Contract
No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and
Testing Work (Stage 2) Environmental
Permit no. EP-364/2009/C, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-05/364/2009/A,
FEp-06/364/2009/a, FEp-07/364/2009/a, FEP-09/364/2009/B, fep-10/364/2009/B
and fep-11/364/2009/B Quarterly Environmental Monitoring
and Audit Report
- march 2015
to may 2015 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
18 June 2015 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
2.5 Principal Work and Activities
4.2. Real Time Noise Monitoring Results
5.4. Review of the Reasons for and the Implications of
Non-compliance
5.5. Summary of action taken in the event of and follow-up
on non-compliance
6. Complaints, Notification of Summons
and Prosecution
7. Cumulative Construction Impact due to
the Concurrent Projects
lIST
OF TABLES
Table I Principal Work
Activities for Contract no. HY/2009/18
Table II Principal
Work Activities for Contract no. HK/2009/01
Table III Principal Work Activities for
Contract no. HK/2009/02
Table IV Principal Work Activities for
Contract no. HY/2009/15
Table V Principal
Work Activities for Contract no. HY/2009/19
Table VI Principal Work Activities for Contract
no. HK/2012/08
Table VII Principal Work Activities for Contract
no. HY/2010/08
Table VIII Principal Work Activities for Contract no.
HY/2011/08
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 2.4 Principal Work Activities for
Contract no. HY/2009/18
Table 2.5 Principal Work Activities for
Contract no. HK/2009/01
Table 2.6 Principal
Work Activities for Contract no. HK/2009/02
Table 2.7 Principal
Work Activities for Contract no. HY/2009/15
Table 2.8 Principal
Work Activities for Contract no. HY/2009/19
Table 2.9 Principal
Work Activities for Contract no. HK/2012/08
Table 2.10 Principal Work
Activities for Contract no. HY/2010/08
Table 2.11 Principal Work
Activities for Contract no. HY/2011/08
Table 3.1 Noise
Monitoring Stations
Table 3.2 Real
Time Noise Monitoring Stations
Table 3.3 Air
Monitoring Stations
Table 4.1 Noise Monitoring Station
for Contract no. HY/2009/18
Table 4.2 Noise Monitoring Stations
for Contract nos. HK/2009/01 and HK/2009/02
Table 4.3 Noise Monitoring Station
for Contract nos. HY/2009/15
Table 4.4 Noise
Monitoring Stations for Contract no. HY/2009/19
Table 4.5 Noise Monitoring Stations for Contract
no. HY/2010/08
Table 4.6 Noise Monitoring Stations for Contract no.
HY/2011/08
Table 4.7 Real
Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.8 Air
Monitoring Stations for Contract no. HY/2009/18
Table 4.9 Air
Monitoring Stations for Contract no. HK/2009/01
Table 4.10 Air
Monitoring Station for Contract no. HK/2009/02
Table 4.11 Air
Monitoring Station for Contract no. HY/2009/15
Table 4.12 Air
Monitoring Stations for Contract no. HY/2009/19
Table 4.13 Air
Monitoring Stations for Contract no. HK/2012/08
Table 4.14 Air
Monitoring Stations for Contract no. HY/2010/08
Table 4.15 Air Monitoring Stations for Contract
no. HY/2011/08
Table 4.16 Details
of Waste Disposal for Contract no. HK/2009/01
Table 4.17 Details
of Waste Disposal for Contract no. HK/2009/02
Table 4.18 Details
of Waste Disposal for Contract no. HY/2009/18
Table 4.19 Details
of Waste Disposal for Contract no. HY/2009/15
Table 4.20 Details
of Waste Disposal for Contract no. HY/2009/19
Table 4.21 Details of Waste Disposal
for Contract no. HK/2012/08
Table 4.22 Details of Waste Disposal for Contract no.
