Contract No: HK/2015/01 Wanchai Development Phase II and Sampling,
Field Measurement and Testing Work (Stage 3) Environmental Permit no. EP-364/2009/E, Further Evironmental
permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEp-07/364/2009/D,
FEP-09/364/2009/B, fep-10/364/2009/B and fep-11/364/2009/B, FEP-12/364/2009/D Quarterly
Environmental Monitoring
and
Audit Report
- March to MAY 2018 –
|
CLIENTS: |
|
Civil Engineering
and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
19 July
2018 |
2.2 Scope of the Project and Site
Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact
Personnel
2.5 Principal Work and Activities
4.2. Real Time Noise Monitoring Results
4.3. Air quality
monitoring Results
5.3. Real Time Noise Monitoring
5.5. Review of the Reasons for and the
Implications of Non-compliance.
5.6. Summary of action taken in the event of
and follow-up on non-compliance.
6. Complaints, Notification
of Summons and Prosecution
7. Cumulative Construction
Impact due to the Concurrent Projects
lIST
OF TABLES
Table I Principal Work Activities
for Contract no. HY/2009/18
Table II Principal
Work Activities for Contract no. HK/2009/01
Table III Principal Work Activities for
Contract no. HK/2009/02
Table IV Principal Work Activities for
Contract no. HY/2009/15
Table V Principal
Work Activities for Contract no. HY/2009/19
Table VI Principal Work Activities for Contract
no. HK/2012/08
Table VII Principal Work Activities for Contract no.
HY/2010/08
Table VIII Principal Work Activities for Contract no.
HY/2011/08
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 2.4 Principal Work Activities for
Contract no. HY/2009/18
Table 2.5 Principal Work Activities for
Contract no. HK/2009/01
Table 2.6 Principal
Work Activities for Contract no. HK/2009/02
Table 2.7 Principal
Work Activities for Contract no. HY/2009/15
Table 2.8 Principal
Work Activities for Contract no. HY/2009/19
Table 2.9 Principal
Work Activities for Contract no. HK/2012/08
Table 2.10 Principal Work
Activities for Contract no. HY/2010/08
Table 2.11 Principal Work
Activities for Contract no. HY/2011/08
Table 3.1 Noise
Monitoring Stations
Table 3.2 Real
Time Noise Monitoring Stations
Table 3.3 Air
quality monitoring Stations
Table 4.1 Noise Monitoring Station
for Contract no. HY/2009/18
Table 4.2 Noise Monitoring
Stations for Contract nos. HK/2009/01 and HK/2009/02
Table 4.3 Noise Monitoring Station
for Contract nos. HY/2009/15
Table 4.4 Noise
Monitoring Stations for Contract no. HY/2009/19
Table 4.5 Noise Monitoring Stations for Contract
no. HY/2010/08
Table 4.6 Noise Monitoring Stations for Contract no.
HY/2011/08
Table 4.7 Real
Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.8 Real Time
Noise Monitoring Stations for Contract no.
HY/2011/08
Table 4.9 Air
quality monitoring Stations for Contract no. HY/2009/18
Table 4.10 Air
quality monitoring Stations for Contract no. HK/2009/01
Table 4.11 Air
quality monitoring Station for Contract no. HK/2009/02
Table 4.12 Air
quality monitoring Station for Contract no. HY/2009/15
Table 4.13 Air
quality monitoring Stations for Contract no. HY/2009/19
Table 4.14 Air
quality monitoring Stations for Contract no. HK/2012/08
Table 4.15 Air
quality monitoring Stations for Contract no. HY/2010/08
Table 4.16 Air quality monitoring Stations for
Contract no. HY/2011/08
Table 4.17 Details
of Waste Disposal for Contract no. HK/2009/01
Table 4.18 Details
of Waste Disposal for Contract no. HK/2009/02
Table 4.19 Details
of Waste Disposal for Contract no. HY/2009/18
Table 4.20 Details
of Waste Disposal for Contract no. HY/2009/15
Table 4.21 Details
of Waste Disposal for Contract no. HY/2009/19
Table 4.22 Details
of Waste Disposal for Contract no. HK/2012/08
Table 4.23 Details of Waste Disposal for Contract no.
HY/2010/08
Table 4.24 Details of
Waste Disposal for Contract no. HY/2011/08
Table 6.1 Cumulative
Statistics on Complaints
Table 6.2 Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure
3.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 2.1 Environmental Mitigation
Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix 4.1 Noise Monitoring Results and
Graphical Presentations
Appendix
4.2 Real-time Noise Monitoring Results and
Graphical Presentations
Appendix 4.3 Air Quality Monitoring Results
and Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 6.2 Notification of Exceedance
Appendix 8.1 Construction Programme of
Individual Contracts
EXECUTIVE
SUMMARY
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under
FEP-05/364/2009
Major construction activities for Contract no. HY/2009/18 have been
commenced on 21
Table I Principal Work Activities for Contract
no. HY/2009/18
March 2018 |
April 2018 |
May 2018 |
Maintenance works |
Maintenance works |
Nil |
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
Major construction activities
for Contract no. HK/2009/01 have been commenced on 25 August 2011. During this
reporting period, the principal work activities are summarized as below:
Table II Principal Work
Activities for Contract no. HK/2009/01
March 2018 |
April 2018 |
May 2018 |
Reinstatement of amenity area |
Reinstatement of amenity area |
Reinstatement of amenity area |
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
Major construction activities
for Contract no. HK/2009/02 have been commenced on 26
Table III Principal Work Activities for Contract no.
