Contract
No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and
Testing Work (Stage 2) Environmental
Permit no. EP-364/2009/B, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEp-07/364/2009/a,
FEp-08/364/2009/a , FEP-09/364/2009/B, fep-10/364/2009/B and
fep-11/364/2009/B Quarterly Environmental Monitoring
and Audit Report
- March 2014
to May 2014 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
23 June 2014 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
2.5 Principal Work and Activities
4.2. Real Time Noise Monitoring Results
5.4. Review of the Reasons for and the Implications of Non-compliance
5.5. Summary of action taken in the event of and follow-up
on non-compliance
6. Complaints, Notification of Summons
and Prosecution
7. Cumulative Construction Impact due to
the Concurrent Projects
lIST
OF TABLES
Table I Principal Work Activities for Contract no.
HY/2009/18
Table II Principal Work Activities for Contract no. HK/2009/01
Table III Principal Work Activities for Contract no. HK/2009/02
Table IV Principal
Work Activities for Contract no. HY/2009/15
Table V Principal Work Activities for Contract no. HY/2009/19
Table
VI Principal Work Activities for
Contract no. HK/2010/06
Table
VII Principal Work Activities for
Contract no. HK/2012/08
Table VIII Principal Work Activities for Contract no. HY/2010/08
Table
IV Principal Work Activities for Contract no. HY/2011/08
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 2.4 Principal
Work Activities for Contract no. HY/2009/18
Table 2.5 Principal
Work Activities for Contract no. HK/2009/01
Table 2.6 Principal
Work Activities for Contract no. HK/2009/02
Table 2.7 Principal
Work Activities for Contract no. HY/2009/15
Table 2.8 Principal
Work Activities for Contract no. HY/2009/19
Table 2.9 Principal Work Activities for Contract
no. HK/2010/06
Table 2.10 Principal
Work Activities for Contract no. HK/2012/08
Table 2.11 Principal Work Activities for Contract no. HY/2010/08
Table 2.12 Principal Work
Activities for Contract no. HY/2011/08
Table 3.1 Noise
Monitoring Station
Table 3.2 Real
Time Noise Monitoring Station
Table 3.3 Air
Monitoring Stations
Table 4.1
Noise
Monitoring Station for Contract no. HY/2009/18
Table 4.2
Noise
Monitoring Stations for Contract nos. HK/2009/01 and HK/2009/02
Table 4.3
Noise
Monitoring Station for Contract nos. HY/2009/15
Table 4.4 Noise Monitoring
Stations for Contract no. HY/2009/19
Table 4.5 Real
Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.6 Air
Monitoring Stations for Contract no. HY/2009/18
Table 4.7 Air
Monitoring Stations for Contract no. HK/2009/01
Table 4.8 Air
Monitoring Station for Contract no. HK/2009/02
Table 4.9 Air
Monitoring Station for Contract no. HY/2009/15
Table 4.10 Air
Monitoring Stations for Contract no. HY/2009/19
Table 4.11 Details
of Waste Disposal for Contract no. HK/2009/01
Table 4.12 Details
of Waste Disposal for Contract no. HK/2009/02
Table 4.13 Details
of Waste Disposal for Contract no. HY/2009/18
Table 4.14 Details
of Waste Disposal for Contract no. HY/2009/15
Table 4.15 Details
of Waste Disposal for Contract no. HY/2009/19
Table
4.16 Details of Waste Disposal for
Contract no. HK/2010/06
Table 4.17 Details of Waste
Disposal for Contract no. HK/2012/08
Table
4.18 Details of Waste Disposal for
Contract no. HY/2012/08
Table 6.1 Cumulative
Statistics on Complaints
Table 6.2 Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 3.1 Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix
2.1 Environmental
Mitigation Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix
4.1 Noise
Monitoring Results and Graphical Presentations
Appendix 4.2 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix
4.3 Air
Quality Monitoring Results and Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 6.2 Notification of Exceedance
Appendix 8.1 Construction Programme of
Individual Contracts
EXECUTIVE
SUMMARY
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB)
- Central Interchange under FEP-05/364/2009/
Major construction activities for Contract no. HY/2009/18 have been
commenced on 21
Table I Principal Work
Activities for Contract no. HY/2009/18
March 2013 |
April 2014 |
May 2014 |
Excavation of
trial pit
Transplanting of
trees
Drainage works
Tunnel works
including scaffolding erection, excavation, OHVD installation, roadside
barriers, top and base slab construction
Trough structure
construction and associated drilling and grouting
Road works
Bridges
construction |
Excavation of trial
pit
Transplanting of
trees
Drainage works
Tunnel works
including scaffolding erection, excavation, OHVD installation, roadside
barriers, top and base slab construction
Trough structure
construction and associated drilling and grouting
Road works
Bridges
construction |
Excavation of
trial pit
Transplanting of
trees
Drainage works
Tunnel works
including scaffolding erection, excavation, OHVD installation, roadside
barriers, top and base slab construction
Trough structure
construction and associated drilling and grouting
Road works
Bridges
construction |
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at
Major construction activities
for Contract no. HK/2009/01 have been commenced on 25 August 2011. During this
reporting period, the principal work activities are summarized as below:
Table II Principal Work Activities for Contract no.
