Contract No: HK/2011/07

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 2)

 

Environmental Permit no. EP-364/2009/B,

Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEp-07/364/2009/a, FEp-08/364/2009/a , FEP-09/364/2009/B, fep-10/364/2009/B and fep-11/364/2009/B

 

Quarterly Environmental Monitoring
and Audit Report

 

- March 2014 to May 2014 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

CHECKED by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

 

23 June 2014


Table of contents

 

1.     Introduction. 1

1.1        Scope of the Report 1

1.2        Structure of the Report 1

2.     Project Background. 2

2.1        Background. 2

2.2        Scope of the Project and Site Description. 2

2.3        Division of the Project Responsibility. 3

2.4        Project Organization and Contact Personnel 4

2.5        Principal Work and Activities. 7

3.     Monitoring Requirements. 12

3.1.       Noise Monitoring. 12

3.2.       Air Monitoring. 14

4.     Monitoring Results. 16

4.1.       Noise Monitoring Results. 16

4.2.       Real Time Noise Monitoring Results. 19

4.3.       Air Monitoring Results. 22

4.4.       Waste Monitoring Results. 24

5.     Compliance Audit. 28

5.1.       Noise Monitoring. 28

5.2.       Air Monitoring. 28

5.3.       Site Audit 29

5.4.       Review of the Reasons for and the Implications of Non-compliance. 31

5.5.       Summary of action taken in the event of and follow-up on non-compliance. 31

6.     Complaints, Notification of Summons and Prosecution. 32

7.     Cumulative Construction Impact due to the Concurrent Projects. 33

8.     Conclusion. 33


lIST OF TABLES

 

Table I          Principal Work Activities for Contract no. HY/2009/18

Table II         Principal Work Activities for Contract no. HK/2009/01

Table III        Principal Work Activities for Contract no. HK/2009/02

Table IV       Principal Work Activities for Contract no. HY/2009/15

Table V        Principal Work Activities for Contract no. HY/2009/19

Table VI        Principal Work Activities for Contract no. HK/2010/06

Table VII       Principal Work Activities for Contract no. HK/2012/08

Table VIII      Principal Work Activities for Contract no. HY/2010/08

Table IV        Principal Work Activities for Contract no. HY/2011/08

Table 2.1      Schedule 2 Designated Projects under this Project

Table 2.2      Details of Individual Contracts under the Project

Table 2.3      Contact Details of Key Personnel

Table 2.4      Principal Work Activities for Contract no. HY/2009/18

Table 2.5      Principal Work Activities for Contract no. HK/2009/01

Table 2.6      Principal Work Activities for Contract no. HK/2009/02

Table 2.7      Principal Work Activities for Contract no. HY/2009/15

Table 2.8      Principal Work Activities for Contract no. HY/2009/19

Table 2.9       Principal Work Activities for Contract no. HK/2010/06

Table 2.10    Principal Work Activities for Contract no. HK/2012/08

Table 2.11    Principal Work Activities for Contract no. HY/2010/08

Table 2.12    Principal Work Activities for Contract no. HY/2011/08

Table 3.1      Noise Monitoring Station

Table 3.2      Real Time Noise Monitoring Station

Table 3.3      Air Monitoring Stations

Table 4.1      Noise Monitoring Station for Contract no. HY/2009/18

Table 4.2      Noise Monitoring Stations for Contract nos. HK/2009/01 and HK/2009/02

Table 4.3      Noise Monitoring Station for Contract nos. HY/2009/15

Table 4.4      Noise Monitoring Stations for Contract no. HY/2009/19

Table 4.5      Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Table 4.6      Air Monitoring Stations for Contract no. HY/2009/18

Table 4.7      Air Monitoring Stations for Contract no. HK/2009/01

Table 4.8      Air Monitoring Station for Contract no. HK/2009/02

Table 4.9      Air Monitoring Station for Contract no. HY/2009/15

Table 4.10    Air Monitoring Stations for Contract no. HY/2009/19

Table 4.11    Details of Waste Disposal for Contract no. HK/2009/01

Table 4.12    Details of Waste Disposal for Contract no. HK/2009/02

Table 4.13    Details of Waste Disposal for Contract no. HY/2009/18

Table 4.14    Details of Waste Disposal for Contract no. HY/2009/15

Table 4.15    Details of Waste Disposal for Contract no. HY/2009/19

Table 4.16    Details of Waste Disposal for Contract no. HK/2010/06

Table 4.17    Details of Waste Disposal for Contract no. HK/2012/08

Table 4.18    Details of Waste Disposal for Contract no. HY/2012/08

Table 6.1      Cumulative Statistics on Complaints

Table 6.2      Cumulative Statistics on Successful Prosecutions

 

 

 

 

 

 

 

 

 

 

 

 

 

 

lIST OF FIGUREs

 

Figure 2.1         Project Layout

Figure 2.2         Project Organization Chart

Figure 3.1         Locations of Environmental Monitoring Stations

 

lIST OF APPENDIces

 

Appendix 2.1    Environmental Mitigation Implementation Schedule

Appendix 3.1    Action and Limit Level

Appendix 4.1    Noise Monitoring Results and Graphical Presentations

Appendix 4.2    Real-time Noise Monitoring Results and Graphical Presentations

Appendix 4.3    Air Quality Monitoring Results and Graphical Presentations

Appendix 5.1    Event Action Plans

Appendix 6.1    Complaint Log

Appendix 6.2     Notification of Exceedance

Appendix 8.1    Construction Programme of Individual Contracts


 

EXECUTIVE SUMMARY

 

  1. This is the Environmental Monitoring and Audit (EM&A) Quarterly Report – March 2014 to May 2014 specific for Environmental Permit no. EP-364/2009/A, Further Environmental Permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-03-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009/B. The EM&A report is prepared by the Environmental Team (ET) employed under Contract No. HK/2011/07 Wan Chai Development Phase II and Central Wanchai Bypass – Sampling, Field Measurement and Testing Works (Stage 2). This report presents the environmental monitoring findings and information recorded during the period March 2014 to May 2014. The cut-off date of reporting is at 27th of each reporting quarter.