HK/2009/02
March 2018 |
April 2018 |
May 2018 |
Joint Inspection with ASD, AECOM and
JV for completion of rectification work within the rooms under Staircases Water test to the Types 3 and 4
Covered Walkway at West Wing New PMMA for the replacement of 8 nos.
of damaged PMMA panels Preparation for raising the vent
shaft, water meters chambers and multi-part covers of P7, P8 and P9 Drainage work Excavation for relocation of temporary fire hydrant PH2582 Jointed inspection with HKE, AECOM and
JV on the new pillar box work Remedial works against water leakage
inside OHVD cells Backfilling behind seawall block Steel fixing of Culvert O bay 15A top
slab and wall Base slab of Culvert O Bay 16A Pipe piling work for ELS of Culvert O Remedial works against water leakage
inside OHVD cells Raising of CMS draw pits and caisson
wall units access opening covers Installation of surface drain cover All backfilling works at surface drain
trench Remedial works for 0.5T rock armor Sewage works at Wan Shing Street |
New PMMA for the replacement of 8 nos.
of damaged PMMA panels Preparation for raising the vent
shaft, water meters chambers and multi-part covers of P7, P8 and P9 Drainage work Remedial works against water leakage
inside OHVD cells Backfilling behind seawall block Pipe piling work for ELS of Box
Culvert O Bay 13, 14 and 15B Installation of ELS for Box Culvert O
Bay 17A Backfilling works for Box Culvert O
Bay 15A and 16A Demolition of D-Wall for construction
of Box Culvert O Preparation works for construction of
Bulkhead at Box Culvert O Bay 19 Preparation works for fabrication of
precast units for Box Culvert O Remedial works against water leakage
inside OHVD cells Temporary drainage system for stock
piling at Portion 5 Construction of manhole no. MH4.17 for
sewage works at Wan Shing Street |
New PMMA for the replacement of 8 nos.
of damaged PMMA panels Preparation for raising the vent
shaft, water meters chambers and multi-part covers of P7, P8 and P9 Drainage work Remedial works against water leakage
and CCTV inside tunnel Installation of breakwater Backfilling behind seawall block Pipe piling work for ELS of Box
Culvert O Bay 13, 14 Installation of ELS for Box Culvert O
Bay 14A and 17A Backfilling works for Box Culvert O
Bay 15A and 16A Demolition of D-Wall for construction
of Box Culvert O Fabrication of precast units for Box
Culvert O Remedial works against water leakage
inside OHVD cells Temporary drainage system for stock
piling at Portion 5 Construction of manhole no. MH4.17 for
sewage works at Wan Shing Street Backfilling for sewage trench at Wan
Shing Street |
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/D
Major construction activities
for Contract no. HY/2009/19 have been commenced on March 2011. During this
reporting period, the principal work activities are summarized as below:
Table V Principal Work
Activities for Contract no. HY/2009/19
March 2018 |
April 2018 |
May 2018 |
Approach ramp structure Construction. Bridge Construction & installation
of enclosure. Retaining wall construction. FEHD depot re-provision works. Oil street drainage works. Installation of skin parapet on TB
bridge at Pier 15-17. Landscape deck, column & pile cap
foundation works. Watson Road Water mains laying works. EVA at EVB. Hing Fat Street road and drainage
works. IEC TD bridge parapet installation. |
Approach ramp structure Construction. Bridge Construction & installation
of enclosure. Retaining wall construction. FEHD depot re-provision works. Oil street drainage works. Installation of skin parapet on TB
bridge at Pier 15-17. Landscape deck, column & pile cap
foundation works. Watson Road Watermains laying works. EVA at EVB. Hing Fat Street road and drainage
works. |
Approach ramp structure Construction. Bridge superstructure, parapet &
installation of enclosure. Retaining wall construction. FEHD depot re-provision works. FEHD metal roof construction. Oil street drainage works. Installation of skin parapet on TB
bridge at Pier 15-17. Landscape deck, column & pile cap
foundation works. Watson Road Watermains laying works. EVA at EVB. Hing Fat Street road and drainage
works. Demolition of TD bridge |
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009/B and FEP-12/364/2009/D
Table VI
Principal Work Activities for Contract no. HK/2012/08
March 2018 |
April 2018 |
May 2018 |
Construction of Slip Road 1 Construction of drainage Asphalt paving Construction of roundabout |
Construction of Slip Road 1 Construction of drainage Asphalt paving Construction of roundabout |
Construction of Slip Road 1 Construction of drainage Asphalt paving Construction of roundabout |
Contract
no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 section under
FEP-10/364/2009B
Table VII Principal Work
Activities for Contract no. HY/2010/08
March 2018 |
April 2018 |
May 2018 |
Tree protection works next to existing
BGO, Drainage improvement works, Utility diversion works, Retaining wall works ELS works, Construction works for subway
extension |
Tree protection works next to existing
BGO, Drainage improvement works, Utility diversion works, Retaining wall works ELS works, |
Tree replanting works in VP, Drainage improvement works, Utility diversion works, Retaining wall works |
Contract
no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
Table VIII Principal Work
Activities for Contract no. HY/2011/08
March 2018 |
April 2018 |
May 2018 |