HK/2009/01
March 2013 |
April 2014 |
May 2014 |
Stage 1 tunnel excavation work to -5.5
mPD including ELS works for 2nd layer Bay 5 and Bay 6 blinding layers Ground treatment works and guide wall
construction at the promenade deck area demolition of the existing pump
house. Installation of pre-bored H-piles Construction of D wall at C1/C2
interface and CSD for pipe pile wall P2 Plant demobilization Removal of silos Road diversion works for the
construction of temporary road at Expo Drive East UU diversion at both south and north
junction. |
New temporary road for diversion of
Expo Drive East Stage 1 tunnel excavation work Installation of pre-bored H-piles Construction of D-wall for the remaining
south D-wall panels at Stage 2 Discharge cooling main laying works
for BI, BG & BF Saltwater main laying works for S8B at
Zone A5-4 and A5-6 at Harbor Road Tree transplanting at the planter
areas near Hong Kong Culture Centre at Tsim Sha Tsui Trimming works at Fairway |
Demolition work of the existing Expo
Drive East Bridge Trench excavation at both northern and
southern ends of existing Expo Drive East Bridge Stage 1 tunnel blinding layer Stage 1 tunnel structure work Excavation & fabrication at tunnel Installation of pre-bored H-piles at
the HKCEC water channel by t Installation of pre-bored H-piles at
the area adjacent to new temporary road Construction of D-wall for the
remaining south D-wall panels at Stage 2 Discharge cooling main laying works
for BI, BG & BF Saltwater main laying works for S8B Trimming works at Fairway The removal work for abandoned
equipment at lower portion of existing P3 & P4 pump houses The removal work for abandoned
equipment for existing P7 & P9 pump houses |
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
Major construction activities
for Contract no. HK/2009/02 have been commenced on 26
Table III Principal Work
Activities for Contract no. HK/2009/02
March 2013 |
April 2014 |
May 2014 |
Casting of OHVD and upper side wall at
Westbound are as follows: Casting for roof slab at Bay 1 , Bay
3, Bay 4 and Bay 7 Rebar fixing at Bay 6. Scaffolding removal of Bay 2 Concreting of D-wall Panel at Tunnel
Portion 2 Casting of bored pile nos. PC 28, PC
30, PC 32 and PN29 Installation of Bored Pile Nos. PN28. Ground treatment for D-wall
construction at Panel Nos. P97 – C105 Guide wall and ground treatment for
D-wall construction at Panel Nos. C
Concreting of 2 nos. D-wall Panels for Tunnel Portion 6 |
Casting of roof Slab at Bay 4a, Bay 5, Bay 6 and Bay 8 Water testing on cracks at roof
slab. The crack mapping for tunnel top slab
from Bay 2 to Bay 4. Removal of ELS at S3 Level. Removal at Bay 4 was now in progress. Eastbound scaffolding removal of Bay 1
to Bay 4 Westbound scaffolding removal at Bay 3
and Bay 4 Concreting and grouting of 6 nos.
D-wall Panel Complete demobilization of D-Wall
plant, including the silo at northern seawall near Box Culvert N1 outfall. Casting of 4 nos. bored pile nos.
