Contract
No: HK/2011/07 Wanchai Development Phase II and Central Wanchai
Bypass Sampling, Field Measurement and
Testing Work (Stage 2) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEp-06/364/2009/a and FEp-07/364/2009/a Quarterly Environmental Monitoring
and Audit Report
- December 2011 to February 2012 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre
Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
                         Raymond Dai Environmental Team Leader |
|
DATE: |
|
29 March
2012 |
1.1    Scope
of the Report
1.2    Structure
of the Report
2.   Project
Background
2.1    Background
2.2    Scope
of the Project and Site Description.
2.3    Division
of the Project Responsibility
2.4    Project
Organization and Contact Personnel
2.5    Principal
Work and Activities
3.   Monitoring
Requirements
3.1.    Noise
Monitoring
3.2.    Air
Monitoring
4.   Monitoring
Results
4.1.    Noise
Monitoring Results
4.2.    Real Time Noise
Monitoring Results
4.3.    Air Monitoring
Results
4.4.    Waste
Monitoring Results
5.1.    Noise
Monitoring
5.2.    Air
Monitoring
5.3.    Site
Audit
5.4.    Review
of the Reasons for and the Implications of Non-compliance
5.5.    Summary
of action taken in the event of and follow-up on non-compliance
6.   Complaints,
Notification of Summons and Prosecution
7.   Cumulative
Construction Impact due to the Concurrent Projects
lIST
OF TABLES
Table I      Principal Work Activities for Contract no.
HY/2009/17
Table II     Principal Work Activities for Contract no. HY/2009/18
Table III     Principal Work Activities for Contract no. HK/2009/01
Table IV     Principal Work Activities for Contract no. HK/2009/02
Table V     Principal Work Activities for Contract no. HY/2009/15
Table VI     Principal Work Activities for Contract no. HY/2009/19
Table 2.1    Schedule 2 Designated Projects under this Project
Table 2.2   Details of Individual Contracts under the Project
Table 2.3   Contact Details of Key Personnel
Table 2.4    Principal Work Activities for Contract no. HY/2009/17
Table 2.5    Principal Work Activities for Contract no. HY/2009/18
Table 2.6    Principal Work Activities for Contract no. HK/2009/01
Table 2.7    Principal Work Activities for Contract no. HK/2009/02
Table 2.8    Principal Work Activities for Contract no. HY/2009/15
Table 2.9    Principal Work Activities for Contract no. HY/2009/19
Table 3.1   Noise Monitoring Station
Table 3.2   Real Time Noise Monitoring Station
Table 3.3   Air Monitoring Stations
Table 4.1    Noise Monitoring Stations for Contract no. HY/2009/17
Table 4.2    Noise Monitoring Station for Contract no. HY/2009/18
Table 4.3    Noise Monitoring Stations for Contract nos. HK/2009/01 and
HK/2009/02
Table 4.4    Noise Monitoring Station for Contract nos. HY/2009/15
Table 4.5    Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.6   Real Time Noise Monitoring Station for Contract no. HY/2009/17
Table 4.7   Real Time Noise Monitoring Stations for Contract no.
HY/2009/19
Table 4.8    Air Monitoring Stations for Contract no. HY/2009/17
Table 4.7    Air Monitoring Stations for Contract no. HY/2009/18
Table 4.10   Air Monitoring Stations for Contract no. HK/2009/01
Table 4.11   Air Monitoring Station for Contract no. HK/2009/02
Table 4.12   Air Monitoring Station for Contract no. HY/2009/15
Table 4.13   Air Monitoring Stations for Contract no. HY/2009/19
Table 4.14  Details of Waste Disposal for Contract no. HY/2009/17
Table 4.15  Details of Waste Disposal for Contract no. HK/2009/01
Table 4.16  Details of Waste Disposal for Contract no. HK/2009/02
Table 4.17  Details of Waste Disposal for Contract no. HY/2009/18
Table 4.18  Details of Waste Disposal for Contract no. HY/2009/15
Table 4.19  Details of Waste Disposal for Contract no. HY/2009/19
Table 6.1   Cumulative Statistics on Complaints
Table 6.2   Cumulative Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure 2.1     Project Layout
Figure
2.2     Project Organization Chart
Figure 3.1      Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix
2.1   Environmental
Mitigation Implementation Schedule
Appendix 3.1   Action and Limit Level
Appendix
4.1   Noise
Monitoring Results and Graphical Presentations
Appendix 4.2   Real-time Noise Monitoring
Results and Graphical Presentations
Appendix
4.3   Air
Quality Monitoring Results and Graphical Presentations
Appendix 5.1   Event Action Plans
Appendix 6.1   Complaint Log
Appendix
6.2   Notification of Exceedance
Appendix 8.1   Construction Programme of
Individual Contracts
EXECUTIVE SUMMARY
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield
Depot - Advanced piling works under FEP-03/364/2009
Major construction activities for Contract no.