HY/2012/08
Table 4.23 Details of
Waste Disposal for Contract no. HY/2011/08
Table 6.1 Cumulative
Statistics on Complaints
Table 6.2 Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 3.1 Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix
2.1 Environmental
Mitigation Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix 4.1 Noise Monitoring Results and
Graphical Presentations
Appendix 4.2 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 4.3 Air Quality Monitoring Results
and Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 6.2 Notification of Exceedance
Appendix 8.1 Construction Programme of
Individual Contracts
EXECUTIVE
SUMMARY
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB)
- Central Interchange under FEP-05/364/2009/
Major construction activities for Contract no. HY/2009/18 have been
commenced on 21
Table I Principal Work Activities for Contract
no. HY/2009/18
March 2015 |
April 2015 |
May 2015 |
Planting trees and shrubs Transplanting of trees Drainage works Trough structure construction
including excavation, concreting and waterproofing and backfill Road works Bridges construction |
Planting trees and shrubs Transplanting of trees Drainage works Trough structure construction
including excavation, concreting and waterproofing and backfill Road works Bridges construction |
Planting trees and shrubs Transplanting of trees Drainage works Trough structure construction
including excavation, concreting and waterproofing and backfill Road works Bridges construction |
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
Major construction activities
for Contract no. HK/2009/01 have been commenced on 25 August 2011. During this
reporting period, the principal work activities are summarized as below:
Table II Principal Work
Activities for Contract no. HK/2009/01
March 2015 |
April 2015 |
May 2015 |
Stage 1 Construction of roadside
barrier Stage 1 Demolition of temporary
upstand Stage 1 Construction of retaining wall
RW1 at slip road 2 Stage 2 ELS works Stage 2 Removal of 2nd layer of
strut/waling at Bay 7 Stage 2 Steel fixing and formwork
erection at Bay 7, 8 and 9 Stage 2 Rebar fixing of exhaust duct Stage 3 ELS excavation and strut
installing works Stage 3 Construction of box culvert
Bay 2 (base slab) and S5A and 5B salt water-main connection Stage 3 Construction of box culvert
Bay 3 to 6 Trench excavation works at A3-5B for sewage
pipeline at Fenwick Pier Street Cooling Main Installation (BI/BG/BF)
at Expo Drive East Outfall and BF at Fleming Road Installation works for Cooling Main
(BF)/ Salt Watermain (S3) / Fresh Watermain (F3) Work zone X1-1 to X1-3 Construction of C3-1 Outfall Reinstatement of cable draw pits at Lung
King Street was in progress |
Stage 1 Construction of roadside
barrier and defect rectification Stage 2 Backfilling of retaining wall
RW1 at slip road 2 Stage 2 ELS and demolition works of
bulkhead wall at Bay 10 Stage 2 Steel fixing and formwork
erection at Bay 7, 8 and 9 OHVD Stage 2 Construction of exhaust duct
at slip road 3 Stage 3 ELS excavation and strut
installing works Stage 3 Base slab construction of box
culvert Bay 2 and Bay 7 Stage 3 Construction of box culvert
Bay 1 Stage 3 Construction of Outfall at
Expo Drive East and backfilling work Sewerage pipeline at Fenwick Pier
Street Pipe laying works for Cooling Main
(BI/BG/BF) Work zone X1-1 to X1-4 at Fleming Road Pipe laying works of C3-1B and
backfilling works of C3-1A |
Stage 1 Construction of roadside
barrier was completed and defect rectification Stage 2 Construction of exhaust duct Stage 2 Construction of base slab Bay
10 Stage 3 ELS excavation and strut
installing work Stage 3 Box culvert diversion Stage 3 Base slab construction of box
culvert Stage 3 Construction works of Outfall
at Expo Drive East Cooling Main Installation (BI/BG) at
Expo Drive East Removal of abandoned cooling main
(P7/P8) at Convention Avenue Sewerage Pipeline A3-4B at Fenwick
Pier Street Installation works for Cooling Main
(BI/BG) / Salt Watermain (S3)/ Fresh Watermain (F3) Reinstatement of Expo Drive East |
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
Major construction activities
for Contract no. HK/2009/02 have been commenced on 26
Table III Principal Work Activities for Contract no.