Construction of Ventilation Buildings,
inclusive of Administration Building, Central, Ventilation Building, East
Ventilation Shaft/Building, West Ventilation Building Application of Thermal Barrier inside
the Tunnel, asphalt pavement Construction of Tunnel Thermal Barrier Installation of Electricals and
Mechanicals Installation of Tunnel Features |
Construction of Ventilation Buildings,
inclusive of Administration Building, Central, Ventilation Building, East
Ventilation Shaft/Building, West Ventilation Building Application of Thermal Barrier inside
the Tunnel, asphalt pavement Installation of Electricals and
Mechanicals Installation of Tunnel Features |
Construction of Ventilation Buildings,
inclusive of Administration Building, Central, Ventilation Building, East
Ventilation Shaft/Building, West Ventilation Building Application of Thermal Barrier inside
the Tunnel, asphalt pavement Installation of Electricals and
Mechanicals Installation of Tunnel Features |
Noise
Monitoring
Real time Noise Monitoring
Limit level exceedance was recorded in
March 2018 reporting period. After the investigation, the exceedance recorded
on 22, 23 and 24 March 2018 are considered as non-project related. No limit
level exceedance was recorded in the April 2018 reporting period.
No limit level exceedance was recorded in
the May 2018 reporting period.
Limit level exceedances were recorded in
March 2018 reporting period. After investigation, the exceedances recorded on
01, 02, 03, 05, 06, 07, 09, 10, 12, 14, 15, 16, 20, 21, 22, 23 and 24 March
2018 were considered as Project related and while other exceedances recorded
are considered as non-Project related.
Limit level exceedances were recorded in
April 2018 reporting period. After investigation, the exceedance recorded on 27
and 28 March 2018 are considered as Project related and while other exceedances
recorded are considered as non-Project related.
Limit level exceedances were recorded in
May 2018 reporting period. After investigation, the exceedances recorded on 9
May 2018 were considered as Project related and the other exceedances recorded
was considered as non-Project related.
No limit level related exceedance was
recorded in March 2018 reporting period.
No limit level exceedance was recorded
in the April 2018 reporting period.
Limit level exceedances were recorded in
the May 2018 reporting period. After the investigation, the exceedances recorded
on 15 May 2018 are considered as non-project related.
Air Quality
Monitoring
Complaints,
Notifications of Summons and Successful Prosecutions
An ICC complaint (Case Ref:
2-4495970766, lodged at 0955hrs on 12 March 2018) was referred to the ET on 27
March 2018. The ICC hotline operator reported that a public complaint was
referred by the Police Force regarding noise emanation from road construction works
at North Point section Island East Corridor (IEC) near 19 Wharf Road at around 0920hrs
on 12 March 2018. Further information regarding the same event was received via
ICC hotline (Case ref: 2-449606553, lodged at 1004hrs on 12 March 2018) was
referred to the ET on 27 March 2018. The complainant further reported that
noise was emanated from road construction works on Island Eastern Corridor
(IEC) near Yu Lee Mo Fan Memorial School. Temporary noise barrier observed to
be transparent in nature was speculated to be ineffective; and it was observed
that only 3 out of the 6 units of temporary noise barrier are installed. The
complainant suggested that additional 6 sections of noise barrier shall be installed.
The noise emanation was started from 0800hrs and he is a resident at 18 Wharf Road
and his rest was adversely affected by the concerned noise emanation. He has contacted
the Environmental Protection Department and the Police Force regarding the
noise emanation. The Environmental Protection Department has replied that
construction works conducted after 0700hrs does not violate statutory
requirement while the Police Force has created an ICC complaint case file
(2-4495970766) for follow up.
ET confirmed with the Resident Site
Staff that Concrete breaking works on IEC Eastbound near Pier F8 and Pier F9
was conducted under Contract HY/2009/19 from 0900hrs to 1000hrs on 12 March
2018. Noise mitigation measure including wrapping of breaking head with acoustic
material was implemented. Enhancement measures including provision of 2.5m high
temporary noise barrier were subsequent implemented on 12 March 2018.
According to RSS confirmed information,
concrete breaking works on IEC Eastbound near Pier F8 and Pier F9 was conducted
under Contract HY/2009/19 from 0900hrs to 1000hrs on 12 March 2018. Noise
mitigation measure including wrapping of breaking head with acoustic material
was implemented. Enhancement measures including provision of 2.5m high temporary
noise barrier were subsequent implemented on 12 March 2018.
Based on review on relevant site record,
noise impact associated with the breaking works on IECL opposite to the
concerned location was observed across March 2018 and project related exceedances
were recorded at nearby noise monitoring station at YLMF Memorial School across
March 2018. Upon identification of the project related exceedance at YLMF
memorial school noise monitoring station, the Contractor is requested to adopt
remedial and enhancement measures to minimize the noise emanation and avoid
noise impact to the nearby sensitive receivers.
