2 excavation and ELS installation works was continued.
Stage 2 preparation works of pumping test was continued.
Stage 2 tunnel structure works was in progress.
Demolition of HKCEC pump house (Kiu Lok Portion) was continued.
Demolition of 10 nos. of pump cells at Convention Avenue was
continued.
Stage 3 installation of pre-bored H-piles and excavation works was
continued.
East Bridge demolition was completed, sheet piling and excavation
works was continued.
Sheet piling for Cooling Main outfall construction zone C3-1
Enhancement Works for Multi-part Covers P1, P3 and P4.
Capping for P9 abandoned cooling main. |
Stage 1 construction of tunnel structures was continued.
Stage 2 excavation and ELS works for construction of exhaust duct was
continued.
Stage 2 pumping test was completed.
Demolition works at HKCEC pump house Kiu Lok portion was completed.
Demolition of 10 nos. of pump cells at Convention Avenue was
substantially completed.
Stage 3 installation of pre-bored H-piles was continued.
The demolition of bulkhead wall at Stage 2 and 3 interface was
completed.
Discharge cooling mainlaying works for BI, BG & BF were continued.
Construction of box culvert was continued. Blinding layer of Bay 1
fabrication yard was cast and formwork was subsequently carried out. 8 nos.
of pile heads at Bay 1 were removed. |
2.5.3. Major
construction activities for Contract no. HK/2009/02 have been commenced on 26
Table 2.6 Principal Work Activities for Contract no. HK/2009/02
September
2014 |
October
2014 |
November
2014 |
The backfilling work for tunnel portion 1
Loading transfer of all utility bridges
Dismantling of ELS
D-Wall trimming works
Excavation for Tunnel Portion 2
Installation of dewatering system
Bored pile PS30, PC31 and PS32
Excavation of PS31
Preparation works for resuming D-Wall construction |
Backfilling work for tunnel portion 1
Excavation for Tunnel Portion 2
ELS installation at Strut Level S1
Installation of dewatering system
Predrilling for bored pile construction at the abandoned HHR Flyover
Approach Ramp
Bored pile
Excavation of PS34
Preparation works for resuming D-Wall construction |
Excavation & installation of ELS at Strut S2 Level
Excavation to Strut S3 Level
Bored pile construction PS34, PS35, PS36, PS37
D-Wall construction.
Demolition of HHR Flyover Approach Ramp |
2.5.4. Major
construction activities for Contract no. HY/2009/15 have been commenced on 13
July 2011. During this reporting period, the principal work activities are
summarized in Table 2.7:
Table 2.7 Principal Work Activities for Contract no.
HY/2009/15
September
2014 |
October
2014 |
November
2014 |
Post tunnel construction at TS1 and TS2
Mined Tunnel drill-and-break works at East and West Portal
Underwater Cutting of Temporary Diaphragm Walls at TS4 and TPCWAE
Permanent lining structure at West Portal of Mined Tunnel |
Post tunnel construction at TS1 and TS2
Mined Tunnel drill-and-break works at East and West Portal
Permanent lining structure at West Portal of Mined Tunnel |
Mined Tunnel drill-and-break works at East and West Portal
Permanent lining structure at Mined Tunnel |
2.5.5. Major
construction activities for Contract no. HY/2009/19 have been commenced on
March 2011. During this reporting period, the principal work activities are
summarized in Table 2.8:
Table 2.8 Principal Work Activities for Contract no.