PN28, PN32, PN33 and PC29. Completing total 60.7% (17 out of 28
nos.) Installation of Bored Pile Nos. PS30 Ground treatment for D-wall
construction at Panel Nos. P97 – C105 Plant mobilization for D-Wall
construction |
Water test on cracks at roof slab Removal of ELS at S3 Level The crack mapping for tunnel top slab Loading Transfer for King Post at top
slab Preparation works for horizontal CJ
slab construction at Bay 1 Dismantling of scaffolding along the
eastbound base slab and 50% along westbound base slab Scaffolding removal at OHVD of
eastbound and westbound Toe grouting & interfacing coring
for southern D-Wall Transferal of D-Wall plant from Tunnel
Portion 2 to Tunnel Portion 3 & 4, including the BC-Cutter and Crane Removal of silo at northern seawall
near Box Culvert N1 outfall Excavation for remaining 2 bored pile
nos. PS15 and PS16 3 nos. D-wall Panel were concreted in
the report period P99, P130 and P145 Critical D-wall interfacing with the
footprint of temporary bridges for HHR Flyover Diversion (Stage 2)
implementation Construction of D-wall panels P98,
P131 and P146 |
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
Major construction activities
for Contract no. HY/2009/15 has been commenced on 13 July 2011. During this
reporting period, the principal work activities are summarized as below:
Table IV Principal Work
Activities for Contract no. HY/2009/15
April
2014 |
May
2014 |
|
Tunnel construction at TS2, TS4 &
TPCWAE Dismantling of struts at TS4 &
TPCWAE Mined Tunnel drill-and-break works and
installation of steel ribs at East and West Portal. Mined tunnel lining construction |
Tunnel construction at TS2, TS4 &
TPCWAE Dismantling of struts at TS4 &
TPCWAE Mined Tunnel drill-and-break works and
installation of steel ribs at East and West Portal. Mined tunnel lining construction |
Tunnel construction (shaft) at TPCWAE Dismantling of struts at TS2, TS4
& TPCWAE Mined Tunnel drill-and-break works and
installation of steel ribs at East and West Portal. Mined tunnel lining construction |
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
Major construction activities
for Contract no. HY/2009/19 have been commenced on March 2011. During this
reporting period, the principal work activities are summarized as below:
Table V Principal Work Activities for Contract no.
HY/2009/19
March 2013 |
April 2014 |
May 2014 |
Road works at Watson Road Bored piling (Land) Removal of strut at ELS Construction of Pile cap, column and
cross-head (Land) Removal of marine platform Construction of Dolphin Cap ELS, EVB and Cut & Cover Tunnel Installation of dewatering well Laying of 1500 pipe Launching of segments Extraction of temporary pile from
marine section Construction of bridge TA1 Pre-bored H-pile for Admin. Building
commenced |
Road works at Watson Road Bored piling (Land) Removal of strut at ELS Construction of Pile cap, column and
cross-head (Land) Removal of marine platform Construction of Dolphin Cap ELS, EVB and Cut & Cover Tunnel Installation of dewatering well Laying of 1500 pipe Launching of segments Extraction of temporary pile from
marine section Construction of bridge TA1 Pre-bored H-pile for Admin. Building
commenced U-beam installation commenced Parapet construction commenced Wing slab extension for segment
commenced Construction of TD bridge commenced |
Road works at Watson Road Bored piling (Land) Removal of strut at ELS Removal of marine platform Construction of Dolphin Cap ELS, EVB and Cut & Cover Tunnel Installation of dewatering well Laying of 1500 pipe Launching of segments Extraction of temporary pile from
marine section Construction of bridge TA1 Pre-bored H-pile for Admin. Building
commenced U-beam installation commenced Parapet construction commenced Wing slab extension for segment
commenced Construction of TD bridge commenced |
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
Table
VI Principal Work Activities for
Contract no. HK/2010/06
March 2013 |
April 2014 |
May 2014 |
Installation of protection layer for
precast unit |
Installation of protection layer for
precast unit |
Completion of laying protection board Preparation works for sealing of cross
wall opening Diversion of power supply |
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
Table VII Principal Work Activities
for Contract no. HK/2012/08
March 2013 |
April 2014 |
May 2014 |
Site preparation works Site survey |
Site preparation works Site survey |
Diaphragm wall construction Site survey |
Contract
no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 section under
FEP-10/364/2009B
Table VIII Principal Work Activities for Contract
no. HY/2010/08
March 2013 |
April 2014 |
May 2014 |
Tree & root pruning works Tree
& root pruning works Tree transplanting works, Tree works within off-site nursery
compound, Drainage improvement works, Sheet piling works, Demarcation of graphics, Erection of noise absorption
sheetings, Installation of site hoardings, Pipe pile & pre-boring works, Re-provisional of turtle pond – peddle