According to ET follow up checking, the
following enhancement measures were proposed and implemented by the Contractor
by 16 March 2018 including provide additional temporary noise barrier and
repair damaged or incomplete temporary noise barrier installed for the breaking
works, provide additional acoustics screen to the breaking tip in addition to temporary
noise barrier installed, provide covering of breaker tip with acoustic material
for noise reduction and conduct breaking works intermittently.
Nevertheless, subsequent to 16 March
2018, it was observed at times that the above mitigation measures were not
fully implemented by the Contractor throughout the remaining breaking works
period. Upon identification of deficiency in mitigation measures, the Contractor
has been requested to rectify any deficiency observed and ensure relevant noise
mitigation measures are implemented and the observed deficiencies are rectified
prior to resumption of the concerned impact associated works. According to
Contractor information, the concerned breaking works have been completed by 26
March 2018.
In view of the public concern and the
identified noise concern, the Contractor of HY/2009/1 was reminded that, shall
future breaking works be required to be conducted on IECL (at works area
located at the East of the noise enclosure), noise mitigation measure including
but not limit to provision of temporary noise barrier with adequate height and
extend and additional noise screen shall be proposed for ET/IEC review and
confirmation prior to conducting the corresponding works to minimize the
potential impact to the surroundings. The Contractor is also advised to review
the adopt construction method with consideration on alterative PME with reduced
noise emanation to minimize the potential noise impact to the surroundings.
An ICC complaint (Case Ref:
2-4530180777) was referred to the ET on 20 April 2018. The complainant reported
that noise pollution was caused by the road works performed by some workers
during midnight at Island Eastern Corridor (near Provident Centre, North Point)
from time to time. They have used heavy noisy machinery and shouted quite often
which disturbed the residents near Provident Centre in North Point seriously.
An EPD complaint case (Case Ref:
H08/RS/00009538-18) was referred to the ET on 23 April 2018. According to EPD
information, the complainant stated that Night time construction noise on
Island Eastern Corridor outside Provident Centre at around 0110hrs on 11th
April 2018.
As the location, time and concern of the
above complaints cased received are identical, the two complaints will be
reported and consolidated into one complaint case for reporting. According to
RSS confirmed information, no construction works was conducted under Contract
HY/2009/19 from 2300hrs on 10 April 2018 to 0100hrs on 11 April 2018.
Installation and welding of steel frames of Traffic Sign FASS06 at works area
opposite to Henrietta Secondary School was conducted under Contract HY/2009/19
between 0100hrs to 0600hrs on 11 April 2018. Total 1 no. of cherry picker, 1
no. of welding machine, 1 no. of lorry, 1 no. of grinder; 3 nos. of with
flashing directional sign and 3 nos. of lorry mounted attenuator were deployed.
Either one PME set consisting 1 no. of welding machine and 1 no. of cherry
picker OR one PME set consisting of 1 no. of lorry and 1 no. of grinder were
operated between 0100hrs to 0600hrs on 11 April 2018 at the concerned works
area. Noise mitigation measures including i) Operation of cherry picker within
permanent noise barrier and ii) Operation of welding machine and grinder inside
acoustic enclosure and iii) Switching off of lorry when idled were implemented
by Contractor of HY/2009/19 for the above construction works. Relevant
Construction Noise Permit numbered GW-RS0249-18 for the above construction works
was in place for the construction works.
In view of the public concern on the
shouting by the workers, the Contractor is also recommended to adopt “walkie-talkie”
for communication to avoid potential nuisance caused to the nearby residents.
The Contractor of HY/2009/19 was reminded to upkeep the site control system for
construction works carried out during restricted hours and night time for Construction
Noise Permit compliance and maintain regular maintenance of the plant and equipment
deployed to avoid potential nuisance to the nearby public.
The First Summons to Defendant was
issued to the Contractors of Contract HY/2009/19 on 18 May 2018 regarding to
carrying out prescribed construction work in Designated Area which was not
permitted in the construction noise permit GW-RS05262-17 and contrary to
Section 6(2)(b) and 6(5), Noise Control Ordinance, Cap. 400.
The Second Summons to Defendant was
issued to the Contractors of Contract HY/2009/19 on 18 May 2018 regarding to
use powered mechanical equipment, namely a concrete lorry mixer, for the
purpose of carrying out of construction work which was not permitted in the construction
noise permit GW-RS05262-17 and contrary to section 6(1)(b) and 6(5), Noise Control
Ordinance, Cap. 400.
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009/E and Further Environmental
permit nos. FEP-01/364/2009,
FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B, FEP-11/364/2009/B
and FEP-12/364/2009/D to
implement the Environmental Monitoring and Audit (EM&A) programme as stipulated
in the EM&A Manual of the approved Environmental Impact Assessment (EIA)
Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register
No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of
EM&A Manual and “Environmental Monitoring and Audit Requirements”
under Particular Specification Section 27.
1.1.3. This report documents the finding of EM&A
works during the period from 27 March
2018 to 26 May 2018.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements – summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results – summarizes the monitoring results
obtained in the reporting period.