HK/2009/17 have been commenced on 5 October 2010. During this reporting period,
the principal work activities for Contract no. HY/2009/17 are summarized as
below:
Table I     Principal
Work Activities for Contract no. HY/2009/17
December 2011 |
January 2012 |
February 2012 |
ELS works
for basement construction for pile cap construction |
ELS works
for basement construction for pile cap construction |
ELS works
for basement construction for pile cap construction |
Contract no. HY/2009/18 - Central - Wan
Chai Bypass (CWB) - Central Interchange
under FEP-05/364/2009/A
Table
II    Principal Work Activities for
Contract no. HY/2009/18
December 2011 |
January 2012 |
February 2012 |
Instrumentation
works for Manholes and Intake Culvert Survey
Excavation
of trial pit
Drainage
work
Site
investigation and pre-drilling works
Diaphragm
wall construction
Hoarding
erection
Roadworks
Grout
curtain
Tree purning |
Instrumentation
works for Manholes and Intake Culvert Survey
Excavation
of trial pit
Drainage
work
Site
investigation and pre-drilling works
Diaphragm
wall construction
Hoarding
erection
Roadwork
Sheet-piling
Grout
curtain
Tree pruning |
Instrumentation
works for Manholes and Intake Culvert Survey
Excavation
of trial pit
Drainage
work
Site
investigation and pre-drilling works
Diaphragm
wall construction
Hoarding erection
Roadwork
Sheet-piling
Grout
curtain
Tree pruning |
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
Major construction activities for Contract no.
HK/2009/01 have been commenced on 25 August 2011. During this reporting period,
the principal work activities are summarized as below:
Table III    Principal Work
Activities for Contract no. HK/2009/01
December 2011 |
January 2012 |
February 2012 |
 /span>Diaphragm wall construction works for CWB
(stage 1).
Pre-drilling
works for CWB (stage 2).
Pre-bored H
pilling works for CWB (stage 1) |
Diaphragm
wall construction works for CWB
Pre-drilling
works for CWB (stage 2)
Pre-bored H
pilling works for CWB
Grouting
works along the southern side of HKCEC water channel |
Diaphragm
wall construction works for CWB (stage 1) and SCL protection Works
Diaphragm
wall construction works for CWB (stage2)
Pre-drill
works for CWB (stage 2)
Pre-bored H
pilling works for CWB (stage 1)
Pre-bored H
pilling for exhaust duct
Installation
of shoring system for construction of CWB Diaphragm wall (stage 1)
Installation
of shoring system for construction of exhaust duct structure at stage 1
Pre-treatment
works for construction of CWB Diaphragm wall (stage 2)
Guide wall
construction for construction of CWB Diaphragm wall (stage 2) |
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
Major construction activities for Contract no.
HK/2009/02 have been commenced on 26 April 2011. During this reporting period, the
principal work activities are summarized as below:
Table IV    Principal Work
Activities for Contract no. HK/2009/02
December 2011 |
January 2012 |
February 2012 |
Tunnel bored
pile works at WCR1 area
Toe grout at
WCR1 area.
Shear pin at
WCR1 area.
Pumping test
at WCR1 area.
King Post at
WCR1 area.
West
bulkhead capping beam.
Steel deck
support for cooling main.
Working deck
B at WCR1.
Deep
excavation of CWB at the eastern area of working deck B. |
Toe grout at
WCR1 area
Shear pin at
WCR1 area
Pumping test
at WCR1 area
King Post at
WCR1 area
Deep
excavation of CWB at the eastern area of working deck B |
Shear pin
and Pumping test at WCR1 area. |
Contract no. HY/2009/15 - Central-Wanchai
Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
Major construction activities for Contract no.
HY/2009/15 has been commenced on 13 July 2011. During this reporting period,
the principal work activities are summarized as below:
Table V    Principal Work Activities for Contract no.
HY/2009/15
December 2011 |
January 2012 |
February 2012 |
Seawall
block construction, reclamation work and diaphragm wall construction
preparation works at TS4
Diaphragm
wall construction at TS1 and TPCWAE
Night time
protection works at CHT
Construction
of dewatering well at Hung Hing Road and POC
Precautionary
works at Abutment A |
Seawall
block construction, reclamation work and diaphragm wall construction preparation
works at TS4
ELS works at
TS1 and TPCWAE
Night time
protection works at CHT
Construction
of dewatering well at Hung Hing Road and POC
Precautionary
works at Abutment A |
Diaphragm
wall construction preparation works at TS4
ELS works at
TS1 and TPCWAE
Night time
protection works at CHT
Cut off wall
preparation works at Hung Hing Road and POC |
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
Major construction activities for Contract no.
HY/2009/19 have been commenced on March 2011. During this reporting period, the
principal work activities are summarized as below:
Table VI    Principal Work Activities for Contract no.
