Contract
No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and
Testing Work (Stage 2) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEp-07/364/2009/a and
FEp-08/364/2009/a Quarterly Environmental Monitoring
and Audit Report
- June to August 2012 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre
Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
                         Raymond Dai Environmental Team Leader |
|
DATE: |
|
27 September
2012 |
1.1    Scope
of the Report
1.2    Structure
of the Report
2.   Project
Background
2.1    Background
2.2    Scope
of the Project and Site Description.
2.3    Division
of the Project Responsibility
2.4    Project
Organization and Contact Personnel
2.5    Principal
Work and Activities
3.   Monitoring
Requirements
3.1.    Noise
Monitoring
3.2.    Air Monitoring
4.   Monitoring
Results
4.1.    Noise
Monitoring Results
4.2.    Real Time Noise Monitoring Results
4.3.    Air Monitoring Results
4.4.    Waste
Monitoring Results
5.1.    Noise
Monitoring
5.2.    Air
Monitoring
5.3.    Site
Audit
5.4.    Review
of the Reasons for and the Implications of Non-compliance
5.5.    Summary
of action taken in the event of and follow-up on non-compliance
6.   Complaints,
Notification of Summons and Prosecution
7.   Cumulative
Construction Impact due to the Concurrent Projects
lIST
OF TABLES
Table I      Principal Work Activities for Contract no.
HY/2009/17
Table II     Principal Work Activities for Contract no. HY/2009/18
Table III     Principal Work Activities for Contract no. HK/2009/01
Table IV     Principal Work Activities for Contract no. HK/2009/02
Table V     Principal Work Activities for Contract no. HY/2009/15
Table VI     Principal Work Activities for Contract no. HY/2009/19
Table 2.1    Schedule 2 Designated Projects under this Project
Table 2.2   Details of Individual Contracts under the Project
Table 2.3   Contact Details of Key Personnel
Table 2.4    Principal Work Activities for Contract no. HY/2009/17
Table 2.5    Principal Work Activities for Contract no. HY/2009/18
Table 2.6    Principal Work Activities for Contract no. HK/2009/01
Table 2.7    Principal Work Activities for Contract no. HK/2009/02
Table 2.8    Principal Work Activities for Contract no. HY/2009/15
Table 2.9    Principal Work Activities for Contract no. HY/2009/19
Table 3.1   Noise Monitoring Station
Table 3.2   Real Time Noise Monitoring Station
Table 3.3   Air Monitoring Stations
Table 4.1    Noise Monitoring Stations for Contract no. HY/2009/17
Table 4.2    Noise Monitoring Station for Contract no. HY/2009/18
Table 4.3    Noise Monitoring Stations for Contract nos. HK/2009/01 and
HK/2009/02
Table 4.4    Noise Monitoring Station for Contract nos. HY/2009/15
Table 4.5    Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.6   Real Time Noise Monitoring Station for Contract no.
HY/2009/17
Table 4.7   Real Time Noise Monitoring Stations for Contract no.
HY/2009/19
Table 4.8    Air Monitoring Stations for Contract no. HY/2009/17
Table 4.7    Air Monitoring Stations for Contract no. HY/2009/18
Table 4.10   Air Monitoring Stations for Contract no. HK/2009/01
Table 4.11   Air Monitoring Station for Contract no. HK/2009/02
Table 4.12   Air Monitoring Station for Contract no. HY/2009/15
Table 4.13   Air Monitoring Stations for Contract no. HY/2009/19
Table 4.14  Details of Waste Disposal for Contract no. HY/2009/17
Table 4.15  Details of Waste Disposal for Contract no. HK/2009/01
Table 4.16  Details of Waste Disposal for Contract no. HK/2009/02
Table 4.17  Details of Waste Disposal for Contract no. HY/2009/18
Table 4.18  Details of Waste Disposal for Contract no. HY/2009/15
Table 4.19  Details of Waste Disposal for Contract no. HY/2009/19
Table 6.1   Cumulative Statistics on Complaints
Table 6.2   Cumulative Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure 2.1     Project Layout
Figure
2.2     Project Organization Chart
Figure 3.1      Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix
2.1   Environmental
Mitigation Implementation Schedule
Appendix 3.1   Action and Limit Level
Appendix
4.1   Noise
Monitoring Results and Graphical Presentations
Appendix 4.2   Real-time Noise Monitoring
Results and Graphical Presentations
Appendix
4.3   Air
Quality Monitoring Results and Graphical Presentations
Appendix 5.1   Event Action Plans
Appendix 6.1   Complaint Log
Appendix
6.2   Notification of Exceedance
Appendix 8.1   Construction Programme of
Individual Contracts
EXECUTIVE SUMMARY