path, Loop detector installation works & UMP installation works. . |
Tree & root pruning works Tree transplanting works, Tree works within off-site nursery
compound, Drainage improvement works, Sheet piling works, Demarcation of graphics, Erection of noise absorption
sheetings, Installation of site hoardings, Sheet piling, pipe piling, ground
pre-treatment & pre-boring works, Re-provisional of turtle pond – peddle
path & Construction of Bowling Green Office. |
Tree & root pruning works Tree transplanting works, Tree works within off-site nursery
compound, Drainage improvement works, Sheet piling works, Demarcation of graphics, Erection of noise absorption
sheetings, Installation of site hoardings and
provision of concrete bund under the site hoardings, Pipe piling, ground pre-treatment
& pre-boring works, Re-provisional of turtle pond – peddle
path & Construction of Bowling Green Office |
Contract
no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
Table IV Principal Work Activities for Contract
no. HY/2011/08
March 2013 |
April 2014 |
May 2014 |
N/A . |
N/A |
No physical construction activity on
site |
Remarks: The FEP for
Contract no. HY/2011/08 was granted in May 2014 reporting month.
Noise Monitoring
Real
time Noise Monitoring
Air Quality
Monitoring
No action level and no limit level
exceedances were recorded in this reporting quarter.
Complaints, Notifications of Summons and
Successful Prosecutions
Nevertheless, in view of the concern
regarding noise nuisance raised by public, it is considered desirable for the
Contractor to review and strengthen the noise mitigation measures around the
concerned location.
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009/B to
implement the Environmental Monitoring and Audit (EM&A) programme as stipulated
in the EM&A Manual of the approved Environmental Impact Assessment (EIA)
Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register
No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of
EM&A Manual and “Environmental Monitoring and Audit Requirements”
under Particular Specification Section 27.
1.1.3. This report documents the finding of EM&A
works during the period from March 2014 to May 2014.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements – summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results – summarizes the monitoring results
obtained in the reporting period.
Section 5 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB)
and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately 4.5 km
in length, and tunnel approximately 3.7 km in length defined from the
connection with the existing Rumsey Street Flyover in Central, through to a
connection with the existing Island Eastern Corridor to the east of the Causeway
Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street
Flyover to provide road connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road
system in the Wan Chai North and
·
Associated road lighting, road signing, traffic
control and surveillance system; and
·
Other associated works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
In
the reporting period, all the contracts were commenced and contract no.
04/HY/2006 had been completed. The details of individual contracts are
summarized in Table2.2.
Table
2.2 Details of Individual Contracts
under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel ( |
DP1 |
13 July 2011 |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
DP works under |
HY/2010/08 |
Central- Wanchai Bypass Tunnel – Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning |
DP1 |
To be commenced tentatively on 4th
quarter in 2014. |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Chun
Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Mr. Simon Liu |
2162 9909 |
2634 1626 |
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack
Chu |
9775 2467 |
|||
Environmental
Officer |
Mr. Terry
Wong |
9757 9846 |
|||
Environmental
Supervisor |
Mr. Stanley Chan |
9047 6148 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827 9996 |
Project Manager |
Mr. Alfred Leung |
3658-3022 |
|||
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
|
9286 9208 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Desmond Sze |
2214
7700 |
2140 6799 |
Deputy Site Agent |
Mr Roger Wong |
2214
7703 |
|||
Environmental Officer |
Ms. |
2823
1161 |
|||
Environmental Engineer |
Mr. Donald Yip |
2214 7721 |
|||
Assistant Environmental Engineer |
Mr. Penny Yiu |
2214
7738 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ray Cheng |
22147742 |
|||
Environmental Supervisor |
Bosco Lee |
22147711 |
|||
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. K C Cheung |
2823 7813 |
2566 2192 |
Site Manager |
Mr. J.H. Chen |
3557 6368 |
|||
Contractor’s
Representative |
Mr. Gene Cheung |
3557
6395 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Ms Esther Choi |
35576348 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529
2880 |
Site
Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Clement Pang |
9481 6024 |
|||
Environmental
Supervisor |
Mr.