 

  1. In the reporting quarter, the principal work activities of individual contracts are included as follows:

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  - Central Interchange under FEP-05/364/2009/

Major construction activities for Contract no. HY/2009/18 have been commenced on 21 April 2011. During this reporting period, the principal work activities for Contract no. HY/2009/18 are summarized as below:

Table I        Principal Work Activities for Contract no. HY/2009/18

March 2013

April 2014

May 2014

Ÿ  Excavation of trial pit

Ÿ  Transplanting of trees

Ÿ  Drainage works

Ÿ  Tunnel works including scaffolding erection, excavation, OHVD installation, roadside barriers, top and base slab construction

Ÿ  Trough structure construction and associated drilling and grouting

Ÿ  Road works

Ÿ  Bridges construction

 

Ÿ   Excavation of trial pit

Ÿ   Transplanting of trees

Ÿ   Drainage works

Ÿ   Tunnel works including scaffolding erection, excavation, OHVD installation, roadside barriers, top and base slab construction

Ÿ   Trough structure construction and associated drilling and grouting

Ÿ   Road works

Ÿ   Bridges construction

 

Ÿ   Excavation of trial pit

Ÿ   Transplanting of trees

Ÿ   Drainage works

Ÿ   Tunnel works including scaffolding erection, excavation, OHVD installation, roadside barriers, top and base slab construction

Ÿ   Trough structure construction and associated drilling and grouting

Ÿ   Road works

Ÿ   Bridges construction

 

 

 

 

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

Major construction activities for Contract no. HK/2009/01 have been commenced on 25 August 2011. During this reporting period, the principal work activities are summarized as below:

Table II       Principal Work Activities for Contract no. HK/2009/01

March 2013

April 2014

May 2014

Ÿ   Stage 1 tunnel excavation work to -5.5 mPD including ELS works for 2nd layer

Ÿ   Bay 5 and Bay 6 blinding layers

Ÿ   Ground treatment works and guide wall construction at the promenade deck area demolition of the existing pump house.

Ÿ   Installation of pre-bored H-piles

Ÿ   Construction of D wall at C1/C2 interface and CSD for pipe pile wall P2

Ÿ   Plant demobilization

Ÿ   Removal of silos

Ÿ   Road diversion works for the construction of temporary road at Expo Drive East

Ÿ   UU diversion at both south and north junction.

 

Ÿ   New temporary road for diversion of Expo Drive East

Ÿ   Stage 1 tunnel excavation work

Ÿ   Installation of pre-bored H-piles

Ÿ   Construction of D-wall for the remaining south D-wall panels at Stage 2

Ÿ   Discharge cooling main laying works for BI, BG & BF

Ÿ   Saltwater main laying works for S8B at Zone A5-4 and A5-6 at Harbor Road

Ÿ   Tree transplanting at the planter areas near Hong Kong Culture Centre at Tsim Sha Tsui

Ÿ   Trimming works at Fairway

 

Ÿ   Demolition work of the existing Expo Drive East Bridge

Ÿ   Trench excavation at both northern and southern ends of existing Expo Drive East

Ÿ   Bridge

Ÿ   Stage 1 tunnel blinding layer

Ÿ   Stage 1 tunnel structure work

Ÿ   Excavation & fabrication at tunnel

Ÿ   Installation of pre-bored H-piles at the HKCEC water channel by t

Ÿ   Installation of pre-bored H-piles at the area adjacent to new temporary road

Ÿ   Construction of D-wall for the remaining south D-wall panels at Stage 2

Ÿ   Discharge cooling main laying works for BI, BG & BF

Ÿ   Saltwater main laying works for S8B

Ÿ   Trimming works at Fairway

Ÿ   The removal work for abandoned equipment at lower portion of existing P3 & P4 pump houses

Ÿ   The removal work for abandoned equipment for existing P7 & P9 pump houses

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

Major construction activities for Contract no. HK/2009/02 have been commenced on 26 April 2011. During this reporting period, the principal work activities are summarized as below:

Table III      Principal Work Activities for Contract no. HK/2009/02

March 2013

April 2014

May 2014

Ÿ   Casting of OHVD and upper side wall at Westbound are as follows:

Ÿ   Casting for roof slab at Bay 1 , Bay 3, Bay 4 and Bay 7

Ÿ   Rebar fixing at Bay 6.

Ÿ   Scaffolding removal of Bay 2

Ÿ   Concreting of D-wall Panel at Tunnel Portion 2

Ÿ   Casting of bored pile nos. PC 28, PC 30, PC 32 and PN29

Ÿ   Installation of Bored Pile Nos. PN28.

Ÿ   Ground treatment for D-wall construction at Panel Nos. P97 – C105

Ÿ   Guide wall and ground treatment for D-wall construction at Panel Nos. C130A – P131

Ÿ   Concreting of 2 nos. D-wall Panels for Tunnel Portion 6

Ÿ   Casting of roof Slab at  Bay 4a, Bay 5, Bay 6 and Bay 8

Ÿ   Water testing on cracks at roof slab. 

Ÿ   The crack mapping for tunnel top slab from Bay 2 to Bay 4.

Ÿ   Removal of ELS at S3 Level.

Ÿ   Removal at Bay 4 was now in progress.

Ÿ   Eastbound scaffolding removal of Bay 1 to Bay 4

Ÿ   Westbound scaffolding removal at Bay 3 and Bay 4

Ÿ   Concreting and grouting of 6 nos. D-wall Panel

Ÿ   Complete demobilization of D-Wall plant, including the silo at northern seawall near Box Culvert N1 outfall.

Ÿ   Casting of 4 nos. bored pile nos. PN28, PN32, PN33 and PC29.

Ÿ   Completing total 60.7% (17 out of 28 nos.)