HY/2009/19
September
2014 |
October
2014 |
November
2014 |
Road works at Watson Road
Bored piling (Land)
Removal/ Installation of strut at ELS
Construction of Dolphin Cap
ELS for Cut &Cover Tunnel and EVB
Excavation of ELS continue
Laying of 1350f pipe
Pre-bored H-pile for Admin. Building continue
Parapet construction continue
Construction of Bridge E
Construction of Bride F4 and F5
Construction of Pump Sump E
Installation of Noise Barrier/enclosure
Modification of existing crosshead at Pier 17-18
IECL Road modification and removal of Median Barrier
Construction of Column F2B
Construction of Pile Cap F1B
Laying of asphalt on Bridge Deck |
Bored piling (Land)
Removal/ Installation of strut at ELS
Construction of Dolphin Cap
ELS for Cut &Cover Tunnel and EVB
Excavation of EVB continue
Laying of 1350f pipe
Pre-bored H-pile for Admin. Building continue
Construction of Bridge E
Construction of Pump Sump E
Construction of Bridge F4 and F5 Wing Extension
Installation of Noise Barrier/enclosure
Modification of existing crosshead at Pier 17-18
IECL Road modification and removal of Median Barrier
Construction of Column F2B
Construction of Pile Cap F1B
Abutment D12 construction |
Bored piling (Land)
ELS for Cut &Cover Tunnel and EVB
Excavation of EVB continue
Laying of 1350 pipe
Pre-bored H-pile for Admin. Building continue
Construction of Bridge E
Construction of Pump Sump
Construction of Bridge F4 and F5 Wing Extension
Installation of Noise Barrier/enclosure
Modification of existing crosshead at Pier 17-18
IECL Road modification and removal of Median Barrier
Construction of Pile Cap F1B
Abutment D12 construction
Demolition of Hing Fat Street Slip Road
Saw cut of parapet at IEC west bound
Mini-pile construction for TA2 bridge |
2.5.6.
Major construction activities for
Contract no. HK/2010/06 have been commenced on March 2011. During this
reporting period, the principal work activities are summarized in Table 2.9
Table 2.9 Principal Work Activities for Contract
no. HK/2010/06
September
2014 |
October
2014 |
November
2014 |
Cross wall sealing
Concreting of turret openings
Sealing of turrets |
Nil |
Nil |
Remarks: The construction works was
completed, and the FEP-08/364/2009/A was surrendered by the Contractor on 3
October 2014
2.5.7.
Major construction activities for
Contract no. HK/2012/08 have been commenced on March 2013. During the reporting
period, the principal work activities are summarized in Table 2.10
Table
2.10 Principal Work Activities for
Contract no. HK/2012/08
September
2014 |
October
2014 |
November
2014 |
Diaphragm wall construction
Bored Pile Construction |
Diaphragm wall construction
Bored Pile Construction |
Diaphragm wall construction
Bored Pile Construction |
2.5.8.
Major construction activities for Contract no.HY/2010/08 have been commenced
on March 2013. During the reporting period, the principal work activities are
summarized in Table 2.11
Table 2.11 Principal Work Activities for
Contract no. HY/2010/08
September
2014 |
October
2014 |
November
2014 |
Tree & root pruning works
Tree transplanting works,
Tree works within off-site nursery compound,
Drainage improvement works,
Sheet piling works,
Excavation and Lateral Support for U-structure,
Erection of noise absorption sheetings,
Pipe piling, ground pre-treatment, pre-boring works & jet grouting
works,
Utility diversion,
Construction of Bowling Green Office &
Temporary Traffic Arrangement & paving works for Victoria Park
Road. |
Tree thinning works
Tree works within off-site nursery compound,
Drainage improvement works,
Sheet piling works,
Excavation and Lateral Support for U-structure,
Erection of noise absorption sheetings,
Pipe piling & grouting works,
Utility diversion works,
Waterproofing works,
Construction of Bowling Green Office &
Temporary Traffic Arrangement & paving works for Victoria Park
Road. |
Tree thinning works,
Tree works within off-site nursery compound,
Tree transplant works,
Shurbs planting works,
Drainage improvement works,
Sheet piling works,
Excavation and Lateral Support for U-structure,
Erection of noise absorption sheeting,
Pipe piling & grouting works,
Utility diversion works,
Waterproofing works &
Construction of Bowling Green Office. |
2.5.9.
Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009B
Table 2.12 Principal Work Activities for Contract no. HY/2011/08
September
2014 |
October
2014 |
November
2014 |
No physical construction activity on site |
Preparation works for starter bar installation on West Ventilation
Building tunnel slab |
Drill and fix starter bars on West Ventilation Building tunnel slab
for building wall |
2.5.10.
Implementation status of the recommended mitigation measures
during this reporting period is presented in Appendix 2.1.
3.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
3.1 and Figure 3.1. Appendix 3.1 shows
the established Action/Limit Levels for the monitoring works.
Table 3.1 Noise Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun
Area |
M3a |
Tung Lo Wan
Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark 1: Location
ID has been updated from M7 to M8 for City Hall
* Remark 2: M7e has
become a reference station starting from 7 Aug 2012
Real time Noise Monitoring Stations