Section 5 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and
Island Eastern Corridor Link (IECL)
includes:
·
A dual three-lane trunk road, approximately 4.5 km
in length, and tunnel approximately 3.7 km in length defined from the
connection with the existing Rumsey Street Flyover in Central, through to a
connection with the existing Island Eastern Corridor to the east of the
Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street
Flyover to provide road connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road
system in the Wan Chai North and
·
Associated road lighting, road signing, traffic
control and surveillance system; and
·
Other associated works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
In the reporting period, the
following construction Contracts were on-going and Contract HY/2009/17,
04/HY/2006, HY/2009/15, HY/2009/18 and HK/2010/06 had been completed. The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 (Completed) |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East (CWB Tunnel) |
DP1 |
26 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel ( |
DP1 |
13 July 2011 (Completed) |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel – Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning |
DP1 |
8 October 2014 |
2.3.3.
The construction works of Contract no.
04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street under FEP-04/364/2009/A was completed, and the FEP was surrendered by
the Contractor on 11 February 2011.
2.3.4.
Construction of bored pile E3B under HY/2009/17 was confirmed
completed and the respective work area under FEP-03/364/2009 was handover and inspected
under HY/2009/19 from 19 Dec 2012 onwards. Subsequently, the FEP-03/364/2009
was surrendered by the Contractor on 28 March 2013.
2.3.5.
Construction works under HK/2010/06 was confirmed completed and
the respective work area under FEP-08/364/2009/A was handover and inspected
under HK/2012/08 from 22 Sep 2014 onwards. Subsequently, the FEP-08/364/2009/A
was surrendered by the Contractor on 3 October 2014.
2.3.6.
The Construction works under HY/2009/15 was confirm completed by
the RSS from 27 October 2017 onwards. The weekly site audit inspection for
HY/2009/15 was suspended from 27 October 2017 onwards.
2.3.7.
As confirmed with CWB RSS, the construction works under Contract
HY/2009/18 was completed from 25 April 2018 onward. The respective weekly site
audit inspection for HY/2009/18 was therefore temporary suspended from 27 April
2018 onwards.
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3.
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Ms. Gloria Tang |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Chun
Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Manager |
Mr. Simon Liu |
9304 8355 |
2634 1626 |
Environmental
Officer |
Mr.
Terry Tsang |
6683
9394 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Paul Yu |
3658-3002 |
2827 9996 |
Environmental Officer |
Mr. C.P. Ho |
9191 8856 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570 8013 |
Site Agent |
Mr. William Luk |
9456 9819 |
|||
Deputy Site Agent |
Mr. Andy Chan |
3758 8879 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
3757 8218 |
|||
Assistant Environmental Officer |
Mr. James Chan |
3757 8217 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214
7700 |
2140 6799 |
Construction Manager |
Mr. Darren Grant |
3971
1460 |
|||
Environmental
Supervisor |
Ms. Penny Yiu |
3937
1065 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Contractor’s
Representative |
Mr. Rex Chan |
3557
6371 |
2566 2192 |
Environmental Officer |
Mr. Desmond Ho |
3557 6215 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N.
Lai |
9137
1811 |
2877
1522 |
Site
Agent |
Mr. George
Cheung |
9268
1918 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Y. L. Ho |
9856
5669 |
|||
China State |
Contractor under Contract no. HY/2010/08 |
Project
Director |
Chris
Leung |
9210
7116 |
3465 2899 |
Site
Agent |
Mr. Thomas
Lui |
3557
6407 |
|||
Environmental
Officer |
Mr. Gabriel
Wong |
3557
6466 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Site Agent |
Mr. Colman Wong |
2823 1410 |
21406799 |
Environmental
Officer |
Ms. Penny Yiu |
3973 1065 |
|||
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
RAMBOLL Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
2.5.1.
Major construction activities for Contract no.
HY/2009/18 have been commenced on 21
Table 2.4 Principal Work Activities
for Contract no. HY/2009/18
March
2018 |
April
2018 |
May
2018 |
Maintenance works |
Maintenance works |
Nil |
2.5.2. Major
construction activities for Contract no. HK/2009/01 have been commenced on 25
August 2011. During this reporting period, the principal work activities are
summarized in Table2.5:
Table 2.5 Principal Work Activities
for Contract no. HK/2009/01
March 2018 |
April 2018 |
May 2018 |
Reinstatement of amenity area |
Reinstatement of amenity area |
Reinstatement of amenity area |
2.5.3. Major
construction activities for Contract no. HK/2009/02 have been commenced on 26
Table 2.6 Principal Work Activities
for Contract no. HK/2009/02
March 2018 |
April 2018 |
May 2018 |
Joint Inspection with ASD, AECOM and
JV for completion of rectification work within the rooms under Staircases Water test to the Types 3 and 4
Covered Walkway at West Wing New PMMA for the replacement of 8 nos.
of damaged PMMA panels Preparation for raising the vent
shaft, water meters chambers and multi-part covers of P7, P8 and P9 Drainage work Excavation for relocation of temporary fire hydrant PH2582 Jointed inspection with HKE, AECOM and
JV on the new pillar box work Remedial works against water leakage
inside OHVD cells Backfilling behind seawall block Steel fixing of Culvert O bay 15A top
slab and wall Base slab of Culvert O Bay 16A Pipe piling work for ELS of Culvert O Remedial works against water leakage
inside OHVD cells Raising of CMS draw pits and caisson
wall units access opening covers Installation of surface drain cover All backfilling works at surface drain
trench Remedial works for 0.5T rock armor Sewage works at Wan Shing Street |
New PMMA for the replacement of 8 nos.