Ÿ   Installation of Bored Pile Nos. PS30

Ÿ   Ground treatment for D-wall construction at Panel Nos. P97 – C105

Ÿ   Plant mobilization for D-Wall construction

 

Ÿ   Water test on cracks at roof slab

Ÿ   Removal of ELS at S3 Level

Ÿ   The crack mapping for tunnel top slab

Ÿ   Loading Transfer for King Post at top slab

Ÿ   Preparation works for horizontal CJ slab construction at Bay 1

Ÿ   Dismantling of scaffolding along the eastbound base slab and 50% along westbound base slab

Ÿ   Scaffolding removal at OHVD of eastbound and westbound

Ÿ   Toe grouting & interfacing coring for southern D-Wall

Ÿ   Transferal of D-Wall plant from Tunnel Portion 2 to Tunnel Portion 3 & 4, including the BC-Cutter and Crane

Ÿ   Removal of silo at northern seawall near Box Culvert N1 outfall

Ÿ   Excavation for remaining 2 bored pile nos. PS15 and PS16

Ÿ   3 nos. D-wall Panel were concreted in the report period P99, P130 and P145 Critical D-wall interfacing with the footprint of temporary bridges for HHR Flyover Diversion (Stage 2) implementation

Ÿ   Construction of D-wall panels P98, P131 and P146

 

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

Major construction activities for Contract no. HY/2009/15 has been commenced on 13 July 2011. During this reporting period, the principal work activities are summarized as below:

Table IV     Principal Work Activities for Contract no. HY/2009/15

March 2013

April 2014

May 2014

Ÿ   Tunnel construction at TS2, TS4 & TPCWAE

Ÿ   Dismantling of struts at TS4 & TPCWAE

Ÿ   Mined Tunnel drill-and-break works and installation of steel ribs at East and West Portal.

Ÿ   Mined tunnel lining construction

 

Ÿ   Tunnel construction at TS2, TS4 & TPCWAE

Ÿ   Dismantling of struts at TS4 & TPCWAE

Ÿ   Mined Tunnel drill-and-break works and installation of steel ribs at East and West Portal.

Ÿ   Mined tunnel lining construction

 

Ÿ   Tunnel construction (shaft) at TPCWAE

Ÿ   Dismantling of struts at TS2, TS4 & TPCWAE

Ÿ   Mined Tunnel drill-and-break works and installation of steel ribs at East and West Portal.

Ÿ   Mined tunnel lining construction

 

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

Major construction activities for Contract no. HY/2009/19 have been commenced on March 2011. During this reporting period, the principal work activities are summarized as below:

Table V      Principal Work Activities for Contract no. HY/2009/19

March 2013

April 2014

May 2014

Ÿ   Road works at Watson Road

Ÿ   Bored piling (Land)

Ÿ   Removal of strut at ELS

Ÿ   Construction of Pile cap, column and cross-head (Land)

Ÿ   Removal of marine platform

Ÿ   Construction of Dolphin Cap

Ÿ   ELS, EVB and Cut & Cover Tunnel

Ÿ   Installation of dewatering well

Ÿ   Laying of 1500 pipe

Ÿ   Launching of segments

Ÿ   Extraction of temporary pile from marine section

Ÿ   Construction of bridge TA1

Ÿ   Pre-bored H-pile for Admin. Building commenced

 

Ÿ   Road works at Watson Road

Ÿ   Bored piling (Land)

Ÿ   Removal of strut at ELS

Ÿ   Construction of Pile cap, column and cross-head (Land)

Ÿ   Removal of marine platform

Ÿ   Construction of Dolphin Cap

Ÿ   ELS, EVB and Cut & Cover Tunnel

Ÿ   Installation of dewatering well

Ÿ   Laying of 1500 pipe

Ÿ   Launching of segments

Ÿ   Extraction of temporary pile from marine section

Ÿ   Construction of bridge TA1

Ÿ   Pre-bored H-pile for Admin. Building commenced

Ÿ   U-beam installation commenced

Ÿ   Parapet construction commenced

Ÿ   Wing slab extension for segment commenced

Ÿ   Construction of TD bridge commenced

 

Ÿ   Road works at Watson Road

Ÿ   Bored piling (Land)

Ÿ   Removal of strut at ELS

Ÿ   Removal of marine platform

Ÿ   Construction of Dolphin Cap

Ÿ   ELS, EVB and Cut & Cover Tunnel

Ÿ   Installation of dewatering well

Ÿ   Laying of 1500 pipe

Ÿ   Launching of segments

Ÿ   Extraction of temporary pile from marine section

Ÿ   Construction of bridge TA1

Ÿ   Pre-bored H-pile for Admin. Building commenced

Ÿ   U-beam installation commenced

Ÿ   Parapet construction commenced

Ÿ   Wing slab extension for segment commenced

Ÿ   Construction of TD bridge commenced

 

 

Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A

Table VI     Principal Work Activities for Contract no. HK/2010/06

March 2013

April 2014

May 2014

Ÿ   Installation of protection layer for precast unit

 

Ÿ   Installation of protection layer for precast unit

 

Ÿ   Completion of laying protection board

Ÿ   Preparation works for sealing of cross wall opening

Ÿ   Diversion of power supply

 

 

Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009B

Table VII                      Principal Work Activities for Contract no. HK/2012/08

March 2013

April 2014

May 2014

Ÿ   Site preparation works

Ÿ   Site survey

Ÿ   Site preparation works

Ÿ   Site survey

Ÿ   Diaphragm wall construction

Ÿ   Site survey

 

 

 

 

Contract no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 section under FEP-10/364/2009B

Table VIII      Principal Work Activities for Contract no. HY/2010/08

March 2013

April 2014

May 2014

Ÿ   Tree & root pruning works Tree & root pruning works

Ÿ   Tree transplanting works,

Ÿ   Tree works within off-site nursery compound,

Ÿ   Drainage improvement works,

Ÿ   Sheet piling works,

Ÿ   Demarcation of graphics,

Ÿ   Erection of noise absorption sheetings,

Ÿ   Installation of site hoardings,

Ÿ   Pipe pile & pre-boring works,

Ÿ   Re-provisional of turtle pond – peddle path,

Ÿ   Loop detector installation works &

Ÿ   UMP installation works.