HY/2009/19
December 2011 |
January 2012 |
February 2012 |
Preparation
works and concreting of marine piles
Fabrication
of bored piling platform
Bored piling
Ground
contamination assessment
D-wall
Construction
Sheet piling
for Box Culvert T
Construction
works for Box Culvert T |
Preparation
works and concreting of marine piles
Fabrication
of bored piling platform
Bored piling
Ground
contamination  /span>assessment
D-wall Construction
Construction
works for Box Culvert T |
Preparation
works and concreting of marine piles
Fabrication
of bored piling platform
Bored piling
(Land)
Ground
contamination assessment
D-wall Construction
(North & South Section)
Guide wall
construction for D-wall / Barette at North side
Construction
works for Box Culvert T
Marine
Piling
Preparing
for fabrication of temporary steel bridge for Culvert U
Construction
of Jetty |
Noise Monitoring
 /span>
Air Quality
Monitoring
Complaints,
Notifications of Summons and Successful Prosecutions
1.1.1.
Lam Geotechnics Limited (LGL) has been
appointed to work as the Environmental Team (ET) under Environmental Permit no.
EP-364/2009A and Further Environmental permit nos.
FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A,
FEP-06/364/2009/A and FEP-07/364/2009/A to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
and in the EM&A Manual of the approved EIA Report for Central-Wan Chai
Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental
monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and  /span>Environmental Monitoring and Audit Requirements under
Particular Specification Section 27.
1.1.3.
This report documents the finding of
EM&A works during the period from 28th November 2011 to 27th February 2012.
Section 1     Introduction  details
the scope and structure of the report.
Section 2     Project
Background  summarizes background and scope of the project, site
description, project organization and contact details of key personnel during
the reporting period.
Section 3     Monitoring
Requirements  summarizes all monitoring parameters, monitoring
locations, monitoring frequency,
duration and action plan.
Section 4     Monitoring
Results  summarizes the monitoring results obtained in the
reporting period.
Section 5     Compliance Audit  
summarizes the auditing
of monitoring results, all exceedances environmental parameters.
Section 6     Complaints, Notification of summons and Prosecution  
summarizes the cumulative statistics on
complaints, notification of summons and prosecution
Section 7     Cumulative Construction Impact due to the Concurrent Projects  summarizes the relevant cumulative construction impact due to the
concurrent activities of the concurrent Projects.
Section 8     Conclusion
2.1.1.
“Wan Chai Development phase II and
Central-Wan Chai Bypass and “Central-Wan Chai Bypass and Island Eastern
Corridor Link (hereafter called “the Project  are Designed Project (DP) under
the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA)
Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register
No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and
11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development
Phase II (WDII) is to provide land at Wan Chai North and North Point for
construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link
(CWB). Land formed under the project will be developed as a world-class
waterfront promenade joining that at the new Central waterfront for public
enjoyment.
2.1.3.
There is a compelling and present need
for the CWB to provide relief to the very congested east-west Connaught Road
Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is
currently operating beyond its capacity. The CWB will provide relief to the
existing congestion along the Corridor and cater for the anticipated growth of
traffic on Hong Kong Island. Without the CWB and its access roads, there will
not be sufficient capacity to serve the heavy traffic demands at both strategic
and local levels.
2.2.1.
Design and
Construction of Central  Wan Chai Bypass and Island Eastern Corridor Link
under the Project involves the construction and operation of a trunk road and its
road tunnel more than 800m in length between portals that is shown at Figure 2.1.
2.2.2.
The study area
encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
 -
A dual
three-lane trunk road, approximately 4.5 km in length, and tunnel approximately
3.7 km in length defined from the connection with the existing Rumsey Street
Flyover in Central, through to a connection with the existing Island Eastern
Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
 -
The Central
Interchange near the Rumsey Street Flyover to provide road connections to the
Central area;
 -
Tunnel control
buildings and ventilation buildings;
 -
Slip roads to
connect the CWB to the local road system in the Wan Chai North and Causeway Bay
area;
 -
Associated
road lighting, road signing, traffic control and surveillance system; and
 -
Other
associated works.
2.2.3.
The project also contains various
Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be
granted by the DEP before they may be either constructed or operated. Table
2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations
of these Schedule 2 DPs.
Table
2.1   Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. 
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits such that the impact
monitoring stations are sub-divided accordingly to facilitate the
implementation of EM&A programme and to streamline the EM&A reporting
for individual FEP holders correspondingly.
2.3.2.
In the reporting period, all the contracts were commenced and
contract no. 04/HY/2006 had been completed. The details of individual
contracts are summarized in Table2.2.