HK/2009/02
March 2015 |
April 2015 |
May 2015 |
Core hole at -19mPD for bulk head wall
demolition and wire cut Blinding layer application for base
slab
Waterproofing application for base slab Concreting for base slab Struts dismantling Construction of capping beam at the
west side Excavation at the west side Installation of observation well, dewatering
well, piezometer at the east side Grouting and shear pin installation
for all D-wall panels at the east side Packer tests |
Bulkhead wall breakthrough by Robot at
the north side Bulkhead wall breakthrough by saw cut
and wire cut Waterproofing application for north
and south walls Rebar fixing at the north wall from
Bay 1 to Bay 4 Rebar fixing at the south wall of Bay
3 and Bay 4 Formworks erection was now in progress
at central wall of Bay 4, at south wall and north wall of Bay 1 Concrete cast for central wall at Bay
1, Bay 2 and Bay 3 Excavation at the west side and struts
installation. Packer tests at the east side Excavation at the east side and
welding for struts installation Installation of observation well, dewatering
well, piezometer at the east side Pump test set up and schedule for pump
test |
Removal of scaffolding and clearance
works Bulkhead wall breakthrough by Robot at
-12.9mPD upper part Dismantling of temporary working
platform Preparation for breakthrough the lower
part by Robot Concrete cast for central wall at Bay
4 Concrete cast for south side wall at
Bay 1, Bay 2, Bay 3 and Bay 4 Concrete cast for north side wall at
Bay 1, Bay 2, Bay 3 and Bay 4 Concrete cast for OHVD base slab at
Bay 1 Rebar fixing and formworks erection
for OHVD side wall at Bay 1 Pump test Excavation at Strut Layer S2 of the
west side Excavation at Strut Layer S2 of the
east side |
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
Major construction activities
for Contract no. HY/2009/15 has been commenced on 13 July 2011. During this
reporting period, the principal work activities are summarized as below:
Table IV Principal Work Activities for Contract no.
HY/2009/15
April
2015 |
May
2015 |
|
Mined Tunnel drill-and-break works at
East and West Portal Permanent lining structure at Mined
Tunnel Construction of diaphragm wall at
TPCWAW |
Mined Tunnel drill-and-break works at
East and West Portal Permanent lining structure at Mined
Tunnel Construction of diaphragm wall at
TPCWAW Fabrication of first layer of ELS for
TPCWAW |
Mined Tunnel drill-and-break works at
East and West Portal Permanent lining structure at Mined
Tunnel Construction of diaphragm wall at
TPCWAW |
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
Major construction activities
for Contract no. HY/2009/19 have been commenced on March 2011. During this
reporting period, the principal work activities are summarized as below:
Table V Principal Work
Activities for Contract no. HY/2009/19
March 2015 |
April 2015 |
May 2015 |
Bored piling (Land) Demolition of ELS for Cut &Cover
Tunnel and EVB Laying of 1350f pipe Pre-bored H-pile for Admin. Building
continue Construction of Bridge E Installation of Noise
Barrier/enclosure IECL Road modification and removal of
Median Barrier Construction of TB Bridge Abutment D12 construction Saw cut of parapet at IEC East bound Construction for TA2 bridge Construction of temporary steel tower
for IEC demolition JBI Gantry Installation |
Demolition of ELS for Cut &Cover
Tunnel and EVB Pre-bored H-pile for Approach Ramp IECL Road modification and removal of
Median Barrier Abutment D12 construction Saw cut of parapet at IEC East bound Construction of TA2 bridge Construction of temporary steel tower
for IEC demolition Saw cut of existing west fast lane of
IEC bridge Demolition of bulk head wall between
C15 to C19 Column modification at F1 to F8 |
Demolition of ELS for EVB Pre-bored H-pile for Pier 23 Construction of TA2 bridge Construction of temporary steel tower
for IEC demolition Saw cut of existing west fast lane of
IEC bridge Demolition of bulk head wall between
C15 to C19 Column modification at F1 to F8 |
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
Table VI Principal
Work Activities for Contract no. HK/2012/08
March 2015 |
April 2015 |
May 2015 |
Diaphragm wall construction Installation of dewatering wells Grouting Construction of ELS at MVB Construction of ELS at Zone A1 |