.

Ÿ   Tree & root pruning works

Ÿ   Tree transplanting works,

Ÿ   Tree works within off-site nursery compound,

Ÿ   Drainage improvement works,

Ÿ   Sheet piling works,

Ÿ   Demarcation of graphics,

Ÿ   Erection of noise absorption sheetings,

Ÿ   Installation of site hoardings,

Ÿ   Sheet piling, pipe piling, ground pre-treatment & pre-boring works,

Ÿ   Re-provisional of turtle pond – peddle path &

Ÿ   Construction of Bowling Green Office.

 

Ÿ   Tree & root pruning works

Ÿ   Tree transplanting works,

Ÿ   Tree works within off-site nursery compound,

Ÿ   Drainage improvement works,

Ÿ   Sheet piling works,

Ÿ   Demarcation of graphics,

Ÿ   Erection of noise absorption sheetings,

Ÿ   Installation of site hoardings and provision of concrete bund under the site hoardings,

Ÿ   Pipe piling, ground pre-treatment & pre-boring works,

Ÿ   Re-provisional of turtle pond – peddle path &

Ÿ   Construction of Bowling Green Office

 

Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

 

Table IV       Principal Work Activities for Contract no. HY/2011/08

March 2013

April 2014

May 2014

Ÿ   N/A

.

Ÿ   N/A

 

Ÿ   No physical construction activity on site

 

Remarks: The FEP for Contract no. HY/2011/08 was granted in May 2014 reporting month.

 

 

 

 

 

 

Noise Monitoring

  1. Per EPD’s letter dated 3 Aug 2012 (received by ET on 6 Aug 2012 through HyD), noise monitoring at M8 – City Hall commenced on 7 Aug 2012, and the monitoring station M7e – International Finance Centre (Eastern Podium) has become a reference station starting from 7 Aug 2012.
  2. Due to safety concerns, the monitoring location for M4b – Victoria Centre has been finely adjusted from 7 June 2012.
  3. Monitoring for report of review baseline noise level was performed from 11 April 2011 to 8 June 2011.  Then the report was submitted on the 20 June 2011, verified by IEC on 18 July 2011 and was approved by ER by January 2012.  The new baseline is used for the noise calculation starting from the January 2012 reporting month.
  4. Noise monitoring was conducted at M1a - Harbour Road Sports Center; M2b - Noon-day gun area; M3a - Tung Lo Wan Fire Station; M4b - Victoria Center; M5b - City Garden, M6 - HK Baptist Church Henrietta Secondary School, M7e and M7w – International Finance Centre eastern and western wing, and M8 – City Hall on a weekly basis.
  5. No action and 2 limit level exceedances at M6 – HK Baptist Church Henrietta Secondary School were recorded on 5 and 11 March 2014 in this reporting month. The exceedances were concluded as non-project related.
  6. No action and 3 limit level exceedances at M6 – HK Baptist Church Henrietta Secondary School were recorded on 2, 8 and 15 April 2014 in this reporting month. The exceedances were concluded as non-project related.
  7. No action and 2 limit level exceedances at M6 – HK Baptist Church Henrietta Secondary School were recorded on 7 and 14 May 2014 in this reporting month. The exceedances were concluded as non-project related.

 

       Real time Noise Monitoring

  1. 24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitefield Depot for the pilling works in FEHD Whitfield Depot and RTN2 – Tunnel (North Point Section) and Island Eastern Corridor Link during the period from 28 September 2012 til 10am on 5 October 2012 in the reporting period.
  2. Real time noise monitoring station at Oil Street Community Liaison Centre (RTN2- Oil Street Community Centre) was relocated from Oil Street Community Liaison Centre to Hong Kong Electric (RTN2a- Electric Centre) on 5 Oct which is a representative of the noise sensitive receiver City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.
  3. As confirmed by CWB RSS, the IECL parapet removal operations will commence in March 2013.  Liaison was conducted with HK Baptist Church Henrietta Secondary School and Po Leung Kuk Yu Lee Mo Fan Memorial School regarding the set up of RTN3 real time noise monitoring station.  Po Leung Kuk Yu Lee Mo Fan Memorial School grant permission for set up on 4 Sep 2012 and station set up was performed on 14 Sep 2012.
  4. Real Time Noise Monitoring at RTN3- Po Leung Kuk Yu Lee Mo Fan Memorial School was commenced since 06 Oct 2012.
  5. Causeway Bay Community Centre has granted permission for set up of real time noise monitoring station on 21 Dec 2012 and station set up was performed on 27 Dec 2012.  The Baseline noise level of RTN4- Causeway Bay Community Centre will adopt the results from the baseline noise monitoring report for EP/364/2009 in 22 April 2010 in which approved by EPD.
  6. According to clause 3.1 stated in EP-364/2009B, “the real-time monitoring system shall be in place no later than two weeks before the commencement date of demolition works of the existing Island Eastern Corridor”. IEC demolition associated construction works was commenced on 3 Feb 2013 and Real time noise monitoring at RTN4-Causeway Bay Community Centre was commenced on 13 Jan 2013.
  7. Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with respect to the commencement of advance works for IEC parapet demolition.
  8. No project related exceedances were recorded in April and May reporting month and no limit level exceedance was recorded in March reporting month at RTN1- FEHD Hong Kong Transport Section Whitfield Depot during this reporting quarter.
  9. No project related exceedance was recorded in March, April and May reporting month at RTN2a-Hong Kong Electric Centre during this reporting quarter.
  10. No limit level exceedance was recorded in March reporting month and no project related exceedance was recorded in the April and May reporting month at RTN3-Yu Lee Mo Fan Memorial School during this reporting quarter.
  11. No limit level exceedances were recorded in March reporting month and no project related exceedance was recorded in April and May reporting month at RTN4-Causeway Bay Community Centre during this reporting quarter.