Jacky Cheung |
9735 9200 |
|||
|
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung
Kit Cheung |
3557
6399 |
3465 2899 |
Project
Manager |
Chan
Ying Lun |
9812
0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467
4299 |
|||
Site
Agent |
Dave
Chan |
3467
4277 |
|||
Environmental
Officer |
C.M.
Wong |
3557
6464 |
|||
Environmental
Supervisor |
Louis
Lam Tsz Kwan |
3557
6470 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Project
Manager |
Paul
Evans |
2823
1111 |
21406799 |
Site
Agent |
Colman Wong |
9730
0806 |
|||
Environmental
Officer |
Donald Ip |
6461
8635 |
|||
Environmental
Supervisor |
Penny Yiu |
2214
7738 |
|||
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
2.5.1.
Major construction activities for Contract no.
HY/2009/18 have been commenced on 21
Table 2.4 Principal Work Activities
for Contract no. HY/2009/18
March
2013 |
April
2014 |
May
2014 |
Excavation of
trial pit
Transplanting of
trees
Drainage works
Tunnel works
including scaffolding erection, excavation, OHVD installation, roadside
barriers, top and base slab construction
Trough structure
construction and associated drilling and grouting
Road works
Bridges
construction |
Excavation of
trial pit
Transplanting of
trees
Drainage works
Tunnel works
including scaffolding erection, excavation, OHVD installation, roadside
barriers, top and base slab construction
Trough structure
construction and associated drilling and grouting
Road works
Bridges
construction |
Excavation of
trial pit
Transplanting of
trees
Drainage works
Tunnel works
including scaffolding erection, excavation, OHVD installation, roadside
barriers, top and base slab construction
Trough structure
construction and associated drilling and grouting
Road works
Bridges
construction |
2.5.2. Major
construction activities for Contract no. HK/2009/01 have been commenced on 25
August 2011. During this reporting period, the principal work activities are
summarized in Table2.5:
Table 2.5 Principal Work Activities for Contract no. HK/2009/01
March
2013 |
April
2014 |
May
2014 |
Stage 1 tunnel excavation work to -5.5 mPD including ELS works for 2nd
layer
Bay 5 and Bay 6 blinding layers
Ground treatment works and guide wall construction at the promenade
deck area demolition of the existing pump house.
Installation of pre-bored H-piles
Construction of D wall at C1/C2 interface and CSD for pipe pile wall
P2
Plant demobilization
Removal of silos
Road diversion works for the construction of temporary road at Expo
Drive East
UU diversion at both south and north junction. |
New temporary road for diversion of Expo Drive East
Stage 1 tunnel excavation work
Installation of pre-bored H-piles
Construction of D-wall for the remaining south D-wall panels at Stage
2
Discharge cooling main laying works for BI, BG & BF
Saltwater main laying works for S8B at Zone A5-4 and A5-6 at Harbor
Road
Tree transplanting at the planter areas near Hong Kong Culture Centre
at Tsim Sha Tsui
Trimming works at Fairway |
Demolition work of the existing Expo Drive East Bridge
Trench excavation at both northern and southern ends of existing Expo
Drive East
Bridge
Stage 1 tunnel blinding layer
Stage 1 tunnel structure work
Excavation & fabrication at tunnel
Installation of pre-bored H-piles at the HKCEC water channel by t
Installation of pre-bored H-piles at the area adjacent to new
temporary road
Construction of D-wall for the remaining south D-wall panels at Stage
2
Discharge cooling main laying works for BI, BG & BF
Saltwater main laying works for S8B
Trimming works at Fairway
The removal work for abandoned equipment at lower portion of existing
P3 & P4
pump houses
The removal work for abandoned equipment for existing P7 & P9 pump
houses |
2.5.3. Major
construction activities for Contract no. HK/2009/02 have been commenced on 26
Table 2.6 Principal Work Activities for Contract no. HK/2009/02
March
2013 |
April
2014 |
May
2014 |
Casting of OHVD and upper side wall at Westbound are as follows:
Casting for roof slab at Bay 1 , Bay 3, Bay 4 and Bay 7
Rebar fixing at Bay 6.