Diaphragm wall construction Installation of dewatering wells Grouting Construction of ELS at MVB Excavation and installation of lateral
support at top-down area Pre-bored H-pile construction |
Diaphragm wall construction Installation of dewatering wells Grouting Construction of ELS at MVB Construction of top-down slab Pre-bored H-pile construction |
Contract
no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 section under
FEP-10/364/2009B
Table VII Principal Work
Activities for Contract no. HY/2010/08
March 2015 |
April 2015 |
May 2015 |
Tree transplanting works next to W1, Drainage improvement works, Sheet piling works, Excavation and Lateral Support for
U-structure works, Erection of noise absorption
sheetings, Pipe piling & grouting works, Utility diversion works, Waterproofing works, Construction of Bowling Green Office
& Construction of ramp for TTA stage II –
eastbound |
Drainage improvement works, Sheet piling works, Excavation and Lateral Support for
U-structure works, Erection of noise absorption
sheetings, Pipe piling & grouting works, Utility diversion works, Waterproofing works, Provisional of Bowling Green, Milling & paving works for TTA
stage II – westbound &. Construction of ramp for TTA stage II
– eastbound |
Tree protection works next to existing
BGO Drainage improvement works, Sheet piling works, Excavation and Lateral Support for
U-structure works, Erection of noise absorption
sheetings, Pipe piling & grouting works, Utility diversion works, Waterproofing works, Renovation works for Bowling Green
Office, Reprovisional of Bowling Green & Demolition of an existing bowling
green office |
Contract
no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
Table VIII Principal Work
Activities for Contract no. HY/2011/08
March 2015 |
April 2015 |
May 2015 |
West Ventilation Building structure construction
Install VE panels bracket and thermal
barrier for Tunnel Site preparation for East Vent Shaft |
West Ventilation Building structure
construction Install VE panels bracket and thermal
barrier for Tunnel Construct reinforcement concrete
structure for EVS |
West Ventilation Building structure
construction Install VE panels bracket and thermal
barrier for Tunnel Construct reinforcement concrete
structure for EVS |
Noise Monitoring
Real
time Noise Monitoring
Air Quality Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
“I live in a building next to Gloucester
Road in Causeway Bay. Recently, I am suffering from unnecessary light source
from the construction site. The banners of the construction companies are
always illuminated with very bright lights.”
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009C and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-09/364/2009/B, FEP-10/364/2009/B and
FEP-11/364/2009/B to implement the Environmental Monitoring and
Audit (EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of
EM&A Manual and “Environmental Monitoring and Audit Requirements”
under Particular Specification Section 27.
1.1.3. This report documents the finding of EM&A
works during the period from March
2015 to May 2015.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements – summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results – summarizes the monitoring results
obtained in the reporting period.
Section 5 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB)
and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately 4.5 km
in length, and tunnel approximately 3.7 km in length defined from the
connection with the existing Rumsey Street Flyover in Central, through to a
connection with the existing Island Eastern Corridor to the east of the
Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street
Flyover to provide road connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road
system in the Wan Chai North and
·
Associated road lighting, road signing, traffic
control and surveillance system; and
·
Other associated works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require Environmental
Permits (EPs) to be granted by the DEP before they may be either constructed or
operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
In
the reporting period, all the contracts were commenced and contract no.