Air Quality Monitoring

  1. Due to extension of site boundary by contractor of HY/2009/19, location of air monitoring station CMA1b – Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.
  2. 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b - Oil Street Community Liaison Centre; CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site Office Area; CMA4a – Society for the Prevention of Cruelty to Animals; CMA5a - Children Garden opposite to Pedestrian Plaza; MA1e and MA1w – International Finance Centre eastern and western wing on every six days basis.

No action level and no limit level exceedances were recorded in this reporting quarter.

 Complaints, Notifications of Summons and Successful Prosecutions

  1. One environmental complaints under FEP-05/364/2009/B were received in the reporting quarter.

 

  1. A public complaint regarding construction noise impact referred by EPD was received by ET on 11 March 2014 (Ref: H04/RS/0004232-14 dated11 March 2014) under FEP-05/364/2009/B. The complainant reported that excessive noise (from the operation of compressors, other heavy machinery and concrete breaking) was emanated from the construction site near IFC in daytime on 27 Feb 2014.

  2. ET confirmed with the Resident Site Staff that the major construction activities at the concerned location conducted on 27 Feb 2014 (Daytime) include backfilling works between north wall and sheet piles and for roof slab, Site hoarding removal; Formwork erection and removal works, false work erection; Concrete breaking works at roof slab and base slab and breaking up of existing tunnel corner; Concreting works for profile barrier inside cut and cover tunnel; and rebar fixing works and WVB basement remediation works. Mitigation measures implemented by the Contractor for the above construction works include the use of quiet plants (air compressor with a Noise Emission Label of 99 dB(A)).

  3. According to relevant site records, major noise emanating construction activities conducted around the concerned location on 27 Feb 2014 include concrete breaking works at roof slab and base slab and breaking up of existing tunnel corner and concreting works. Based on information verified by the RSS, noise mitigation measure including utilization of quiet air compressor with noise emission label of 99 dB(A) was implemented by the Contractor on the 27 February 2014 to minimize the potential noise impact.

  4. Having reviewed the monitoring data of the monitoring stations in the vicinity of the construction site near IFC, namely noise monitoring stations M7e and M7w, no limit level exceedances were recorded on 24 Feb 2014 and 4 March 2014 and the major concrete breaking works at the concerned location conducted on 27 February 2014 was continued across the above monitoring period. In addition, no particular observations regarding noise impact were recorded during weekly site inspection conducted on 27 Feb 2014. No non-conformity was identified. As such, the construction activities under Contract HY/2009/18 were considered generally in compliance with the statutory requirement.

Nevertheless, in view of the concern regarding noise nuisance raised by public, it is considered desirable for the Contractor to review and strengthen the noise mitigation measures around the concerned location.

 

  1. Follow-up inspection was conducted during weekly environmental inspection on 13 March 2014, additional noise mitigation measure including erection of noise blanket for concrete breaking works were implemented by the Contractor to further minimize the noise nuisance to nearby public.

 


1.         Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009/B to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.     This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and “Environmental Monitoring and Audit Requirements” under Particular Specification Section 27.

1.1.3.     This report documents the finding of EM&A works during the period from March 2014 to May 2014.

1.2          Structure of the Report

 

Section 1          Introduction – details the scope and structure of the report.

 

Section 2          Project Background – summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3          Monitoring Requirements – summarizes all monitoring parameters, monitoring locations, monitoring frequency, duration and action plan.

 

Section 4          Monitoring Results – summarizes the monitoring results obtained in the reporting period.

 

Section 5          Compliance Audit – summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 6          Complaints, Notification of summons and Prosecution – summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 7          Cumulative Construction Impact due to the Concurrent Projects summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8          Conclusion

2.         Project Background

2.1          Background

2.1.1.     “Wan Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.     The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.     There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2          Scope of the Project and Site Description

2.2.1.     Design and Construction of Central – Wan Chai Bypass and Island Eastern Corridor Link under the Project involves the construction and operation of a trunk road and its road tunnel more than 800m in length between portals that is shown at Figure 2.1.

2.2.2.     The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:

·          A dual three-lane trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length defined from the connection with the existing Rumsey Street Flyover in Central, through to a connection with the existing Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);

·          The Central Interchange near the Rumsey Street Flyover to provide road connections to the Central area;

·          Tunnel control buildings and ventilation buildings;

·          Slip roads to connect the CWB to the local road system in the Wan Chai North and Causeway Bay area;

·          Associated road lighting, road signing, traffic control and surveillance system; and

·          Other associated works.

 

2.2.3.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1    Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3          Division of the Project Responsibility

2.3.1.     Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.     In the reporting period, all the contracts were commenced and contract no. 04/HY/2006 had been completed. The details of individual contracts are summarized in Table2.2.

Table 2.2    Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HY/2009/17

Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works.

DP1

5 October 2010

(Completed)

HY/2009/18

Central – Wan Chai Bypass (CWB) – Central Interchange

DP1

21 April 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010

(Completed)

HK/2009/01

Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East(CWB Tunnel)

DP1

26 April 2011

HY/2009/15

Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

DP1

13 July 2011

HY/2009/19

Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

HK/2012/08

Wan Chai Development Phase II- Central-Wan Chai Bypass at Wan Chai West

DP1,DP2, DP3

DP works under
EP-364 to be commenced tentatively in late 2013.

HY/2010/08

Central- Wanchai Bypass Tunnel – Tunnel (Slip Road 8)

DP1, DP2, DP3

21 March 2013

HY/2011/08

Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

DP1

To be commenced tentatively on 4th quarter in 2014.