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield
Depot - Advanced piling works under FEP-03/364/2009
Major construction activities for
Contract no. HK/2009/17 have been commenced on 5 October 2010. During this
reporting period, the principal work activities for Contract no. HY/2009/17 are
summarized as below:
Table I     Principal
Work Activities for Contract no. HY/2009/17
June 2012 |
July 2012 |
August 2012 |
ELS works for basement construction for pile cap
construction |
ELS works for basement construction for pile cap
construction |
ELS works for basement construction for pile cap
construction |
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) 
- Central Interchange under FEP-05/364/2009/A
Table
II    Principal Work Activities for
Contract no. HY/2009/18
June 2012 |
July 2012 |
August 2012 |
Trial Pit
Instrumentation and
monitoring works
Drainage works
Site investigation and
pre-drilling works
D-wall construction
Sheet piling
Grout curtain
Tree Transplantation
Earthwork
Preparation works in
existing tunnel
Stitch coring
Approach ramp structure
works
Top down slab
Road works
Tunnel works
Excavation and Lateral
Support |
Excavation of trial pit
Transplanting of trees
Hoarding erection and
modification
Installation of couplers,
UU detection, trial trench, pre-drilling
Site investigation and
pre-drill works
Excavation
Diaphragm wall construction
Sheet Piling
Drainage works
Tunnel works
Top down slab construction
Trough structure
construction and associated drilling and grouting
Road works
OHVD installation
Site access set up at
Portion 6
Pumping test |
Excavation of trial pit
Transplanting of trees
Hoarding erection and
modification
Installation of couplers,
UU detection, trial trench, pre-drilling
Site investigation and
pre-drill works
Excavation
Diaphragm wall construction
Sheet Piling
Drainage works
Tunnel works
Top down slab construction
Trough structure
construction and associated drilling and grouting
Road works
OHVD installation
Site access set up at
Portion 6
TTA near Gate 3
Pumping test |
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre - Tunnel Works under FEP-02/364/2009
Major construction activities for
Contract no. HK/2009/01 have been commenced on 25 August 2011. During this
reporting period, the principal work activities are summarized as below:
Table III    Principal Work
Activities for Contract no. HK/2009/01
June 2012 |
July 2012 |
August 2012 |
Diaphragm wall construction
works for CWB (Stage2)
Pre-drilling works for CWB
(Stage2)
Pre-bored H piling works
for SCL
Excavation for CWB top slab
(Bay1  Bay 4)
Waterproofing works for CWB
top slab (Bay 1  Bay 4)
Excavation and installation
of shoring system for construction of exhaust duct structure
Excavation for SCL top slab
construction works
Construction of SCL top
slab (Bay 3)
Trimming of SCL Diaphragm
wall head |
Diaphragm wall construction
works for CWB (Stage2)
Pre-drilling works for CWB
(Stage 2)
Waterproofing works for CWB
top slab (Bay 1  Bay 4)
Backfilling works for CWB
top slab
Excavation and installation
of shoring system for construction of exhaust duct structure
Construction of exhaust
duct (Bay 2)
Trimming of SCL Diaphragm
wall head (Bay 3)
Construction of SCL top
slab (Bay 3)
Remedial works for SCL
Diaphragm Wall
Load test on SCL pre-bored
H-piles |
Diaphragm wall construction
works for CWB (Stage2) at the northern side
Pre-drilling works for CWB
(Stage 2)
Construction of exhaust
duct structure (Bay 1 and Bay 2) including waterproofing and protective
screeding
Trimming of SCL Diaphragm
wall head
Construction of SCL top
slab (Bay 2 & Bay 3)
Remedial works for SCL
Diaphragm Wall |
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
Major construction activities for
Contract no. HK/2009/02 have been commenced on 26 April 2011. During this reporting period, the principal work
activities are summarized as below:
Table IV    Principal Work
Activities for Contract no. HK/2009/02
June 2012 |
July 2012 |
August 2012 |
Deep excavation works. The excavation level has reached -9.0mPD to
-9.8mPD on the eastern and western portion of the site respectively.
Tunnel Pre-drill work of
bored pile at tunnel portion 3 & 4 area.
Trench excavation for guide
wall of Diaphragm wall at tunnel portion 3 & 4 area.
Guide wall construction for
Diaphragm wall at tunnel portion 3 & 4 area.
Bored pile PC34 and PC35.
Pre-drill for bored pile
and diaphragm wall.
Handover of Government Helipad
at Tunnel Portion 3&4 and initial Survey at ex-helipad.