Table
2.2  Details of Individual Contracts
under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central  Wan Chai Bypass (CWB)  Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre  Tunnel Works |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1 |
13 July 2011 |
HY/2009/19 |
Central  Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil
Engineering and Development Department and Highways Department are the overall
project controllers for the Wan Chai Development Phase II and Central-Wan Chai
Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and
lines of communication with respect to environmental protection works are shown
in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3  Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Lam Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
Project Manager |
Mr. K. S. Law |
9090 1378 |
2566 7522 |
Site Agent |
Mr. Tony Au |
9725 5874 |
2566 7522 |
||
Sub Agent |
Mr. Johnny Wong |
9725 5870 |
2566 7522 |
||
Chun Wo  Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
Mr. PL Yue |
2162 9909 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Sub Agent |
Mr. Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 2467 |
|||
Construction
Manager |
Mr KK Yuen |
9498 1213 |
|||
Construction
Manager |
Mr. Andy Yu |
9648 4896 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Environmental
Supervisor |
Ms. Kiwi Chan |
6227 8840 |
|||
|
|
Environmental
Supervisor |
Mr. Yeung Sze King |
9047 9952 |
|
Environmental
Supervisor |
Mr. Les Chow |
6692 2423 |
|
||
Environmental
Supervisor |
Mr. Otto Yau |
9260 4485 |
|
||
Chun Wo  CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658-3002 |
2827 9996 |
Site Agent |
Mr. Mak Kam Wing |
3658-3044 |
|||
Quality & Environmental Manager |
Mr. C.P. Ho |
3658-3000 |
|||
Environmental Officer |
Ms Flora Ng |
3658-3064 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Engineer |
Mr. Simon Wong |
9281 4346 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214 7700 |
2140 6799 |
Deputy Site Agent |
Mr. Desmond Sze |
2214 7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2566 2192 |
Site Agent |
Mr. P J Fan |
3557 6368 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Environmental Supervisor |
Mr. Kelven Yip |
3557 6347 |
|||
Environmental Supervisor |
Mr. Tim Fung |
3557 6349 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team
Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
Major
construction activities for Contract no. HK/2009/17 have been commenced on 5
October 2010. During this reporting period, the principal work activities for Contract
no. HY/2009/17 are summarized in Table2.4.
Table 2.4   Principal Work Activities for Contract no. HY/2009/17
December 2011 |
January 2012 |
February 2012 |
ELS works for
basement construction for pile cap construction |
ELS works
for basement construction for pile cap construction |
ELS works
for basement construction for pile cap construction |
Table 2.5   Principal Work Activities for Contract no.
HY/2009/18
December 2011 |
January 2012 |
February 2012 |
Instrumentation
works for Manholes and Intake Culvert Survey
Excavation
of trial pit
Drainage
work
Site
investigation and pre-drilling works
Diaphragm
wall construction
Hoarding
erection
Roadworks
Grout
curtain
Tree purning |
Instrumentation
works for Manholes and Intake Culvert Survey
Excavation
of trial pit
Drainage
work
Site
investigation and pre-drilling works
Diaphragm
wall construction
Hoarding
erection
Roadwork
Sheet-piling
Grout
curtain
Tree pruning |
Instrumentation
works for Manholes and Intake Culvert Survey
Excavation
of trial pit
Drainage
work
Site
investigation and pre-drilling works
Diaphragm
wall construction
Hoarding
erection
Roadwork
Sheet-piling
Grout
curtain
Tree pruning |
2.5.3.
Major
construction activities for Contract no. HK/2009/01 have been commenced on 25
August 2011. During this reporting period, the principal work activities are
summarized in Table2.6:
Table 2.6   Principal Work Activities
for Contract no. HK/2009/01
December 2011 |
January 2012 |
February 2012 |
 /span>Diaphragm wall construction works for CWB
(stage 1).
Pre-drilling
works for CWB (stage 2).
·Pre-bored H
pilling works for CWB (stage 1) |
Diaphragm
wall construction works for CWB
Pre-drilling
works for CWB (stage 2)
Pre-bored H
pilling works for CWB
Grouting
works along the southern side of HKCEC water channel |
Diaphragm
wall construction works for CWB (stage 1) and SCL protection Works
Diaphragm
wall construction works for CWB (stage2)
Pre-drill
works for CWB (stage 2)
Pre-bored H
pilling works for CWB (stage 1)
Pre-bored H
pilling for exhaust duct
Installation
of shoring system for construction of CWB Diaphragm wall (stage 1)
Installation
of shoring system for construction of exhaust duct structure at stage 1
Pre-treatment
works for construction of CWB Diaphragm wall (stage 2)
Guide wall
construction for construction of CWB Diaphragm wall (stage 2) |
2.5.4.
Major
construction activities for Contract no. HK/2009/02 have been commenced on 26 April 2011. During this reporting period, the principal work activities are
summarized in Table2.7:
Table
2.7   Principal Work Activities for Contract no. HK/2009/02
December 2011 |
January 2012 |
February 2012 |
Tunnel bored
pile works at WCR1 area
Toe grout at
WCR1 area.
Shear pin at
WCR1 area.
Pumping test
at WCR1 area.
King Post at
WCR1 area.
West
bulkhead capping beam.
Steel deck
support for cooling main.
Working deck
B at WCR1.
Deep
excavation of CWB at the eastern area of working deck B. |
Toe grout at
WCR1 area
Shear pin at
WCR1 area
Pumping test
at WCR1 area
King Post at
WCR1 area
Deep
excavation of CWB at the eastern area of working deck B |
Shear pin
and Pumping test at WCR1 area. |
2.5.5.