 

 

2.4          Project Organization and Contact Personnel

2.4.1.     Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.     The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer’s Representative for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer’s Representative for CWB

Principal Resident Engineer

Mr. Peter Poon

3916 1818

3529 2829

Chun Wo – Leader Joint Venture

Contractor under Contract no. HK/2009/01

Site Agent

Mr. Simon Liu

2162 9909

2634 1626

Deputy Site Agent

Mr. Andy Yu

9648 4896

Construction Manager

Mr. Wyman Wong

9627 2467

Construction Manager

Mr. Jack Chu

9775 2467

Environmental Officer

Mr. Terry Wong

9757 9846

Environmental Supervisor

Mr. Stanley Chan

9047 6148

Chun Wo – CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Site Agent

Mr. K.K. Yuen

3658-3002

2827 9996

Project Manager

Mr. Alfred Leung

3658-3022

Quality & Environmental Manager

(Environmental Officer)

Mr. C.P. Ho

3658-3000

Chun Wo - CRGL - MBEC Joint Venture

Contractor under Contract no. HY/2009/19

Project Manager

Mr. David Lau

3758 8879

2570 8013

Site Agent

Mr. Paul Yu

9456 9819

Environmental Officer

Mr. M.H. Isa

9884 0810

Environmental Engineer

Calvin Leung

9286 9208

Construction Manager (Marine)

William Luk

9610 1101

Construction Manager

(Land)

Patrick Cheung

9643 3012

Construction Manager

(Land)

Eric Fong

6191 9337

Operation Manager (Land)

Yung Kwok Wah

9834 1010

Leighton Contractors (Asia) Limited

Contractor under Contract no. HY/2009/18

Site Agent

Mr. Desmond Sze

2214 7700

2140 6799

Deputy Site Agent

Mr Roger Wong

2214 7703

Environmental Officer

Ms. Lighting Chan

2823 1161

Environmental Engineer

Mr. Donald Yip

2214 7721

Assistant Environmental Engineer

Mr. Penny Yiu

2214 7738

Environmental Supervisor

K. P. Lai

6461 4660

Environmental Supervisor

Ray Cheng

22147742

Environmental Supervisor

Bosco Lee

22147711

Environmental Supervisor

Ryan Tsui

2214 7705

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

Mr. K C Cheung

2823 7813

2566 2192

Site Manager

Mr. J.H. Chen

3557 6368

Contractor’s Representative

Mr. Gene Cheung

3557 6395

Head of construction

Mr. Roger Cheung

3557 6371

Environmental Officer

Mr. Andy Mak

3557 6215

Environmental Supervisor

Ms Esther Choi

35576348

Gammon -Leader JV

Contractor under Contract no. HK/2010/06

Project Manager

Mr. Paul Lui

9095 7922

2529 2880

Site Agent

Mr. Keith Tse

2529 2068

Environmental Officer

Mr. Clement Pang

9481 6024

Environmental Supervisor

Mr. Jacky Cheung

9735 9200

China State

Contractor under Contract no.HY/2010/08

Project Director

Cheung Kit Cheung

3557 6399

3465 2899

Project Manager

Chan Ying Lun

9812 0592

Deputy Project Manager

Chris Leung

3467 4299

Site Agent

Dave Chan

3467 4277

Environmental Officer

C.M. Wong

3557 6464

Environmental Supervisor

Louis Lam Tsz Kwan

3557 6470

Leighton Joint Venture

Contractor under Contract no. HY/2011/08

Project Manager

Paul Evans

2823 1111

21406799

Site Agent

Colman Wong

9730 0806

Environmental Officer

Donald Ip

6461 8635

Environmental Supervisor

Penny Yiu

2214 7738

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3465 2888

3465 2899

 

 

2.5          Principal Work and Activities

2.5.1.     Major construction activities for Contract no. HY/2009/18 have been commenced on 21 April 2011. During this reporting period, the principal work activities for Contract no. HY/2009/18 are summarized in Table2.4:

Table 2.4    Principal Work Activities for Contract no. HY/2009/18

March 2013

April 2014

May 2014

Ÿ  Excavation of trial pit

Ÿ  Transplanting of trees

Ÿ  Drainage works

Ÿ  Tunnel works including scaffolding erection, excavation, OHVD installation, roadside barriers, top and base slab construction

Ÿ  Trough structure construction and associated drilling and grouting

Ÿ  Road works

Ÿ  Bridges construction

 

Ÿ   Excavation of trial pit

Ÿ   Transplanting of trees

Ÿ   Drainage works

Ÿ   Tunnel works including scaffolding erection, excavation, OHVD installation, roadside barriers, top and base slab construction

Ÿ   Trough structure construction and associated drilling and grouting

Ÿ   Road works

Ÿ   Bridges construction

 

Ÿ   Excavation of trial pit

Ÿ   Transplanting of trees

Ÿ   Drainage works

Ÿ   Tunnel works including scaffolding erection, excavation, OHVD installation, roadside barriers, top and base slab construction

Ÿ   Trough structure construction and associated drilling and grouting

Ÿ   Road works

Ÿ   Bridges construction

 

 

2.5.2.     Major construction activities for Contract no. HK/2009/01 have been commenced on 25 August 2011. During this reporting period, the principal work activities are summarized in Table2.5:

Table 2.5    Principal Work Activities for Contract no. HK/2009/01

March 2013

April 2014

May 2014

Ÿ   Stage 1 tunnel excavation work to -5.5 mPD including ELS works for 2nd layer

Ÿ   Bay 5 and Bay 6 blinding layers

Ÿ   Ground treatment works and guide wall construction at the promenade deck area demolition of the existing pump house.

Ÿ   Installation of pre-bored H-piles

Ÿ   Construction of D wall at C1/C2 interface and CSD for pipe pile wall P2

Ÿ   Plant demobilization

Ÿ   Removal of silos

Ÿ   Road diversion works for the construction of temporary road at Expo Drive East

Ÿ   UU diversion at both south and north junction.