04/HY/2006 had been completed. The details of individual contracts are
summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel ( |
DP1 |
13 July 2011 |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
DP works under |
HY/2010/08 |
Central- Wanchai Bypass Tunnel – Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning |
DP1 |
8 October 2014 |
2.3.3.
The construction works of Contract no.
04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street under FEP-04/364/2009/A was completed, and the FEP was surrendered by
the Contractor on 11 February 2011.
2.3.4.
Construction of bored pile E3B under HY/2009/17 was confirmed
completed and the respective work area under FEP-03/364/2009 was handover and inspected
under HY/2009/19 from 19 Dec 2012 onwards. Subsequently, the FEP-03/364/2009
was surrendered by the Contractor on 28 March 2013.
2.3.5.
Construction works under HK/2010/06 was confirmed completed and the
respective work area under FEP-08/364/2009/A was handover and inspected under
HK/2012/08 from 22 Sep 2014 onwards. Subsequently, the FEP-08/364/2009/A was
surrendered by the Contractor on 3 October 2014.
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3.
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Chun
Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Mr. Simon Liu |
2162 9909 |
2634 1626 |
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack
Chu |
9775 2467 |
|||
Environmental
Officer |
Mr. Wendy
Ng |
9803 0057 |
|||
Environmental
Supervisor |
Mr. Connie Chan |
2162 9935 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827 9996 |
Project Manager |
Mr. Alfred Leung |
3658-3022 |
|||
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
|
9286 9208 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214
7700 |
2140 6799 |
Deputy Site Agent |
Mr Roger Wong |
2214
7703 |
|||
Environmental Officer |
Ms. |
2823
1161 |
|||
Environmental Engineer |
Mr. Chris Chan |
2214 7721 |
|||
Assistant Environmental Engineer |
Mr. Penny Yiu |
2214
7738 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ray Cheng |
22147742 |
|||
Environmental Supervisor |
Bosco Lee |
22147711 |
|||
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. K C Cheung |
2823 7813 |
2566 2192 |
Site Manager |
Mr. Y.Huo |
3557 6368 |
|||
Contractor’s
Representative |
Mr. Gene Cheung |
3557
6395 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Ms Esther Choi |
35576348 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N.
Lai |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Eddie
Chung |
9193
8871 |
|||
Site
Agent |
Mr. Keith
Tse |
9095
7922 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Y.L.
Ho |
6050
4919 |
|
||
China |
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung
Kit Cheung |
3557
6399 |
3465 2899 |
Project
Manager |
Chan
Ying Lun |
9812
0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467
4299 |
|||
Site
Agent |
Dave
Chan |
3467
4277 |
|||
Environmental
Officer |
C.M.
Wong |
3557
6464 |
|||
Environmental
Supervisor |
Louis
Lam Tsz Kwan |
3557
6470 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Project
Manager |
Paul
Evans |
2823
1111 |
21406799 |
Site
Agent |
Colman Wong |
9730
0806 |
|||
Environmental
Officer |
Chris Chan |
9765
6151 |
|||
Environmental
Supervisor |
Penny Yiu |
2214
7738 |
|||
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
2.5.1.
Major construction activities for Contract no.