Scaffolding removal of Bay 2
Concreting of D-wall Panel at Tunnel Portion 2
Casting of bored pile nos. PC 28, PC 30, PC 32 and PN29
Installation of Bored Pile Nos. PN28.
Ground treatment for D-wall construction at Panel Nos. P97 – C105
Guide wall and ground treatment for D-wall construction at Panel Nos.
C Concreting of 2 nos. D-wall Panels for
Tunnel Portion 6 |
Casting of roof Slab at Bay 4a,
Bay 5, Bay 6 and Bay 8
Water testing on cracks at roof slab.
The crack mapping for tunnel top slab from Bay 2 to Bay 4.
Removal of ELS at S3 Level.
Removal at Bay 4 was now in progress.
Eastbound scaffolding removal of Bay 1 to Bay 4
Westbound scaffolding removal at Bay 3 and Bay 4
Concreting and grouting of 6 nos. D-wall Panel
Complete demobilization of D-Wall plant, including the silo at
northern seawall near Box Culvert N1 outfall.
Casting of 4 nos. bored pile nos. PN28, PN32, PN33 and PC29.
Completing total 60.7% (17 out of 28 nos.)
Installation of Bored Pile Nos. PS30
Ground treatment for D-wall construction at Panel Nos. P97 – C105
Plant mobilization for D-Wall construction |
Water test on cracks at roof slab
Removal of ELS at S3 Level
The crack mapping for tunnel top slab
Loading Transfer for King Post at top slab
Preparation works for horizontal CJ slab construction at Bay 1
Dismantling of scaffolding along the eastbound base slab and 50% along
westbound base slab
Scaffolding removal at OHVD of eastbound and westbound
Toe grouting & interfacing coring for southern D-Wall
Transferal of D-Wall plant from Tunnel Portion 2 to Tunnel Portion 3
& 4, including the BC-Cutter and Crane
Removal of silo at northern seawall near Box Culvert N1 outfall
Excavation for remaining 2 bored pile nos. PS15 and PS16
3 nos. D-wall Panel were concreted in the report period P99, P130 and
P145 Critical D-wall interfacing with the footprint of temporary bridges for
HHR Flyover Diversion (Stage 2) implementation
Construction of D-wall panels P98, P131 and P146 |
2.5.4. Major
construction activities for Contract no. HY/2009/15 have been commenced on 13
July 2011. During this reporting period, the principal work activities are
summarized in Table 2.7:
Table 2.7 Principal Work Activities for Contract no.
HY/2009/15
March
2013 |
April
2014 |
May
2014 |
Tunnel construction at TS2, TS4 & TPCWAE
Dismantling of struts at TS4 & TPCWAE
Mined Tunnel drill-and-break works and installation of steel ribs at
East and West Portal.
Mined tunnel lining construction |
Tunnel construction at TS2, TS4 & TPCWAE
Dismantling of struts at TS4 & TPCWAE
Mined Tunnel drill-and-break works and installation of steel ribs at
East and West Portal.
Mined tunnel lining construction |
Tunnel construction (shaft) at TPCWAE
Dismantling of struts at TS2, TS4 & TPCWAE
Mined Tunnel drill-and-break works and installation of steel ribs at
East and West Portal.
Mined tunnel lining construction |
2.5.5. Major
construction activities for Contract no. HY/2009/19 have been commenced on March
2011. During this reporting period, the principal work activities are
summarized in Table 2.8:
Table 2.8 Principal Work Activities for Contract no.