Half bay of bulkhead wall
construction |
Deep excavation works to
-12.0mPD and -9.8mPD on the eastern and western portion of the site respectively
Tunnel bored pile works at
tunnel portion 3 & 4 area
Tunnel Pre-drill work of
bored pile at tunnel portion 3 & 4 area
Trench excavation for guide
wall of Diaphragm wall at tunnel portion 3 & 4 area
Guide wall construction for
Eastern Bulkhead Diaphragm wall at tunnel portion 3 & 4 area |
Deep excavation works
reached -19mPD to -18mPD on the eastern and western portion of the site respectively
Pre-drill holes
Guide wall construction for
Eastern Bulkhead Diaphragm wall at tunnel portion 3 & 4 area
Silo tank, desander and bar
bending yard setup for diaphragm wall construction at existing helipad
Diaphragm wall construction
of panel P110 |
Contract no. HY/2009/15 - Central-Wanchai Bypass  
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
Major construction activities for
Contract no. HY/2009/15 has been commenced on 13 July 2011. During this
reporting period, the principal work activities are summarized as below:
Table V    Principal Work Activities for Contract no.
HY/2009/15
June 2012 |
July 2012 |
August 2012 |
Diaphragm wall construction works at TS4
ELS works at TPCWAE
Cut and cover tunnel construction at TS1
Night time protection works at CHT
Cut off wall preparation works at Hung Hing Road
and POC |
Diaphragm wall construction works at TS4
Rock breaking works at TPCWAE
Removal of temporary reclamation at TS1
Dismantling of scaffold in tunnel box at TS1
Mined tunnel preparation works at TPCWAE |
Diaphragm wall construction works at TS4
Rock breaking works at TPCWAE
Removal of temporary reclamation at TS1
Dismantling of scaffold in tunnel box at TS1
Preparation works for bored piling at eastern
breakwater
Mined tunnel preparation works at TPCWAE |
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
Major construction activities for
Contract no. HY/2009/19 have been commenced on March 2011. During this
reporting period, the principal work activities are summarized as below:
Table VI    Principal Work Activities for Contract no.
HY/2009/19
June 2012 |
July 2012 |
August 2012 |
Road works at Watson Road
Fabrication of bored piling
platform
Bored piling (Land)
Ground contamination
assessment
Pre-drilling works for
bored pile and Diaphragm wall
D-wall Construction (North
& South Section)
Guide wall construction for
D-wall / Barette at North side
Construction works for Box
Culvert T
Construct ion of socket-H
pile for Marine works
Construction of pre-bored
H-pile works for Culvert U
Installation of sheet pile
at D9 location
Construction of pile cap |
Road works at Watson Road
Fabrication of bored piling
platform
Bored piling (Land)
Ground contamination assessment
Pre-drilling works for
bored pile and Diaphragm wall
D-wall Construction (North
& South Section)
Guide wall construction for
D-wall / Barette at North side
Construct ion of socket-H
pile
Construction of pre-bored
H-pile works for Culvert U |
Road works at Watson Road
Bored piling (Land)
Ground contamination assessment
Pre-drilling works for
bored pile and Diaphragm wall
D-wall Construction (North
& South Section)
Guide wall construction for
D-wall / Barette at North side
Construction works for Box
Culvert T
Marine Piling
Construct ion of socket-H
pile
Construction of pre-bored
H-pile works for Culvert U
Construction of 1500f drainage pipe
Construction of Pile cap
& column (Land) |
Table VII   Principal Work Activities for Contract no. HK/2010/06
June 2012 |
July 2012 |
August 2012 |
Construction of pre-cast unit in China |
Construction of pre-cast unit in China |
Construction of pre-cast unit in China |
Noise Monitoring
 /span>
Air Quality Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A and FEP-08/364/2009/A to
implement the Environmental Monitoring and Audit (EM&A) programme as stipulated
in the EM&A Manual of the approved Environmental Impact Assessment (EIA)
Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register
No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of
EM&A Manual and  /span>Environmental Monitoring and Audit Requirements 
under Particular Specification Section 27.
1.1.3.
This
report documents the finding of EM&A works during the period from June to August 2012.
Section 1     Introduction  details the scope and structure of the
report.
Section 2     Project Background  summarizes background
and scope of the project, site description, project organization and contact
details of key personnel during the reporting period.
Section 3     Monitoring Requirements  summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4     Monitoring Results  summarizes the
monitoring results obtained in the reporting period.
Section 5     Compliance Audit  summarizes the auditing of
monitoring results, all exceedances environmental parameters.
Section 6     Complaints, Notification of summons and
Prosecution  summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 7     Cumulative Construction Impact due to the
Concurrent Projects  summarizes the relevant cumulative
construction impact due to the concurrent activities of the concurrent Projects.