Major
construction activities for Contract no. HY/2009/15 have been commenced on 13
July 2011. During this reporting period, the principal work activities are
summarized in Table 2.8:
Table
2.8   Principal Work Activities for
Contract no. HY/2009/15
December 2011 |
January 2012 |
February 2012 |
Seawall
block construction, reclamation work and diaphragm wall construction
preparation works at TS4
Diaphragm
wall construction at TS1 and TPCWAE
Night time
protection works at CHT
Construction
of dewatering well at Hung Hing Road and POC
Precautionary
works at Abutment A |
Seawall
block construction, reclamation work and diaphragm wall construction
preparation works at TS4
ELS works at
TS1 and TPCWAE
Night time
protection works at CHT
Construction
of dewatering well at Hung Hing Road and POC
Precautionary
works at Abutment A |
Diaphragm
wall construction preparation works at TS4
ELS works at
TS1 and TPCWAE
Night time
protection works at CHT
Cut off wall
preparation works at Hung Hing Road and POC |
2.5.6.
Major
construction activities for Contract no. HY/2009/19 have been commenced on
March 2011. During this reporting period, the principal work activities are
summarized in Table 2.9:
Table
2.9   Principal Work Activities for
Contract no. HY/2009/19
December 2011 |
January 2012 |
February 2012 |
Preparation
works and concreting of marine piles
Fabrication
of bored piling platform
Bored piling
Ground
contamination assessment
D-wall
Construction
Sheet piling
for Box Culvert T
Construction
works for Box Culvert T |
Preparation
works and concreting of marine piles
Fabrication
of bored piling platform
Bored piling
Ground
contamination assessment
D-wall Construction
Construction
works for Box Culvert T |
Preparation
works and concreting of marine piles
Fabrication
of bored piling platform
Bored piling
(Land)
Ground
contamination assessment
D-wall Construction
(North & South Section)
Guide wall
construction for D-wall / Barette at North side
Construction
works for Box Culvert T
Marine
Piling
Preparing
for fabrication of temporary steel bridge for Culvert U
Construction
of Jetty |
2.5.7.
Implementation status of the recommended
mitigation measures during this reporting period is presented in Appendix 2.1.
3.1.1.
The noise monitoring stations for the
Project are listed and shown in Table 3.1 and Figure 3.1.  /span>Appendix 3.1 shows the established Action/Limit Levels for the monitoring
works.
Table 3.1  Noise Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun
Area |
M3a |
Tung Lo Wan
Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist
Church Henrietta Secondary School |
M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
Real time Noise
Monitoring Stations
3.1.2.
The noise monitoring stations for the
Project are listed and shown in Table 3.2 and
Figure 3.1..
Appendix 3.1 shows the established Action/Limit Levels for the monitoring
works.
Table 3.2  Real Time Noise Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring Parameters, Frequency and Duration
3.1.3.
The construction noise level
shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes)
shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For
all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
3.1.4.
Noise monitoring shall be carried
out at all the designated monitoring stations. The monitoring frequency shall
depend on the scale of the construction activities. The following is an initial
guide on the regular monitoring frequency for each station on a weekly basis
when noise generating activities are underway:
 -
One set of measurements between
0700 and 1900 hours on normal weekdays.
3.1.5.
Real time noise shall be carried
out at the designated monitoring stations. The following is an initial guide on
the regular monitoring frequency for each station on a 24 hours daily basis
when noise generating activities are underway:
 -
One set of measurements between
0700 and 1900 hours on normal weekdays.
 -
One set of measurements between 1900
and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.
 -
One set of measurements between 2300
and 0700 hours on next day on everyday.
3.1.6.
If construction works are
extended to include works during the hours of 1900  0700 as well as public
holidays and Sundays, additional weekly impact monitoring shall be carried out
during respective restricted hours periods. Applicable permits under NCO shall
be obtained by the Contractor.
Monitoring Equipment
3.1.7.
As referred to in the Technical
Memorandum  issued under the NCO, sound level meters in compliance with the
International Electrotechnical Commission Publications 651: 1979 (Type 1) and
804: 1985 (Type 1) specifications shall be used for carrying out the noise
monitoring. Immediately prior to and following each noise measurement the
accuracy of the sound level meter shall be checked using an acoustic calibrator
generating a known sound pressure level at a known frequency. Measurements may
be accepted as valid only if the calibration level from before and after the
noise measurement agree to within 1.0 dB.
3.1.8.
Noise measurements shall not be
made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts
exceeding 10 m/s. The wind speed shall be checked with a portable wind speed
meter capable of measuring the wind speed in m/s.
3.1.9.
The sound level meter shall be
checked using an acoustic calibrator generating a known sound pressure level at
a known frequency before deployment to the site and during each site visit.
Measurements may be accepted as valid only if the calibration level from before
and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring
Stations
3.2.1.
The air monitoring stations for the
Project are listed and shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table 3.3  Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
Causeway Bay Community
Centre |
Causeway Bay |
CMA3a |
Future CWB site office
at Wanchai Waterfront Promenade |
Causeway Bay |
CMA4a |
Society for the Prevention
of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to Pedestrian Plaza |
Wan Chai |
CMA6a |
Future AECOM site
office at Work Area |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (Western End of Podium) |
Central |
Air Monitoring Parameters,
Frequency and Duration
3.2.2.
One-hour and 24-hour TSP levels
should be measured to indicate the impacts of construction dust on air quality.