HY/2009/18 have been commenced on 21
Table 2.4 Principal Work Activities
for Contract no. HY/2009/18
March
2015 |
April
2015 |
May
2015 |
Planting trees and shrubs
Transplanting of trees
Drainage works
Trough structure construction including excavation, concreting and
waterproofing and backfill
Road works
Bridges construction |
Planting trees and shrubs
Transplanting of trees
Drainage works
Trough structure construction including excavation, concreting and
waterproofing and backfill
Road works
Bridges construction |
Planting trees and shrubs
Transplanting of trees
Drainage works
Trough structure construction including excavation, concreting and
waterproofing and backfill
Road works
Bridges construction |
2.5.2. Major
construction activities for Contract no. HK/2009/01 have been commenced on 25
August 2011. During this reporting period, the principal work activities are
summarized in Table2.5:
Table 2.5 Principal Work Activities
for Contract no. HK/2009/01
March
2015 |
April
2015 |
May
2015 |
Stage 1 Construction of roadside barrier
Stage 1 Demolition of temporary upstand
Stage 1 Construction of retaining wall RW1 at slip road 2
Stage 2 ELS works
Stage 2 Removal of 2nd layer of strut/waling at Bay 7
Stage 2 Steel fixing and formwork erection at Bay 7, 8 and 9
Stage 2 Rebar fixing of exhaust duct
Stage 3 ELS excavation and strut installing works
Stage 3 Construction of box culvert Bay 2 (base slab) and S5A and 5B
salt water-main connection
Stage 3 Construction of box culvert Bay 3 to 6
Trench excavation works at A3-5B for sewage pipeline at Fenwick Pier
Street
Cooling Main Installation (BI/BG/BF) at Expo Drive East Outfall and BF
at Fleming Road
Installation works for Cooling Main (BF)/ Salt Watermain (S3) / Fresh
Watermain (F3)
Work zone X1-1 to X1-3
Construction of C3-1 Outfall
Reinstatement of cable draw pits at Lung King Street was in progress |
Stage 1 Construction of roadside barrier and defect rectification
Stage 2 Backfilling of retaining wall RW1 at slip road 2
Stage 2 ELS and demolition works of bulkhead wall at Bay 10
Stage 2 Steel fixing and formwork erection at Bay 7, 8 and 9 OHVD
Stage 2 Construction of exhaust duct at slip road 3
Stage 3 ELS excavation and strut installing works
Stage 3 Base slab construction of box culvert Bay 2 and Bay 7
Stage 3 Construction of box culvert Bay 1
Stage 3 Construction of Outfall at Expo Drive East and backfilling
work
Sewerage pipeline at Fenwick Pier Street
Pipe laying works for Cooling Main (BI/BG/BF)
Work zone X1-1 to X1-4 at Fleming Road
Pipe laying works of C3-1B and backfilling works of C3-1A |
Stage 1 Construction of roadside barrier was completed and defect
rectification
Stage 2 Construction of exhaust duct
Stage 2 Construction of base slab Bay 10
Stage 3 ELS excavation and strut installing work
Stage 3 Box culvert diversion
Stage 3 Base slab construction of box culvert
Stage 3 Construction works of Outfall at Expo Drive East
Cooling Main Installation (BI/BG) at Expo Drive East
Removal of abandoned cooling main (P7/P8) at Convention Avenue
Sewerage Pipeline A3-4B at Fenwick Pier Street
Installation works for Cooling Main (BI/BG) / Salt Watermain (S3)/
Fresh Watermain (F3)
Reinstatement of Expo Drive East |
2.5.3. Major
construction activities for Contract no. HK/2009/02 have been commenced on 26
Table 2.6 Principal Work Activities
for Contract no. HK/2009/02
March
2015 |
April
2015 |
May
2015 |
Core hole at -19mPD for bulk head wall demolition and wire cut
Blinding layer application for base slab
Waterproofing application for base slab
Concreting for base slab
Struts dismantling
Construction of capping beam at the west side
Excavation at the west side
Installation of observation well, dewatering well, piezometer at the east
side
Grouting and shear pin installation for all D-wall panels at the east
side
Packer tests |
Bulkhead wall breakthrough by Robot at the north side
Bulkhead wall breakthrough by saw cut and wire cut
Waterproofing application for north and south walls
Rebar fixing at the north wall from Bay 1 to Bay 4
Rebar fixing at the south wall of Bay 3 and Bay 4
Formworks erection was now in progress at central wall of Bay 4, at
south wall and north wall of Bay 1
Concrete cast for central wall at Bay 1, Bay 2 and Bay 3
Excavation at the west side and struts installation.