Section 8     Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass and “Central-Wan Chai
Bypass and Island Eastern Corridor Link (hereafter called “the Project  are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern
Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on
31 August 2001 and 11 December 2008 respectively.
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested east-west Connaught Road Central/Harcourt Road / Gloucester Road
Corridor (the Corridor) which is currently operating beyond its capacity. The
CWB will provide relief to the existing congestion along the Corridor and cater
for the anticipated growth of traffic on Hong Kong Island. Without the CWB and
its access roads, there will not be sufficient capacity to serve the heavy
traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central  Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure
2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island
Eastern Corridor Link (IECL) includes:
 -
A dual three-lane trunk road, approximately 4.5 km
in length, and tunnel approximately 3.7 km in length defined from the
connection with the existing Rumsey Street Flyover in Central, through to a
connection with the existing Island Eastern Corridor to the east of the
Causeway Bay Typhoon Shelter (CBTS);
 -
The Central Interchange near the Rumsey Street
Flyover to provide road connections to the Central area;
 -
Tunnel control buildings and ventilation buildings;
 -
Slip roads to connect the CWB to the local road
system in the Wan Chai North and Causeway Bay area;
 -
Associated road lighting, road signing, traffic
control and surveillance system; and
 -
Other associated works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1   Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual contracts
will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are
sub-divided accordingly to facilitate the implementation of EM&A programme
and to streamline the EM&A reporting for individual FEP holders
correspondingly.
2.3.2.
In
the reporting period, all the contracts were commenced and contract no.
04/HY/2006 had been completed. The details of individual contracts are
summarized in Table2.2.
Table
2.2  Details of Individual Contracts
under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central  Wan Chai Bypass (CWB)  Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre  Tunnel Works |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1 |
13 July 2011 |
HY/2009/19 |
Central  Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For
the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table 2.3  Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Lam Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
Project Manager |
Mr. K. S. Law |
9090 1378 |
2566 7522 |
Site Agent |
Mr. Tony Au |
9725 5874 |
2566 7522 |
||
Sub Agent |
Mr. Johnny Wong |
9725 5870 |
2566 7522 |
||
Chun Wo  Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
Mr. PL Yue |
2162 9909 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Sub Agent |
Mr. Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 2467 |
|||
Construction
Manager |
Mr KK Yuen |
9498 1213 |
|||
Construction
Manager |
Mr. Andy Yu |
9648 4896 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Environmental
Supervisor |
Ms. Kiwi Chan |
6227 8840 |
|||
|
|
Environmental
Supervisor |
Mr. Yeung Sze King |
9047 9952 |
|
Environmental
Supervisor |
Mr. Les Chow |
6692 2423 |
|
||
Environmental
Supervisor |
Mr. Otto Yau |
9260 4485 |
|
||
Chun Wo  CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658-3002 |
2827 9996 |
Site Agent |
Mr. Mak Kam Wing |
3658-3044 |
|||
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Calvin Leung |
9286 9208 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214 7700 |
2140 6799 |
Deputy Site Agent |
Mr. Desmond Sze |
2214 7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2566 2192 |
Site Agent |
Mr. P J Fan |
3557 6368 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Environmental Supervisor |
Mr. Kelven Yip |
3557 6347 |
|||
Environmental Supervisor |
Mr. Tim Fung |
3557 6349 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Lee Wai Man |
9481 6024 |
|||
Environmental
Supervisor |
Mr. Clement
Pang |
9735 9200 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team
Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
Major construction activities for Contract no.
HK/2009/17 have been commenced on 5 October 2010. During
this reporting period, the principal work activities for Contract no. HY/2009/17
are summarized in Table2.4.
Table 2.4   Principal Work Activities for Contract no. HY/2009/17
June 2012 |
July 2012 |
August 2012 |
ELS works for basement construction for pile cap
construction |
ELS works for basement construction for pile cap
construction |
ELS works for basement construction for pile cap
construction |
Table 2.5   Principal Work Activities for Contract no.
HY/2009/18
June 2012 |
July 2012 |
August 2012 |
Trial Pit
Instrumentation and
monitoring works
Drainage works
Site investigation and
pre-drilling works
D-wall construction
Sheet piling
Grout curtain
Tree Transplantation
Earthwork
Preparation works in
existing tunnel
Stitch coring
Approach ramp structure
works
Top down slab
Road works
Tunnel works
Excavation and Lateral
Support |
Excavation of trial pit
Transplanting of trees
Hoarding erection and
modification
Installation of couplers,
UU detection, trial trench, pre-drilling
Site investigation and
pre-drill works
Excavation
Diaphragm wall construction
Sheet Piling
Drainage works
Tunnel works
Top down slab construction
Trough structure
construction and associated drilling and grouting
Road works
OHVD installation
Site access set up at
Portion 6
Pumping test |
Excavation of trial pit
Transplanting of trees
Hoarding erection and
modification
Installation of couplers,
UU detection, trial trench, pre-drilling
Site investigation and
pre-drill works
Excavation
Diaphragm wall construction
Sheet Piling
Drainage works
Tunnel works
Top down slab construction
Trough structure
construction and associated drilling and grouting
Road works
OHVD installation
Site access set up at
Portion 6
TTA near Gate 3
Pumping test |
2.5.3.