The 24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
3.2.3.
All relevant data including
temperature, pressure, weather conditions, elapsed-time meter reading for the
start and stop of the sampler, identification and weight of the filter paper,
and any other local atmospheric factors affecting or affected by site
conditions, etc., shall be recorded down in detail.
3.2.4.
For regular impact monitoring,
the sampling frequency of at least once in every six-days, shall be strictly
observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour
TSP monitoring, the sampling frequency of at least three times in every
six-days should be undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5.
High volume samplers (HVSs) in
compliance with the following specifications shall be used for carrying out the
1-hour and 24-hour TSP monitoring:
 -
0.6 - 1.7 m3 per minute
adjustable flow range;
 -
Equipped with a timing / control
device with +/- 5 minutes accuracy for 24 hours operation;
 -
Installed with elapsed-time meter
with +/- 2 minutes accuracy for 24 hours operation;
 -
Capable of providing a minimum
exposed area of 406 cm2;
 -
Flow control accuracy: +/- 2.5%
deviation over 24-hour sampling period;
 -
Equipped with a shelter to
protect the filter and sampler;
 -
Incorporated with an electronic
mass flow rate controller or other equivalent devices;
 -
Equipped with a flow recorder for
continuous monitoring;
 -
Provided with a peaked roof
inlet;
 -
Incorporated with a manometer;
 -
Able to hold and seal the filter
paper to the sampler housing at horizontal position;
 -
Easily changeable filter; and
 -
Capable of operating continuously
for a 24-hour period.
3.2.6.
Initial calibration of dust
monitoring equipment shall be conducted upon installation and thereafter at
bi-monthly intervals. The transfer standard shall be traceable to the
internationally recognized primary standard and be calibrated annually. The
concern parties such as IEC shall properly document the calibration data for
future reference. All the data should be converted into standard temperature
and pressure condition.
3.2.7.
Laboratory Measurement / Analysis
3.2.8.
A clean laboratory with constant
temperature and humidity control, and equipped with necessary measuring and
conditioning instruments to handle the dust samples collected, shall be
available for sample analysis, and equipment calibration and maintenance. The
laboratory should be HOKLAS accredited.
3.2.9.
Filter paper of size 8" x
10" shall be labelled before sampling. It shall be a clean filter paper
with no pinholes, and shall be conditioned in a humidity-controlled chamber for
over 24-hours and be pre-weighed before use for the sampling.
3.2.10. After sampling, the filter paper loaded with dust shall be kept in a
clean and tightly sealed plastic bag. The filter paper shall then be returned
to the laboratory for reconditioning in the humidity controlled chamber
followed by accurate weighing by an electronic balance with readout down to 0.1
mg. The balance shall be regularly calibrated against a traceable standard.
3.2.11. All the collected samples shall be kept in a good condition for 6 months
before disposal.
4.0.1.
Monitoring for report of review
baseline noise level was performed from 11 April 2011 to 8 June 2011. Then the report was submitted on the 20 June
2011, verified by IEC on 18 July 2011 and was approved by ER by January
2012. The new baseline is used for the
noise calculation starting from the January 2012 reporting month.
4.0.2.
The environmental monitoring will
be implemented based on the division of works areas of each designed project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing
work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure 2.1
and Figure 3.1. The monitoring results are
presented in according to the Individual Contract(s).
4.0.3.
In the reporting period, the concurrent
contracts are as follows:
Contract no. HY/2009/15  
Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
Contract no. HY/2009/17  Central
–Wanchai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under
FEP-03/364/2009
Contract no. HY/2009/18  Central
–Wanchai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
Contract no. HY/2009/19  Central
 Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009
Contract no. HK/2009/01 –Wanchai
Development Phase II  Central –Wanchai Bypass at Hong Kong Convention and
Exhibition Centre
Contract no. HK/2009/02 Wanchai
Development Phase II  Central- Wanchai Bypass at Wanchai East
Contract no. HY/2009/17 –Central - Wanchai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
4.1.1.
The proposed division of noise
monitoring stations for Contract no. HY/2009/17 is summarized in Table
4.1 below:
Table 4.1   Noise Monitoring Stations for Contract no.  /span>HY/2009/17
Station |
Description |
M4b |
Victoria Centre |
Reporting
month of December 2011
4.1.2.
No limit level exceedance was
recorded during daytime of reporting month of December 2011. One action level exceedance was recorded as one complaint regarding to
noise was received on 20 December 2011 in this reporting period.
Reporting month of January 2012
4.1.3.
No limit level exceedance was
recorded during daytime of reporting month of January 2012. One action level exceedance was
recorded as one complaint regarding to noise was received on 30 December 2011
in this reporting period.
Reporting month of February 2012
4.1.4.
No exceedance was recorded in the February 2012 reporting period.
4.1.5.
Noise monitoring results measured
in this reporting period are reviewed and summarized. Details of graphical presentation can be referred in Appendix 4.1. 
Contract no. HY/2009/18 - Central - Wanchai Bypass
(CWB)  Central Interchange under FEP-05/364/2009/A
4.1.6.