Packer tests at the east side
Excavation at the east side and welding for struts installation
Installation of observation well, dewatering well, piezometer at the east
side
Pump test set up and schedule for pump test |
Removal of scaffolding and clearance works
Bulkhead wall breakthrough by Robot at -12.9mPD upper part
Dismantling of temporary working platform
Preparation for breakthrough the lower part by Robot
Concrete cast for central wall at Bay 4
Concrete cast for south side wall at Bay 1, Bay 2, Bay 3 and Bay 4
Concrete cast for north side wall at Bay 1, Bay 2, Bay 3 and Bay 4
Concrete cast for OHVD base slab at Bay 1
Rebar fixing and formworks erection for OHVD side wall at Bay 1
Pump test
Excavation at Strut Layer S2 of the west side
Excavation at Strut Layer S2 of the east side |
2.5.4. Major
construction activities for Contract no. HY/2009/15 have been commenced on 13
July 2011. During this reporting period, the principal work activities are
summarized in Table 2.7:
Table 2.7 Principal Work Activities
for Contract no. HY/2009/15
March
2015 |
April
2015 |
May
2015 |
Mined Tunnel drill-and-break works at East and West Portal
Permanent lining structure at Mined Tunnel
Construction of diaphragm wall at TPCWAW |
Mined Tunnel drill-and-break works at East and West Portal
Permanent lining structure at Mined Tunnel
Construction of diaphragm wall at TPCWAW
Fabrication of first layer of ELS for TPCWAW |
Construction of OHVD and base slab at Mined Tunnel
Inner bench excavation
Permanent lining structure at Mined Tunnel
Construction of diaphragm wall at TPCWAW
Installation of king post
Fabrication of first layer of ELS for TPCWAW
Excavation of ELS at TPCWAW |
2.5.5. Major
construction activities for Contract no. HY/2009/19 have been commenced on
March 2011. During this reporting period, the principal work activities are
summarized in Table 2.8:
Table 2.8 Principal Work Activities
for Contract no. HY/2009/19
March
2015 |
April
2015 |
May
2015 |
Bored piling (Land)
Demolition of ELS for Cut &Cover Tunnel and EVB
Laying of 1350f pipe
Pre-bored H-pile for Admin. Building continue
Construction of Bridge E
Installation of Noise Barrier/enclosure
IECL Road modification and removal of Median Barrier
Construction of TB Bridge
Abutment D12 construction
Saw cut of parapet at IEC East bound
Construction for TA2 bridge
Construction of temporary steel tower for IEC demolition
JBI Gantry Installation |
Demolition of ELS for Cut &Cover Tunnel and EVB
Pre-bored H-pile for Approach Ramp
IECL Road modification and removal of Median Barrier
Abutment D12 construction
Saw cut of parapet at IEC East bound
Construction of TA2 bridge
Construction of temporary steel tower for IEC demolition
Saw cut of existing west fast lane of IEC bridge
Demolition of bulk head wall between C15 to C19
Column modification at F1 to F8 |
Demolition of ELS for EVB
Pre-bored H-pile for Pier 23
Construction of TA2 bridge
Construction of temporary steel tower for IEC demolition
Saw cut of existing west fast lane of IEC bridge
Demolition of bulk head wall between C15 to C19
Column modification at F1 to F8
|
2.5.6.
Major construction activities for
Contract no. HK/2012/08 have been commenced on March 2013. During the reporting
period, the principal work activities are summarized in Table 2.10
Table 2.9 Principal Work Activities for Contract no. HK/2012/08
March
2015 |
April
2015 |
May
2015 |
Diaphragm wall construction
Installation of dewatering wells
Grouting
Construction of ELS at MVB
Construction of ELS at Zone A1 |
Diaphragm wall construction
Installation of dewatering wells
Grouting
Construction of ELS at MVB
Excavation and installation of lateral support at top-down area
Pre-bored H-pile construction |
Diaphragm wall construction
Installation of dewatering wells
Grouting
Construction of ELS at MVB
Construction of top-down slab
Pre-bored H-pile construction |
2.5.7.