Major construction activities for Contract no.
HK/2009/01 have been commenced on 25 August 2011. During this reporting period,
the principal work activities are summarized in Table2.6:
Table 2.6   Principal Work Activities
for Contract no. HK/2009/01
June 2012 |
July 2012 |
August 2012 |
Diaphragm wall construction
works for CWB (Stage2)
Pre-drilling works for CWB
(Stage2)
Pre-bored H piling works
for SCL
Excavation for CWB top slab
(Bay1  Bay 4)
Waterproofing works for CWB
top slab (Bay 1  Bay 4)
Excavation and installation
of shoring system for construction of exhaust duct structure
Excavation for SCL top slab
construction works
Construction of SCL top
slab (Bay 3)
Trimming of SCL Diaphragm
wall head |
Diaphragm wall construction
works for CWB (Stage2)
Pre-drilling works for CWB
(Stage 2)
Waterproofing works for CWB
top slab (Bay 1  Bay 4)
Backfilling works for CWB
top slab
Excavation and installation
of shoring system for construction of exhaust duct structure
Construction of exhaust
duct (Bay 2)
Trimming of SCL Diaphragm
wall head (Bay 3)
Construction of SCL top
slab (Bay 3)
Remedial works for SCL
Diaphragm Wall
Load test on SCL pre-bored
H-piles |
Diaphragm wall construction
works for CWB (Stage2) at the northern side
Pre-drilling works for CWB
(Stage 2)
Construction of exhaust
duct structure (Bay 1 and Bay 2) including waterproofing and protective
screeding
Trimming of SCL Diaphragm
wall head
Construction of SCL top
slab (Bay 2 & Bay 3)
Remedial works for SCL
Diaphragm Wall |
2.5.4.
Major construction activities for Contract no.
HK/2009/02 have been commenced on 26 April 2011. During this reporting period, the principal work
activities are summarized in Table2.7:
Table
2.7   Principal Work Activities for Contract no. HK/2009/02
June 2012 |
July 2012 |
August 2012 |
Deep excavation works. The excavation level has reached -9.0mPD to
-9.8mPD on the eastern and western portion of the site respectively.
Tunnel Pre-drill work of
bored pile at tunnel portion 3 & 4 area.
Trench excavation for guide
wall of Diaphragm wall at tunnel portion 3 & 4 area.
Guide wall construction for
Diaphragm wall at tunnel portion 3 & 4 area.
Bored pile PC34 and PC35.
Pre-drill for bored pile
and diaphragm wall.
Handover of Government
Helipad at Tunnel Portion 3&4 and initial Survey at ex-helipad.
Half bay of bulkhead wall
construction |
Deep excavation works to
-12.0mPD and -9.8mPD on the eastern and western portion of the site respectively
Tunnel bored pile works at
tunnel portion 3 & 4 area
Tunnel Pre-drill work of
bored pile at tunnel portion 3 & 4 area
Trench excavation for guide
wall of Diaphragm wall at tunnel portion 3 & 4 area
Guide wall construction for
Eastern Bulkhead Diaphragm wall at tunnel portion 3 & 4 area |
Deep excavation works
reached -19mPD to -18mPD on the eastern and western portion of the site respectively
Pre-drill holes
Guide wall construction for
Eastern Bulkhead Diaphragm wall at tunnel portion 3 & 4 area
Silo tank, desander and bar
bending yard setup for diaphragm wall construction at existing helipad
Diaphragm wall construction
of panel P110 |
2.5.5.
Major construction activities for Contract no.
HY/2009/15 have been commenced on 13 July 2011. During this reporting period,
the principal work activities are summarized in Table 2.8:
Table
2.8   Principal Work Activities for Contract
no. HY/2009/15
June 2012 |
July 2012 |
August 2012 |
Diaphragm wall construction works at TS4
ELS works at TPCWAE
Cut and cover tunnel construction at TS1
Night time protection works at CHT
Cut off wall preparation works at Hung Hing Road
and POC |
Diaphragm wall construction works at TS4
Rock breaking works at TPCWAE
Removal of temporary reclamation at TS1
Dismantling of scaffold in tunnel box at TS1
Mined tunnel preparation works at TPCWAE |
Diaphragm wall construction works at TS4
Rock breaking works at TPCWAE
Removal of temporary reclamation at TS1
Dismantling of scaffold in tunnel box at TS1
Preparation works for bored piling at eastern
breakwater
Mined tunnel preparation works at TPCWAE |
2.5.6.