Noise monitoring for the Central
Interchange works under contract no. HY/2009/18 was commenced on 22 April
2011.The proposed division of noise monitoring stations for Contract no.
HY/2009/18 are summarized in Table 4.2 below.
Table 4.2   Noise Monitoring Station for Contract no. HY/2009/18
Station |
Description |
M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
Reporting month of December 2011
4.1.7.
No action level and one limit
level exceedance was recorded at M7e during daytime on 20 December 2011. After
checking contractor’s work schedules and investigation found that nearby
traffic as the major noise sources contributor, and the limit level
exceedance was considered as non-project related.
Reporting month of January 2012
4.1.8.
No limit and action level
exceedance was recorded during daytime of reporting month of January 2012.
Reporting month of February 2012
4.1.9.
No limit and action level exceedance
was recorded during daytime of reporting month of February 2012.
4.1.10.
Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in
Appendix 4.1. Details of the Notification of Exceedance
can be referred in Appendix 6.2.
Contract no. HK/2009/01 - Wanchai Development Phase II - Central -
Wanchai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works
under FEP-02/364/2009 and Contract no. HK/2009/02 - Wanchai Development Phase
II - Central - Wanchai Bypass at Wanchai East (CWB Tunnel) under
FEP-01/364/2009
4.1.11. The commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011 and HK/2009/02 under
FEP-01/364/2009 is on 26 April 2011.The proposed division of air monitoring
stations are summarized in Table 4.3 below.
Table 4.3   Noise Monitoring Stations for Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
4.1.12. Three limit level exceedances were recorded at M1a on 29 November, 6
December 2011 and 10 January 2012 during restricted hour.  /span>All exceedances were considered non-project
related.
4.1.13.
Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1 and the complaints can be referred in
Appendix
6.1. Details of the Notification of Exceedance can be referred in
Appendix
6.2.
Contract no. HY/2009/15 - Central-Wanchai
Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
4.1.14. The commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise monitoring was
commenced on 13 July 2011. The proposed division of noise monitoring
stations are summarized in in Table 4.4 below.
Table 4.4   Noise Monitoring Station for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.15. No action level and limit level exceedance was recorded during daytime
of the reporting period.
4.1.16.
Details
of noise monitoring results and graphical presentation can be referred in
Appendix 4.1 and the complaints can be referred in
Appendix
6.1. 
4.1.17. Noise monitoring for the tunnel works under contract no. HY/2009/19 was
commenced on 24 April 2011. The proposed division of noise monitoring stations
are summarized in Table 4.5 below.
Table 4.5   Noise Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
4.1.18.
No limit level exceedance was
recorded in the period between December 2011 to February 2012.
4.1.19.
Two action limit level
exceedances were recorded as two complaints regarding two noise complaints
regarding to noise were received on 20 and 30 December 2011.
4.1.20.
Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in
Appendix 4.1 and the Notification of Exceedance can be
referred in Appendix 6.2.
Contract no. HY/2009/17
–Central - Wanchai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works
under FEP-03/364/2009 and Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under
FEP-07/364/2009/A
4.2.1.
The proposed division of real
time noise monitoring stations are summarized in Table 4.6 below.
Real time noise monitoring for the piling works under contract no. HY/2009/17
was commenced on 5 October 2010.
Table 4.6  Real Time Noise Monitoring
Station for Contract no. HY/2009/17
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
Real time noise
monitoring results and graphical presentation during night time period are for
information only.
4.2.2.
No project
related action and limit level exceedance were recorded in the reporting
period. Real time noise monitoring results measured in this reporting period are
reviewed and summarized. Details of real time
noise monitoring results and graphical presentation can be referred to Appendix 4.2
4.2.3.
The proposed division of noise
monitoring stations are summarized in Table 4.7 below. Real time
noise monitoring for major construction works under contract no. HY/2009/19 was
commenced on 24 April 2011.
Table 4.7  Real Time Noise Monitoring
Stations for Contract no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
RTN2 |
North Point |
Oil Street Community Liaison Center |
Real time noise
monitoring results and graphical presentation during night time period are for
information only.
4.2.4.
No project
related action and limit level exceedance were recorded in the reporting
period. Real time noise monitoring results measured in this reporting period are
reviewed and summarized. Details of real time noise monitoring results and
graphical presentation can be referred to Appendix 4.2
4.3.1
Due to lack of
electricity supply at station CMA1b, 24hr-TSP was rescheduled from 4, 10, 20, 26 January and 13 February 2012 to 5, 11, 21, 27 January and 16 February 2012.
4.3.2
Due to lack of
electricity supply at station CMA2a, 24hr-TSP was rescheduled from 12 December 2011 to 13
December 2011.
4.3.3
Due to lack of
electricity supply at station CMA3a, 24hr-TSP was rescheduled from 16 January and 13 February 2012 to 17 January and 14 February 2012.
4.3.4
Due to lack of
electricity supply at station MA1w, 24hr-TSP was rescheduled from 16 January 2012 to 17 January 2012.