of damaged PMMA panels Preparation for raising the vent
shaft, water meters chambers and multi-part covers of P7, P8 and P9 Drainage work Remedial works against water leakage
inside OHVD cells Backfilling behind seawall block Pipe piling work for ELS of Box
Culvert O Bay 13, 14 and 15B Installation of ELS for Box Culvert O
Bay 17A Backfilling works for Box Culvert O
Bay 15A and 16A Demolition of D-Wall for construction
of Box Culvert O Preparation works for construction of
Bulkhead at Box Culvert O Bay 19 Preparation works for fabrication of
precast units for Box Culvert O Remedial works against water leakage
inside OHVD cells Temporary drainage system for stock piling
at Portion 5 Construction of manhole no. MH4.17 for
sewage works at Wan Shing Street |
New PMMA for the replacement of 8 nos.
of damaged PMMA panels Preparation for raising the vent
shaft, water meters chambers and multi-part covers of P7, P8 and P9 Drainage work Remedial works against water leakage
and CCTV inside tunnel Installation of breakwater Backfilling behind seawall block Pipe piling work for ELS of Box
Culvert O Bay 13, 14 Installation of ELS for Box Culvert O
Bay 14A and 17A Backfilling works for Box Culvert O
Bay 15A and 16A Demolition of D-Wall for construction
of Box Culvert O Fabrication of precast units for Box
Culvert O Remedial works against water leakage
inside OHVD cells Temporary drainage system for stock
piling at Portion 5 Construction of manhole no. MH4.17 for
sewage works at Wan Shing Street Backfilling for sewage trench at Wan
Shing Street |
2.5.4. Major
construction activities for Contract no. HY/2009/19 have been commenced on
March 2011. During this reporting period, the principal work activities are
summarized in Table 2.8:
Table 2.8 Principal Work Activities
for Contract no. HY/2009/19
March
2018 |
April
2018 |
May
2018 |
Approach ramp structure Construction.
Bridge Construction & installation of enclosure.
Retaining wall construction.
FEHD depot re-provision works.
Oil street drainage works.
Installation of skin parapet on TB bridge at Pier 15-17.
Landscape deck, column & pile cap foundation works.
Watson Road Water mains laying works.
EVA at EVB.
Hing Fat Street road and drainage works.
IEC TD bridge parapet installation. |
Approach ramp structure Construction.
Bridge Construction & installation of enclosure.
Retaining wall construction.
FEHD depot re-provision works.
Oil street drainage works.
Installation of skin parapet on TB bridge at Pier 15-17.
Landscape deck, column & pile cap foundation works.
Watson Road Watermains laying works.
EVA at EVB.
Hing Fat Street road and drainage works. |
Approach ramp structure Construction.
Bridge superstructure, parapet & installation of enclosure.
Retaining wall construction.
FEHD depot re-provision works.
FEHD metal roof construction.
Oil street drainage works.
Installation of skin parapet on TB bridge at Pier 15-17.
Landscape deck, column & pile cap foundation works.
Watson Road Watermains laying works.
EVA at EVB.
Hing Fat Street road and drainage works.
Demolition of TD bridge |
2.5.5.
Major construction activities for
Contract no. HK/2012/08 have been commenced on March 2013. During the reporting
period, the principal work activities are summarized in Table 2.9
Table 2.9 Principal Work Activities for Contract no. HK/2012/08
March
2018 |
April
2018 |
May
2018 |
Construction of Slip Road 1
Construction of drainage
Asphalt paving
Construction of roundabout |
Construction of Slip Road 1
Construction of drainage
Asphalt paving
Construction of roundabout |
Construction of Slip Road 1
Construction of drainage
Asphalt paving
Construction of roundabout |
2.5.6.
Major construction activities for Contract no. HY/2010/08 have been commenced
on March 2013. During the reporting period, the principal work activities are
summarized in Table 2.10
Table 2.10 Principal Work Activities for Contract no. HY/2010/08
March
2018 |
April
2018 |
May
2018 |
Tree protection works next to existing BGO,
Drainage improvement works,
Utility diversion works,
Retaining wall works
ELS works,
Construction works for subway extension |
Tree protection works next to existing BGO,
Drainage improvement works,
Utility diversion works,
Retaining wall works
ELS works, |
Tree replanting works in VP,
Drainage improvement works,
Utility diversion works,
Retaining wall works |
2.5.7.
Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009B. During the reporting period, the principal work
activities are summarized in Table 2.11
Table 2.11 Principal
Work Activities for Contract no. HY/2011/08
March 2018 |
April 2018 |
May 2018 |
Construction of Ventilation Buildings,
inclusive of Administration Building, Central, Ventilation Building, East
Ventilation Shaft/Building, West Ventilation Building Application of Thermal Barrier inside
the Tunnel, asphalt pavement Construction of Tunnel Thermal Barrier Installation of Electricals and
Mechanicals Installation of Tunnel Features |
Construction of Ventilation Buildings,
inclusive of Administration Building, Central, Ventilation Building, East
Ventilation Shaft/Building, West Ventilation Building Application of Thermal Barrier inside
the Tunnel, asphalt pavement Installation of Electricals and
Mechanicals Installation of Tunnel Features |
Construction of Ventilation Buildings,
inclusive of Administration Building, Central, Ventilation Building, East
Ventilation Shaft/Building, West Ventilation Building Application of Thermal Barrier inside
the Tunnel, asphalt pavement Installation of Electricals and
Mechanicals Installation of Tunnel Features |
2.5.8.
Implementation status of the recommended mitigation measures
during this reporting period is presented in Appendix 2.1.
3.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
3.1 and Figure 3.1. Appendix
3.1 shows
the established Action/Limit Levels for the monitoring works.
Table
3.1 Noise Monitoring Station
Station |
Description |
M1a* |
Footbridge at Ex-Harbour Road Sports Centre |
M2b |
Noon Gun
Area |
M3a |
Tung Lo Wan
Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
M7e* |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8** |
City Hall |
Remark*: Location ID
has been updated from M7 to M8 for City Hall
Remark**: M7e has become
a reference station starting from 7 Aug 2012
Remarks***: The
location ID of monitoring station M1a was updated as “Footbridge for Ex-Harbour
Road Sports Centre” in May 2017.
Real time Noise Monitoring Stations
3.1.2.
The
noise monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1 shows the established Action/Limit Levels for
the monitoring works.
Table 3.2 Real Time Noise
Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2a* |
Electric Centre |
North Point |
RTN3 |
Po Leung Kuk Yu Lee Mo Fan
Memorial School |
Tin Hau |
RTN4 |
|
Remarks*: RTN2 was
relocated from Oil Street Community Liaison Centre to Electric Centre on 05 Oct
2012 and re-designated as RTN2a.
Noise Monitoring
Parameters, Frequency and Duration
3.1.3.
The construction noise level shall be measured in terms of
the A-weighted equivalent continuous sound pressure level (Leq). Leq (30
minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For
all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.4.
Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.5.
Real
time noise shall be carried out at the designated monitoring stations. The
following is an initial guide on the regular monitoring frequency for each
station on a 24 hours daily basis when noise generating activities are
underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
3.1.6.
If
construction works are extended to include works during the hours of 1900 –
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
3.1.7.
As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
3.1.8.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
3.1.9.
The
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency before deployment to the site
and during each site visit. Measurements may be accepted as valid only if the
calibration level from before and after the noise measurement agree to within
1.0 dB.
Air Quality Monitoring
Stations
3.2.1. The air quality monitoring stations for the Project
are listed and shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table
3.3 Air quality monitoring
Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Harbour Grand Hotel
Boundary Wall |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5b |
Pedestrian Plaza** |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (Western End of Podium) |
Central |
Remarks*: The location ID of monitoring
station CMA1b was updated as “Oil Street Site Office” in
Remarks**: With respect to the area handover, the air
quality monitoring station CMA5a at Children Playgrounds opposite to the
Pedestrian Plaza was relocated to the Pedestrian Plaza on 3 December 2014. The
station reference and location ID of the air quality monitoring station CMA5a
was updated as CMA5b and Pedestrian Plaza respectively.
Air quality monitoring
Parameters, Frequency and Duration
3.2.2. One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
3.2.3. All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
3.2.4. For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5. High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
·
0.6
– 1.7 m3 per minute adjustable flow range;
·
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable
of providing a minimum exposed area of 406 cm2;
·
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped
with a shelter to protect the filter and sampler;
·
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
Equipped
with a flow recorder for continuous monitoring;
·
Provided
with a peaked roof inlet;
·
Incorporated
with a manometer;
·
Able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
Easily
changeable filter; and
·
Capable
of operating continuously for a 24-hour period.
3.2.6. Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
3.2.7. Laboratory Measurement / Analysis
3.2.8. A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
3.2.9. Filter paper of size 8” x 10” shall be labelled
before sampling. It shall be a clean filter paper with no pinholes, and shall
be conditioned in a humidity-controlled chamber for over 24-hours and be
pre-weighed before use for the sampling.
3.2.10. After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
3.2.11. All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.0.1. Per EPD’s letter
dated 3 Aug 2012 (received by ET on 6 Aug 2012 through HyD), noise monitoring
at M8 – City Hall commenced on 7 Aug 2012, and the monitoring station M7e –
International Finance Centre (Eastern Podium) has become a reference station
starting from 7 Aug 2012.
4.0.2. Due to safety
concerns, the monitoring location for M4b – Victoria Centre has been finely
adjusted from 7 June 2012.
4.0.3. Monitoring for report of review baseline noise
level was performed from 11
4.0.4. The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various
contracts, latest status of work commencement and monitoring stations is shown
in Figure 2.1 and Figure 3.1. The
monitoring results are presented in according to the Individual Contract(s).
4.0.5. The Construction works under HY/2009/18
was confirm completed by the RSS from 25 April 2018 onwards. The associated
monitoring station for HY/2009/18 were temporary suspended from 27 April 2018
onwards.