Major construction activities for Contract no.
HY/2009/19 have been commenced on March 2011. During this reporting period, the
principal work activities are summarized in Table 2.9:
Table
2.9   Principal Work Activities for
Contract no. HY/2009/19
June 2012 |
July 2012 |
August 2012 |
Road works at Watson Road
Fabrication of bored piling
platform
Bored piling (Land)
Ground contamination
assessment
Pre-drilling works for
bored pile and Diaphragm wall
D-wall Construction (North
& South Section)
Guide wall construction for
D-wall / Barette at North side
Construction works for Box
Culvert T
Construct ion of socket-H
pile for Marine works
Construction of pre-bored
H-pile works for Culvert U
Installation of sheet pile
at D9 location
Construction of pile cap |
Road works at Watson Road
Fabrication of bored piling
platform
Bored piling (Land)
Ground contamination assessment
Pre-drilling works for
bored pile and Diaphragm wall
D-wall Construction (North
& South Section)
Guide wall construction for
D-wall / Barette at North side
Construct ion of socket-H
pile
Construction of pre-bored
H-pile works for Culvert U |
Road works at Watson Road
Bored piling (Land)
Ground contamination assessment
Pre-drilling works for
bored pile and Diaphragm wall
D-wall Construction (North
& South Section)
Guide wall construction for
D-wall / Barette at North side
Construction works for Box
Culvert T
Marine Piling
Construct ion of socket-H
pile
Construction of pre-bored
H-pile works for Culvert U
Construction of 1500f drainage pipe
Construction of Pile cap
& column (Land) |
2.5.7.
Major construction activities for Contract no.
HK/2010/06 have been commenced on March 2011. During this reporting period, the
principal work activities are summarized in Table 2.10:
Table 2.10 Principal Work Activities
for Contract no. HK/2010/06
June 2012 |
July 2012 |
August 2012 |
Construction of pre-cast unit in China |
Construction of pre-cast unit in China |
Construction of pre-cast unit in China |
2.5.8.
Implementation
status of the recommended mitigation measures during this reporting period is
presented in Appendix 2.1.
3.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
3.1 and Figure 3.1.  /span>Appendix
3.1 shows
the established Action/Limit Levels for the monitoring works.
Table 3.1  Noise Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun
Area |
M3a |
Tung Lo Wan
Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist
Church Henrietta Secondary School |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark 1: Location
ID has been updated from M7 to M8 for City Hall
* Remark 2: M7e has
become a reference station starting from 7 Aug 2012
Real time Noise Monitoring Stations
3.1.2.
The
noise monitoring stations for the Project are listed and shown in Table 3.2 and
Figure 3.1..
Appendix 3.1
shows the established Action/Limit Levels for the monitoring works.
Table 3.2  Real Time Noise Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise
Monitoring Parameters, Frequency and Duration
3.1.3.
The construction noise level shall be measured in terms of the
A-weighted equivalent continuous sound pressure level (Leq). Leq
(30 minutes) shall be used as the monitoring parameter for the time period between
0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5
minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria. Supplementary information for data
auditing, statistical results such as L10 and L90 shall
also be obtained for reference.
3.1.4.
Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
 -
One
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.5.
Real
time noise shall be carried out at the designated monitoring stations. The
following is an initial guide on the regular monitoring frequency for each
station on a 24 hours daily basis when noise generating activities are
underway:
 -
One
set of measurements between 0700 and 1900 hours on normal weekdays.
 -
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
 -
One
set of measurements between 2300 and 0700 hours on next day on everyday.
3.1.6.
If
construction works are extended to include works during the hours of 1900  
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring
Equipment
3.1.7.
As
referred to in the Technical Memorandum  issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
3.1.8.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
3.1.9.
The
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency before deployment to the site
and during each site visit. Measurements may be accepted as valid only if the
calibration level from before and after the noise measurement agree to within
1.0 dB.
Air Quality Monitoring
Stations
3.2.1.
The
air monitoring stations for the Project are listed and shown in Table
3.3 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table 3.3  Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
Causeway Bay Community
Centre |
Causeway Bay |
CMA3a |
Future CWB site office
at Wanchai Waterfront Promenade |
Causeway Bay |
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to Pedestrian Plaza |
Wan Chai |
CMA6a |
Future AECOM site
office at Work Area |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (Western End of Podium) |
Central |
Air Monitoring Parameters,
Frequency and Duration
3.2.2.
One-hour
and 24-hour TSP levels should be measured to indicate the impacts of
construction dust on air quality. The 24-hour TSP levels shall be measured by
following the standard high volume sampling method as set out in the Title 40
of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.
3.2.3.