4.3.5
Due to lack of
electricity supply at station CMA5a, 24hr-TSP was rescheduled from 18 February 2012 to 20 February 2012.
Contract no. HY/2009/17
–Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling
works under FEP-03/364/2009
4.3.6
The proposed division of air
monitoring stations are summarized in Table 4.8 below. Air monitoring for
the piling works under contract no. HY/2009/17 was commenced on 8 October 2010.
Table 4.8   Air Monitoring Stations
for Contract no. HY/2009/17
Station |
Description |
CMA2a |
Causeway Bay Community Centre |
4.3.7
No exceedance was recorded in the
reporting period. Air quality monitoring results measured in this reporting
period are reviewed and summarized. 
Details of air monitoring results and graphical presentation can be
referred in Appendix 4.3. 
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  Central
Interchange under FEP-05/364/2009/A
4.3.8
The proposed division of air
monitoring stations are summarized in Table 4.9 below.
Table 4.7   Air Monitoring Stations
for Contract no.
HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
4.3.9
Air monitoring for the Central
Interchange works under contract no. HY/2009/18 was commenced on 21 April 2011.
4.3.10
No exceedance was recorded in the
reporting period. Air quality monitoring results measured in this reporting
period are reviewed and summarized. 
Details of air monitoring results and graphical presentation can be
referred in Appendix 4.3. 
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
4.3.11
The commencement of construction
works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. The proposed division of air
monitoring stations are summarized in Table 4.10 below.
Table 4.10 Air Monitoring Station for
Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to Pedestrian Plaza |
4.3.12
No exceedance was recorded in the
reporting period. Air quality monitoring results measured in this reporting period
are reviewed and summarized. Details of
air monitoring results and graphical presentation can be referred in
Appendix 4.3. 
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
Table 4.11 Air Monitoring Station for
Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
4.3.14
No exceedance was recorded in the
reporting period. Air quality monitoring results measured in this reporting
period are reviewed and summarized. 
Details of air monitoring results and graphical presentation can be
referred in Appendix 4.3. 
Contract no. HY/2009/15 - Central-Wanchai Bypass  Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
4.3.15
The commencement of construction
works for Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. The proposed division of air monitoring stations
are summarized in Table 4.12 below.
Table
4.12 Air Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB site office at Wanchai
Waterfront Promenade |
4.3.16
No exceedance was recorded in the
reporting period. Air quality monitoring results measured in this reporting
period are reviewed and summarized. Details
of air monitoring results and graphical presentation can be referred in Appendix 4.3. 
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link 
under FEP-07/364/2009/A
4.3.17 Air monitoring for the tunnel works was commenced on 26 April 2011 for
Contract no. HY/2009/19 under FEP-07/364/2009/A. The
proposed division of air monitoring stations are summarized in Table 4.13 below.
Table 4.13 Air Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil St Community Liaison Centre |
CMA2a |
Causeway Bay Community Centre |
4.3.18.
No exceedance was recorded in the
reporting period. Air quality monitoring results measured in this reporting
period are reviewed and summarized. 
Details of air monitoring results and graphical presentation can be
referred in Appendix 4.3. 
Contract no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield
Depot - Advanced piling works under FEP-03/364/2009
4.4.1.
No inert and non-inert
C&D waste was disposed in the reporting period. Details of the waste flow
table are summarized in Table 4.14
Table 4.14 Details of Waste Disposal for Contract no. HY/2009/17
Waste Type |
Quantity
this quarter, m3 |
Cumulative
Quantity-to-Date, m3 |
Disposal /
Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
N/A |
||
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Contract nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under
FEP-02/364/2009
4.4.2.
Inert and non-inert C&D waste
was disposed of in this reporting period. Details of the waste flow table are
summarized in Table 4.15.
Table 4.15 Details of Waste Disposal for
Contract no. HK/2009/01
Inert C&D materials disposed |
4673.58 |
16540.09 |
TKO137, TM38 |
Inert C&D materials recycled |
NIL |
389.96 |
N/A |
Non-inert C&D materials disposed |
105.4 |
609.96 |
SENT Landfill |
Non-inert C&D materials recycled |
8823 |
135754 |
N/A |
Chemical waste disposed |
530 |
5600 |
Kwun Kee (Chemical Waste Collector) |
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
4.4.3.
Inert and non inert C&D waste
were disposed of in this reporting period. Details of the waste flow table are
summarized in Table 4.16.
Table 4.16 Details of Waste Disposal for
Contract no. HK/2009/02
Inert C&D materials disposed |
30,299 |
87,749 |
TKO137, TM 38 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
90 |
146 |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
2,071 |
3,175 |
N/A |
Contractor
clarified that no Inert and Non-inert C&D materials disposed in
June 2011
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB)  Central Interchange under
FEP-05/364/2009/A
4.4.4.
Inert and non-inert C&D waste
was disposed of in this reporting period. Details of the waste flow table are
summarized in Table 4.17.
Table 4.17 Details of Waste Disposal for
Contract no. HY/2009/18
Inert C&D materials disposed |
5829 |
T.K.O. 137 |
|
Inert C&D materials recycled |
NIL |