Major construction activities for Contract no.HY/2010/08 have been commenced
on March 2013. During the reporting period, the principal work activities are
summarized in Table 2.11
Table 2.10 Principal Work Activities for Contract no. HY/2010/08
March
2015 |
April
2015 |
May
2015 |
Tree transplanting works next to W1,
Drainage improvement works,
Sheet piling works,
Excavation and Lateral Support for U-structure works,
Erection of noise absorption sheetings,
Pipe piling & grouting works,
Utility diversion works,
Waterproofing works,
Construction of Bowling Green Office &
Construction of ramp for TTA stage II – eastbound |
Drainage improvement works,
Sheet piling works,
Excavation and Lateral Support for U-structure works,
Erection of noise absorption sheetings,
Pipe piling & grouting works,
Utility diversion works,
Waterproofing works,
Provisional of Bowling Green,
Milling & paving works for TTA stage II – westbound &.
Construction of ramp for TTA stage II – eastbound |
Tree protection works next to existing BGO
Drainage improvement works,
Sheet piling works,
Excavation and Lateral Support for U-structure works,
Erection of noise absorption sheetings,
Pipe piling & grouting works,
Utility diversion works,
Waterproofing works,
Renovation works for Bowling Green Office,
Reprovisional of Bowling Green &
Demolition of an existing bowling green office |
2.5.8.
Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009B
Table 2.11 Principal Work Activities for Contract no. HY/2011/08
March
2015 |
April
2015 |
May
2015 |
West Ventilation Building structure construction
Install VE panels bracket and thermal barrier for Tunnel
Site preparation for East Vent Shaft |
West Ventilation Building structure construction
Install VE panels bracket and thermal barrier for Tunnel
Construct reinforcement concrete structure for EVS |
West Ventilation Building structure construction
Install VE panels bracket and thermal barrier for Tunnel
Construct reinforcement concrete structure for EVS |
2.5.9.
Implementation status of the recommended mitigation measures
during this reporting period is presented in Appendix 2.1.
3.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
3.1 and Figure 3.1. Appendix 3.1 shows
the established Action/Limit Levels for the monitoring works.
Table
3.1 Noise Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun
Area |
M3a |
Tung Lo Wan
Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark 1: Location
ID has been updated from M7 to M8 for City Hall
* Remark 2: M7e has
become a reference station starting from 7 Aug 2012
Real time Noise Monitoring Stations
3.1.2.
The
noise monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1
shows the established Action/Limit Levels for the monitoring works.
Table 3.2 Real Time Noise
Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2a |
Electric Centre |
North Point |
RTN3 |
Pok Leung Kuk Yu |
Tin Hau |
RTN4 |
|
* RTN2 was relocated from
Oil Street Community Liaison Centre to Electric Centre on
05 Oct 2012 and re-designated
as RTN2a.
Noise Monitoring
Parameters, Frequency and Duration
3.1.3.
The construction noise level shall be measured in terms of
the A-weighted equivalent continuous sound pressure level (Leq). Leq (30
minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For
all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.4.
Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.5.
Real
time noise shall be carried out at the designated monitoring stations. The
following is an initial guide on the regular monitoring frequency for each
station on a 24 hours daily basis when noise generating activities are
underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
3.1.6.
If
construction works are extended to include works during the hours of 1900 –
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
3.1.7.
As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
3.1.8.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
3.1.9.
The
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency before deployment to the site
and during each site visit. Measurements may be accepted as valid only if the
calibration level from before and after the noise measurement agree to within
1.0 dB.
Air Quality Monitoring
Stations
3.2.1. The air monitoring stations for the Project are
listed and shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table
3.3 Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Site Office* |
North Point |
CMA2a |
|