All
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and any other local atmospheric factors affecting or
affected by site conditions, etc., shall be recorded down in detail.
3.2.4.
For
regular impact monitoring, the sampling frequency of at least once in every
six-days, shall be strictly observed at all the monitoring stations for 24-hour
TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least
three times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5.
High
volume samplers (HVSs) in compliance with the following specifications shall be
used for carrying out the 1-hour and 24-hour TSP monitoring:
 -
0.6  
1.7 m3 per minute adjustable flow range;
 -
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
 -
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
 -
Capable
of providing a minimum exposed area of 406 cm2;
 -
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
 -
Equipped
with a shelter to protect the filter and sampler;
 -
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
 -
Equipped
with a flow recorder for continuous monitoring;
 -
Provided
with a peaked roof inlet;
 -
Incorporated
with a manometer;
 -
Able
to hold and seal the filter paper to the sampler housing at horizontal
position;
 -
Easily
changeable filter; and
 -
Capable
of operating continuously for a 24-hour period.
3.2.6.
Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be
traceable to the internationally recognized primary standard and be calibrated
annually. The concern parties such as IEC shall properly document the
calibration data for future reference. All the data should be converted into
standard temperature and pressure condition.
3.2.7.
Laboratory
Measurement / Analysis
3.2.8.
A
clean laboratory with constant temperature and humidity control, and equipped
with necessary measuring and conditioning instruments to handle the dust
samples collected, shall be available for sample analysis, and equipment
calibration and maintenance. The laboratory should be HOKLAS accredited.
3.2.9.
Filter
paper of size 8 x 10 shall be labelled before sampling. It shall be a clean
filter paper with no pinholes, and shall be conditioned in a humidity-controlled
chamber for over 24-hours and be pre-weighed before use for the sampling.
3.2.10. After sampling, the filter paper loaded
with dust shall be kept in a clean and tightly sealed plastic bag. The filter
paper shall then be returned to the laboratory for reconditioning in the
humidity controlled chamber followed by accurate weighing by an electronic
balance with readout down to 0.1 mg. The balance shall be regularly calibrated
against a traceable standard.
3.2.11. All the collected samples shall be kept
in a good condition for 6 months before disposal.
4.0.1.
Per EPD’s letter dated 3 Aug 2012 (received by ET
on 6 Aug 2012 through HyD), noise monitoring at M8  City Hall commenced on 7
Aug 2012, and the monitoring station M7e  International Finance Centre
(Eastern Podium) has become a reference station starting from 7 Aug 2012.
4.0.2.
Due to safety concerns, the monitoring location for
M4b  Victoria Centre has been finely adjusted from 7 June 2012.
4.0.3.
Monitoring
for report of review baseline noise level was performed from 11 April 2011 to 8
June 2011. Then the report was submitted
on the 20 June 2011, verified by IEC on 18 July 2011 and was approved by ER by
January 2012. The new baseline is used
for the noise calculation starting from the January 2012 reporting month.
4.0.4.
The
environmental monitoring will be implemented based on the division of works
areas of each designed project managed under different contracts with separate
FEP applied by individual contractors. 
Overall layout showing work areas of various contracts, latest status of
work commencement and monitoring stations is shown in Figure 2.1
and Figure 3.1. The monitoring results are
presented in according to the Individual Contract(s).
4.0.5.
In the
reporting period, the concurrent contracts are as follows:
Contract
no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
Contract
no. HY/2009/17  Central –Wanchai Bypass (CWB) at FEHD Whitfield Depot  
Advanced piling works under FEP-03/364/2009
Contract
no. HY/2009/18  Central –Wanchai Bypass (CWB)  Central Interchange under
FEP-05/364/2009/A
Contract
no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009
Contract
no. HK/2009/01 –Wanchai Development Phase II  Central –Wanchai Bypass at Hong
Kong Convention and Exhibition Centre
Contract
no. HK/2009/02 Wanchai Development Phase II  Central- Wanchai Bypass at Wanchai
East
4.1.1.
Due
to adverse weather condition, monitoring at station M1a, noise monitoring was rescheduled from 24
July 2012 to 25 July 2012.
4.1.2.
Due
to equipment repair, monitoring at station M4b, noise
monitoring was rescheduled from 23 August 2012 to 24 August 2012.
4.1.3.
Due
to equipment repair, monitoring at station M6, noise
monitoring was rescheduled from 23 August 2012 to 24 August 2012.
4.1.4.
Due
to adverse weather condition, monitoring at station M7e, noise monitoring was rescheduled from 24
July 2012 to 25 July 2012.
4.1.5.
Due
to adverse weather condition, monitoring at station M7w, noise monitoring was rescheduled from 24
July 2012 to 25 July 2012.