 

Ÿ   New temporary road for diversion of Expo Drive East

Ÿ   Stage 1 tunnel excavation work

Ÿ   Installation of pre-bored H-piles

Ÿ   Construction of D-wall for the remaining south D-wall panels at Stage 2

Ÿ   Discharge cooling main laying works for BI, BG & BF

Ÿ   Saltwater main laying works for S8B at Zone A5-4 and A5-6 at Harbor Road

Ÿ   Tree transplanting at the planter areas near Hong Kong Culture Centre at Tsim Sha Tsui

Ÿ   Trimming works at Fairway

 

Ÿ   Demolition work of the existing Expo Drive East Bridge

Ÿ   Trench excavation at both northern and southern ends of existing Expo Drive East

Ÿ   Bridge

Ÿ   Stage 1 tunnel blinding layer

Ÿ   Stage 1 tunnel structure work

Ÿ   Excavation & fabrication at tunnel

Ÿ   Installation of pre-bored H-piles at the HKCEC water channel by t

Ÿ   Installation of pre-bored H-piles at the area adjacent to new temporary road

Ÿ   Construction of D-wall for the remaining south D-wall panels at Stage 2

Ÿ   Discharge cooling main laying works for BI, BG & BF

Ÿ   Saltwater main laying works for S8B

Ÿ   Trimming works at Fairway

Ÿ   The removal work for abandoned equipment at lower portion of existing P3 & P4

Ÿ   pump houses

Ÿ   The removal work for abandoned equipment for existing P7 & P9 pump houses

 

2.5.3.     Major construction activities for Contract no. HK/2009/02 have been commenced on 26 April 2011. During this reporting period, the principal work activities are summarized in Table2.6:

Table 2.6    Principal Work Activities for Contract no. HK/2009/02

March 2013

April 2014

May 2014

Ÿ   Casting of OHVD and upper side wall at Westbound are as follows:

Ÿ   Casting for roof slab at Bay 1 , Bay 3, Bay 4 and Bay 7

Ÿ   Rebar fixing at Bay 6.

Ÿ   Scaffolding removal of Bay 2

Ÿ   Concreting of D-wall Panel at Tunnel Portion 2

Ÿ   Casting of bored pile nos. PC 28, PC 30, PC 32 and PN29

Ÿ   Installation of Bored Pile Nos. PN28.

Ÿ   Ground treatment for D-wall construction at Panel Nos. P97 – C105

Ÿ   Guide wall and ground treatment for D-wall construction at Panel Nos. C130A – P131

Ÿ   Concreting of 2 nos. D-wall Panels for Tunnel Portion 6

Ÿ   Casting of roof Slab at  Bay 4a, Bay 5, Bay 6 and Bay 8

Ÿ   Water testing on cracks at roof slab. 

Ÿ   The crack mapping for tunnel top slab from Bay 2 to Bay 4.

Ÿ   Removal of ELS at S3 Level.

Ÿ   Removal at Bay 4 was now in progress.

Ÿ   Eastbound scaffolding removal of Bay 1 to Bay 4

Ÿ   Westbound scaffolding removal at Bay 3 and Bay 4

Ÿ   Concreting and grouting of 6 nos. D-wall Panel

Ÿ   Complete demobilization of D-Wall plant, including the silo at northern seawall near Box Culvert N1 outfall.

Ÿ   Casting of 4 nos. bored pile nos. PN28, PN32, PN33 and PC29.

Ÿ   Completing total 60.7% (17 out of 28 nos.)

Ÿ   Installation of Bored Pile Nos. PS30

Ÿ   Ground treatment for D-wall construction at Panel Nos. P97 – C105

Ÿ   Plant mobilization for D-Wall construction

 

Ÿ   Water test on cracks at roof slab

Ÿ   Removal of ELS at S3 Level

Ÿ   The crack mapping for tunnel top slab

Ÿ   Loading Transfer for King Post at top slab

Ÿ   Preparation works for horizontal CJ slab construction at Bay 1

Ÿ   Dismantling of scaffolding along the eastbound base slab and 50% along westbound base slab

Ÿ   Scaffolding removal at OHVD of eastbound and westbound

Ÿ   Toe grouting & interfacing coring for southern D-Wall

Ÿ   Transferal of D-Wall plant from Tunnel Portion 2 to Tunnel Portion 3 & 4, including the BC-Cutter and Crane

Ÿ   Removal of silo at northern seawall near Box Culvert N1 outfall

Ÿ   Excavation for remaining 2 bored pile nos. PS15 and PS16

Ÿ   3 nos. D-wall Panel were concreted in the report period P99, P130 and P145 Critical D-wall interfacing with the footprint of temporary bridges for HHR Flyover Diversion (Stage 2) implementation

Ÿ   Construction of D-wall panels P98, P131 and P146

 

2.5.4.     Major construction activities for Contract no. HY/2009/15 have been commenced on 13 July 2011. During this reporting period, the principal work activities are summarized in Table 2.7:

Table 2.7    Principal Work Activities for Contract no. HY/2009/15

March 2013

April 2014

May 2014

Ÿ   Tunnel construction at TS2, TS4 & TPCWAE

Ÿ   Dismantling of struts at TS4 & TPCWAE

Ÿ   Mined Tunnel drill-and-break works and installation of steel ribs at East and West Portal.

Ÿ   Mined tunnel lining construction

Ÿ   Tunnel construction at TS2, TS4 & TPCWAE

Ÿ   Dismantling of struts at TS4 & TPCWAE

Ÿ   Mined Tunnel drill-and-break works and installation of steel ribs at East and West Portal.

Ÿ   Mined tunnel lining construction

Ÿ   Tunnel construction (shaft) at TPCWAE

Ÿ   Dismantling of struts at TS2, TS4 & TPCWAE

Ÿ   Mined Tunnel drill-and-break works and installation of steel ribs at East and West Portal.