4.0.6. The Construction works under HY/2009/15
was confirm completed by the RSS from 27 October 2017 onwards. The associated
monitoring station for HY/2009/15 were temporally suspended from 27 October
2017 onwards.
4.0.7. In the reporting period, the concurrent contracts are
as follows:
Contract
no. HY/2009/18 – Central –Wanchai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009
Contract
no. HK/2009/01 –Wanchai Development Phase II – Central –Wanchai Bypass at Hong
Kong Convention and Exhibition Centre under FEP-02/364/2009
Contract
no. HK/2009/02 Wanchai Development Phase II – Central- Wanchai Bypass at Wanchai
East under FEP-01/364/2009
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/200/B
Contract
no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 Section under
FEP-10/364/2009/B
Contract no. HY/2011/08 –Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/B
Contract no.
HY/2009/18 – Central – Wanchai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
4.1.1.
Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22
Table
4.1
Noise Monitoring Station for Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark: M7e has become a reference station starting from 7 Aug 2012
4.1.2. No action or limit level exceedance was
recorded in the March and April 2018 reporting period.
4.1.3. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1.
Contract no. HK/2009/01 - Wanchai Development Phase
II - Central - Wanchai Bypass at Hong Kong Convention and Exhibition Centre -
Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 - Wanchai
Development Phase II - Central - Wanchai Bypass at Wanchai East (CWB Tunnel)
under FEP-01/364/2009
4.1.4.
The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011
and HK/2009/02 under FEP-01/364/2009 is on 26
Table
4.2
Noise
Monitoring Stations
for Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Footbridge at Ex-Harbour Road Sports Centre |
4.1.5.
No action or limit level exceedance was
recorded in the March, April and May 2018 reporting period.
4.1.6.
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 4.1.
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
4.1.7. Noise monitoring for the tunnel works under
contract no. HY/2009/19 was commenced on 24
Table 4.4
Noise Monitoring
Stations for Contract no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Reporting period of March 2018
4.1.8.
One limit level exceedance was recorded at M6
HK Baptist Church Henrietta Secondary School on 06 March 2018 in the March 2018
reporting period.
After checking
with Contractor of HY/2009/19, concurrent saw cutting works and breaking works
was conducted opposite to the monitoring location and the above construction
works were observed as the major noise contribution during monitoring. As such,
the exceedances were considered as Project related. Remedial actions including
saw cutting works alone without concurrent operation of breaker and provision
of additional temporary noise barrier for cutting works were implemented by the
Contractor and no further exceedances was recorded during the additional
monitoring on 08 March 2018. The Contractor of HY/2009/19 was advised to avoid
future concurrent operation of major noise emanating works such as breaking and
saw cutting works to avoid potential cumulative impact.
4.1.9.
One action level exceedance regarding noise
emanation on 12 March 2018 under Contract HY/2009/19 was referred to the
Environmental Team on 27 March 2018 in the March 2018 reporting period.
After investigation, the exceedance was found
to be related to the breaking works conducted on IECL around YLMF memorial
school and Wharf Road causing noise nuisance to the nearby receivers. According
to ET follow up checking, the following enhancement measures were proposed and implemented
by the Contractor by 16 March 2018 including provide additional temporary noise
barrier and repair damaged or incomplete temporary noise barrier installed for
the breaking works, provide additional acoustics screen to the breaking tip in
addition to temporary noise barrier installed, provide covering of breaker tip
with acoustic material for noise reduction and conduct breaking works
intermittently.
Reporting period of April 2018
4.1.10.
No action or limit level exceedance was
recorded in the April 2018 reporting period.
Reporting period of May 2018
4.1.11.
No action or limit level exceedance was
recorded in the May 2018 reporting period.
4.1.12.
Noise monitoring results measured in this
reporting period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix 4.1 and the Notification of Exceedance can be
referred in Appendix 6.2.
Contract no. HY/2010/08 –
Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-09/364/2009/B
4.1.13. The commencement of construction works
for Contract no. HY/2010/08 under FEP-10/364/2009/B was on 02 September 2013.
Noise monitoring was commenced on 02 September 2013. The proposed divisions of
noise monitoring stations are summarized in Table 4.5 below.
Table 4.5
Noise Monitoring Stations
for Contract
no. HY/2010/08
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.14.
No action or limit level exceedance was recorded in the March, April and
May 2018 reporting period.
4.1.15.
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 4.1.
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
4.1.16. Noise monitoring for the Central
Interchange works under contract no. HY/2011/08 was commenced on 22 April 2011.The
proposed division of noise monitoring stations for Contract no. HY/2011/08 are
summarized in Table 4.6 below:
Table 4.6 Noise
Monitoring Stations for
Contract no. HY/2011/08
Station |
Description |
M4b |
Victoria Centre |
*M7e |
International Finance Centre (Eastern End of
Podium) |
M7w |
International Finance Centre (Western End of
Podium) |
M8 |
City Hall |
*
Remark: M7e has become a reference station starting from 7 Aug 2012
4.1.17.
No action or limit level exceedance was recorded in the March, April and
May 2018 reporting period.
4.1.18.
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 4.1
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corri