Contract
no. HY/2009/17 –Central  Wanchai Bypass (CWB) at FEHD Whitfield Depot  
Advanced piling works under FEP-03/364/2009
4.1.6.
The
proposed division of noise monitoring stations for Contract no. HY/2009/17 is
summarized in Table 4.1 below:
Table 4.1   Noise Monitoring Stations for Contract no.  /span>HY/2009/17
Station |
Description |
M4b |
Victoria Centre |
4.1.7.
No
exceedance was recorded in this reporting
period.
4.1.8.
Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of graphical
presentation can be referred in
Appendix 4.1. 
Contract no.
HY/2009/18  Central  Wanchai Bypass (CWB)  Central Interchange under
FEP-05/364/2009/A
4.1.9.
Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2009/18 are summarized in Table 4.2 below.
Table 4.2   Noise Monitoring Station for Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
*
Remark : M7e has become a reference station starting from 7 Aug 2012
Reporting month of March 2012
4.1.10.
No
exceedance was recorded in this reporting
period.
4.1.11.
Noise monitoring results measured in this reporting
period are reviewed and summarized. 
Details of noise monitoring results and graphical presentation can be
referred in Appendix 4.1.
Contract no. HK/2009/01 - Wanchai
Development Phase II - Central - Wanchai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009 and Contract no.
HK/2009/02 - Wanchai Development Phase II - Central - Wanchai Bypass at Wanchai
East (CWB Tunnel) under FEP-01/364/2009
4.1.12.
The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011 and
HK/2009/02 under FEP-01/364/2009 is on 26 April 2011.The proposed division of air
monitoring stations are summarized in Table 4.3 below.
Table 4.3   Noise Monitoring Stations for Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
4.1.13.
No
exceedance was recorded in this reporting
period.
4.1.14.
Noise monitoring results measured in this reporting
period are reviewed and summarized. 
Details of noise monitoring results and graphical presentation can be
referred in Appendix 4.1.
Contract no.
HY/2009/15 - Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
4.1.15.
The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise monitoring was
commenced on 13 July 2011. The proposed division of noise monitoring
stations are summarized in in Table 4.4 below.
Table 4.4   Noise Monitoring Station for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.16. No exceedance was recorded in this
reporting period.
4.1.17.
Details of noise monitoring results and graphical
presentation can be referred in
Appendix 4.1. 
4.1.18. Noise monitoring for the tunnel works
under contract no. HY/2009/19 was commenced on 24 April 2011. The proposed
division of noise monitoring stations are summarized in Table 4.5 below.
Table 4.5   Noise Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
Reporting
month of June 2012
4.1.19.
No
action level exceedance was recorded in this reporting period.
4.1.20.
Two
limit level exceedances were recorded on 7 and 12 Jun 2012 at M6  HK Baptist
Church Henrietta Secondary School in the reporting month.  /span>Major traffic jam and no major work activities
were observed during monitoring, the limit level exceedances were considered as
non-project related.
Reporting
month of July 2012
4.1.21.
No
action or limit level exceedance was recorded in the reporting month.
Reporting
month of August 2012
4.1.22.
No
action level and one limit level exceedance was recorded on 24 August 2012 at
M6  HK Baptist Church Henrietta Secondary School in the reporting month. Major traffic jam and no major work
activities were observed during monitoring, the limit level exceedance was
considered as non-project related.
4.1.23.
Noise monitoring results measured in this reporting
period are reviewed and summarized. 
Details of noise monitoring results and graphical presentation can be
referred in
Appendix 4.1 and the
Notification of Exceedance can be referred in
Appendix 6.2.
Contract no. HY/2009/17 –Central - Wanchai
Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009 and Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
4.2.1.
The
proposed division of real time noise monitoring stations are summarized in Table
4.6 below. Real time noise monitoring for the piling works under
contract no. HY/2009/17 was commenced on 5 October 2010.
Table 4.6  Real Time Noise Monitoring
Station for Contract no. HY/2009/17
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
Real
time noise monitoring results and graphical presentation during night time
period are for information only.
4.2.2.
No project-related action and limit level
exceedance was recorded during the June reporting month.
4.2.3.
No
action level exceedance and non-project related limit level exceedances were
recorded at RTN1 during the July reporting month.
4.2.4.
No project-related action and limit level
exceedance during the August reporting month.
4.2.5.
Real
time noise monitoring results measured in this reporting period are reviewed
and summarized. Details
of real time noise monitoring results and graphical presentation can be
referred to Appendix 4.2
4.2.6.
The
proposed division of noise monitoring stations are summarized in Table 4.7
below. Real time noise monitoring for major construction works under contract
no. HY/2009/19 was commenced on 24 April 2011.
Table 4.7  Real Time Noise Monitoring
Stations