HY/2009/19
March
2013 |
April
2014 |
May
2014 |
Road works at Watson Road
Bored piling (Land)
Removal of strut at ELS
Construction of Pile cap, column and cross-head (Land)
Removal of marine platform
Construction of Dolphin Cap
ELS, EVB and Cut & Cover Tunnel
Installation of dewatering well
Laying of 1500 pipe
Launching of segments
Extraction of temporary pile from marine section
Construction of bridge TA1
Pre-bored H-pile for Admin. Building commenced |
Road works at Watson Road
Bored piling (Land)
Removal of strut at ELS
Construction of Pile cap, column and cross-head (Land)
Removal of marine platform
Construction of Dolphin Cap
ELS, EVB and Cut & Cover Tunnel
Installation of dewatering well
Laying of 1500 pipe
Launching of segments
Extraction of temporary pile from marine section
Construction of bridge TA1
Pre-bored H-pile for Admin. Building commenced
U-beam installation commenced
Parapet construction commenced
Wing slab extension for segment commenced
Construction of TD bridge commenced |
Road works at Watson Road
Bored piling (Land)
Removal of strut at ELS
Removal of marine platform
Construction of Dolphin Cap
ELS, EVB and Cut & Cover Tunnel
Installation of dewatering well
Laying of 1500 pipe
Launching of segments
Extraction of temporary pile from marine section
Construction of bridge TA1
Pre-bored H-pile for Admin. Building commenced
U-beam installation commenced
Parapet construction commenced
Wing slab extension for segment commenced
Construction of TD bridge commenced |
2.5.6.
Major construction activities for
Contract no. HK/2010/06 have been commenced on March 2011. During this
reporting period, the principal work activities are summarized in Table 2.9
Table 2.9 Principal Work Activities for Contract
no. HK/2010/06
March
2013 |
April
2014 |
May
2014 |
Installation of protection layer for precast unit |
Installation of protection layer for precast unit |
Completion of laying protection board
Preparation works for sealing of cross wall opening
Diversion of power supply |
2.5.7.
Major construction activities for
Contract no. HK/2012/08 have been commenced on March 2013. During the reporting
period, the principal work activities are summarized in Table 2.10
Table
2.10 Principal Work Activities for
Contract no. HK/2012/08
March
2013 |
April
2014 |
May
2014 |
Site preparation works
Site survey |
Site preparation works
Site survey |
Diaphragm wall construction
Site survey |
2.5.8.
Major construction activities for Contract no.HY/2010/08 have been commenced
on March 2013. During the reporting period, the principal work activities are
summarized in Table 2.11
Table
2.11 Principal Work Activities for
Contract no. HY/2010/08
March
2013 |
April
2014 |
May
2014 |
Tree & root pruning works Tree & root pruning works
Tree transplanting works,
Tree works within off-site nursery compound,
Drainage improvement works,
Sheet piling works,
Demarcation of graphics,
Erection of noise absorption sheetings,
Installation of site hoardings,
Pipe pile & pre-boring works,
Re-provisional of turtle pond – peddle path,
Loop detector installation works &
UMP installation works. . |
Tree & root pruning works
Tree transplanting works,
Tree works within off-site nursery compound,
Drainage improvement works,
Sheet piling works,
Demarcation of graphics,
Erection of noise absorption sheetings,
Installation of site hoardings,
Sheet piling, pipe piling, ground pre-treatment & pre-boring
works,
Re-provisional of turtle pond – peddle path &
Construction of Bowling Green Office. |
Tree & root pruning works
Tree transplanting works,
Tree works within off-site nursery compound,
Drainage improvement works,
Sheet piling works,
Demarcation of graphics,
Erection of noise absorption sheetings,
Installation of site hoardings and provision of concrete bund under
the site hoardings,
Pipe piling, ground pre-treatment & pre-boring works,
Re-provisional of turtle pond – peddle path &
Construction of Bowling Green Office |
2.5.9.
Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009B
Table 2.12 Principal
Work Activities for Contract no. HY/2011/08
March
2013 |
April
2014 |
May
2014 |
N/A . |
N/A |
No physical construction activity on site |
Remarks: The FEP for Contract no. HY/2011/08 was
granted in May 2014 reporting month.
2.5.10.
Implementation status of the recommended mitigation measures
during this reporting period is presented in Appendix 2.1.
3.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
3.1 and Figure 3.1. Appendix 3.1 shows
the established Action/Limit Levels for the monitoring works.
Table 3.1 Noise Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun
Area |
M3a |
Tung Lo Wan
Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark 1: Location
ID has been updated from M7 to M8 for City Hall
* Remark 2: M7e has
become a reference station starting from 7 Aug 2012
Real time Noise Monitoring Stations
3.1.2.
The
noise monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1
shows the established Action/Limit Levels for the monitoring works.
Table
3.2 Real Time Noise Monitoring Station
District |
Station |
Description |