Ÿ   Mined tunnel lining construction

2.5.5.     Major construction activities for Contract no. HY/2009/19 have been commenced on March 2011. During this reporting period, the principal work activities are summarized in Table 2.8:

Table 2.8    Principal Work Activities for Contract no. HY/2009/19

March 2013

April 2014

May 2014

Ÿ   Road works at Watson Road

Ÿ   Bored piling (Land)

Ÿ   Removal of strut at ELS

Ÿ   Construction of Pile cap, column and cross-head (Land)

Ÿ   Removal of marine platform

Ÿ   Construction of Dolphin Cap

Ÿ   ELS, EVB and Cut & Cover Tunnel

Ÿ   Installation of dewatering well

Ÿ   Laying of 1500 pipe

Ÿ   Launching of segments

Ÿ   Extraction of temporary pile from marine section

Ÿ   Construction of bridge TA1

Ÿ   Pre-bored H-pile for Admin. Building commenced

 

Ÿ   Road works at Watson Road

Ÿ   Bored piling (Land)

Ÿ   Removal of strut at ELS

Ÿ   Construction of Pile cap, column and cross-head (Land)

Ÿ   Removal of marine platform

Ÿ   Construction of Dolphin Cap

Ÿ   ELS, EVB and Cut & Cover Tunnel

Ÿ   Installation of dewatering well

Ÿ   Laying of 1500 pipe

Ÿ   Launching of segments

Ÿ   Extraction of temporary pile from marine section

Ÿ   Construction of bridge TA1

Ÿ   Pre-bored H-pile for Admin. Building commenced

Ÿ   U-beam installation commenced

Ÿ   Parapet construction commenced

Ÿ   Wing slab extension for segment commenced

Ÿ   Construction of TD bridge commenced

 

Ÿ   Road works at Watson Road

Ÿ   Bored piling (Land)

Ÿ   Removal of strut at ELS

Ÿ   Removal of marine platform

Ÿ   Construction of Dolphin Cap

Ÿ   ELS, EVB and Cut & Cover Tunnel

Ÿ   Installation of dewatering well

Ÿ   Laying of 1500 pipe

Ÿ   Launching of segments

Ÿ   Extraction of temporary pile from marine section

Ÿ   Construction of bridge TA1

Ÿ   Pre-bored H-pile for Admin. Building commenced

Ÿ   U-beam installation commenced

Ÿ   Parapet construction commenced

Ÿ   Wing slab extension for segment commenced

Ÿ   Construction of TD bridge commenced

 

 

 

 

 

2.5.6.     Major construction activities for Contract no. HK/2010/06 have been commenced on March 2011. During this reporting period, the principal work activities are summarized in Table 2.9

            Table 2.9          Principal Work Activities for Contract no. HK/2010/06

March 2013

April 2014

May 2014

Ÿ   Installation of protection layer for precast unit

 

Ÿ   Installation of protection layer for precast unit

 

Ÿ   Completion of laying protection board

Ÿ   Preparation works for sealing of cross wall opening

Ÿ   Diversion of power supply

 

2.5.7.     Major construction activities for Contract no. HK/2012/08 have been commenced on March 2013. During the reporting period, the principal work activities are summarized in Table 2.10

Table 2.10      Principal Work Activities for Contract no. HK/2012/08

March 2013

April 2014

May 2014

Ÿ   Site preparation works

Ÿ   Site survey

Ÿ   Site preparation works

Ÿ   Site survey

Ÿ   Diaphragm wall construction

Ÿ   Site survey

2.5.8.     Major construction activities for Contract no.HY/2010/08 have been commenced on March 2013. During the reporting period, the principal work activities are summarized in Table 2.11

             Table 2.11          Principal Work Activities for Contract no. HY/2010/08

March 2013

April 2014

May 2014

Ÿ   Tree & root pruning works Tree & root pruning works

Ÿ   Tree transplanting works,

Ÿ   Tree works within off-site nursery compound,

Ÿ   Drainage improvement works,

Ÿ   Sheet piling works,

Ÿ   Demarcation of graphics,

Ÿ   Erection of noise absorption sheetings,

Ÿ   Installation of site hoardings,

Ÿ   Pipe pile & pre-boring works,

Ÿ   Re-provisional of turtle pond – peddle path,

Ÿ   Loop detector installation works &

Ÿ   UMP installation works.

.

Ÿ   Tree & root pruning works

Ÿ   Tree transplanting works,

Ÿ   Tree works within off-site nursery compound,

Ÿ   Drainage improvement works,

Ÿ   Sheet piling works,

Ÿ   Demarcation of graphics,

Ÿ   Erection of noise absorption sheetings,

Ÿ   Installation of site hoardings,

Ÿ   Sheet piling, pipe piling, ground pre-treatment & pre-boring works,

Ÿ   Re-provisional of turtle pond – peddle path &

Ÿ   Construction of Bowling Green Office.

 

Ÿ   Tree & root pruning works

Ÿ   Tree transplanting works,

Ÿ   Tree works within off-site nursery compound,

Ÿ   Drainage improvement works,

Ÿ   Sheet piling works,

Ÿ   Demarcation of graphics,

Ÿ   Erection of noise absorption sheetings,

Ÿ   Installation of site hoardings and provision of concrete bund under the site hoardings,

Ÿ   Pipe piling, ground pre-treatment & pre-boring works,

Ÿ   Re-provisional of turtle pond – peddle path &

Ÿ   Construction of Bowling Green Office

2.5.9.     Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

Table 2.12     Principal Work Activities for Contract no. HY/2011/08

March 2013

April 2014

May 2014

Ÿ             N/A

.

Ÿ                  N/A

 

Ÿ   No physical construction activity on site

 

Remarks: The FEP for Contract no. HY/2011/08 was granted in May 2014 reporting month.

2.5.10.   Implementation status of the recommended mitigation measures during this reporting period is presented in Appendix 2.1.

3.         Monitoring Requirements

3.1.          Noise Monitoring

Noise Monitoring Stations

3.1.1.     The noise monitoring stations for the Project are listed and shown in Table 3.1 and Figure 3.1.  Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.1    Noise Monitoring Station

Station

Description

M1a

Harbour Road Sports Centre

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

*M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

M8

City Hall

* Remark 1: Location ID has been updated from M7 to M8 for City Hall

* Remark 2: M7e has become a reference station starting from 7 Aug 2012

Real time Noise Monitoring Stations

3.1.2.     The noise monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.2    Real Time Noise Monitoring Station

District

Station

Description