Contract No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and Testing Work
(Stage 2) Environmental
Permit no. EP-356/2009, Further Evironmental permit nos. fep-01/356/2009,
fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 and fep-05/356/2009 Quarterly
Environmental Monitoring
and Audit Report
- DeCember 2011 to February 2012 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai,
H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED
by: |
|
                         Raymond Dai Environmental Team Leader |
|
DATE: |
|
29 March 2012 |
1.1    Scope of the Report
1.2    Structure of the Report
2.   Project Background
2.1    Background
2.2    Scope
of the Project and Site Description
2.3    Division of the Project
Responsibility
2.4    Project Organization and Contact
Personnel
2.5    Principle
Work and Activities
3.   Monitoring Requirements
3.1.    Noise Monitoring
3.2.    Air Monitoring
3.3.    Water Quality Monitoring
4.   Monitoring Results
4.1.    Noise Monitoring Results
4.2.    Real Time Noise Monitoring Results
4.3.    Air Monitoring Results
4.4.    Water Monitoring Results
4.5.    Waste Monitoring Results
5.1.    Noise Monitoring
5.2.    Real-time Noise Monitoring
5.3.    Air Monitoring
5.4.    Water Quality Monitoring
5.5.    Site Audit
5.6.    Review
of the Reasons for and the Implications of Non-compliance
5.7.    Summary
of action taken in the event of and follow-up on non-compliance
6.   Complaints, Notification
of Summons and Prosecution
7.   Cumulative Construction
Impact due to the Concurrent Projects.
lIST OF
TABLES
Table I        Principle Work Activities for Contract no. HY/2009/11
Table II       Principle
Work Activities for Contract no. HK/2009/01
Table III       Principle
Work Activities for Contract no. HK/2009/02
Table IV      Principle Work Activities for Contract no. HY/2009/15
Table V       Principle Work Activities for Contract no. HK/2010/06
Table VI      Principle Work Activities
for Contract no. HY/2009/19
Table 2.1      Schedule 2 Designated Projects under this Project
Table 2.2     Details of Individual Contracts under the Project
Table 2.3     Contact Details of Key Personnel
Table 2.4      Principle Work Activities for Contract no. HY/2009/11
Table 2.5      Principle Work Activities for Contract no. HK/2009/01
Table 2.6      Principle Work Activities for Contract no. HK/2009/02
Table 2.7      Principle Work Activities for Contract no. HY/2009/15
Table 2.8      Principle Work Activities for Contract no. HK/2010/06
Table 2.9      Principle
Work Activities for Contract no. HY/2009/19
Table 3.1     Noise
Monitoring Stations
Table 3.2     Real
Time Noise Monitoring Station
Table 3.3     Air
Monitoring Stations
Table 3.4      Marine
Water Quality Stations for Water Quality Monitoring
Table 3.5     Marine
Water Quality Monitoring Frequency and Parameters
Table 3.6      Marine Water Quality
Stations for Enhanced Water Quality Monitoring
Table 3.7      Marine Water Quality
Stations for Additional DO Monitoring
Table 4.1      Noise
Monitoring Stations for Contract no. 
HY/2009/11
Table 4.2      Noise Monitoring
Station for Contract nos. HK/2009/01 and HK/2009/02
Table 4.3      Noise
Monitoring Station for Contract nos. HY/2009/15
Table 4.4      Noise
Monitoring Station for Contract nos. HY/2009/19
Table 4.5     Real
Time Noise Monitoring Station for Contract no. HY/2009/11
Table 4.6     Real
Time Noise Monitoring Station for Contract no. HY/2009/19
Table 4.7     Air Monitoring
Stations for Contract no. HY/2009/11
Table 4.8      Air Monitoring Stations for Contract no. HK/2009/01
Table 4.9      Air Monitoring
Station for Contract no. HK/2009/02
Table 4.10     Air
Monitoring Station for Contract no. HY/2009/15
Table 4.11     Air
Monitoring Station for Contract no. HY/2009/19
Table 4.12    Water
Monitoring Stations for Contract no. 
HY/2009/11
Table 4.13     Water
Monitoring Stations for Contract no. HK/2009/01
Table 4.14     Water
Monitoring Stations for Contract no. HK/2009/02
Table 4.15     Water
Monitoring Stations for Contract no. HK/2010/06
Table 4.16     Water
Monitoring Stations for Contract no. HY/2009/15
Table
4.17     Water Monitoring Stations for
Contract no. HY/2009/19
Table 4.18     Summary of Water Quality Monitoring Exceedances in Reporting
period
Table 4.19    Details
of Waste Disposal for Contract no. HY/2009/11
Table 4.20    Details
of Waste Disposal for Contract no. HK/2009/01
Table 4.21    Details
of Waste Disposal for Contract no. HK/2009/02
Table 4.22    Details
of Waste Disposal for Contract no. HY/2009/15
Table 4.23    Details
of Waste Disposal for Contract no. HK/2010/06
Table 6.1     Cumulative
Statistics on Complaints
Table 6.2     Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1     Project
Layout
Figure 2.2     Project
Organization Chart
Figure 3.1     Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
2.1  Environmental Mitigation
Implementation Schedule
Appendix 3.1  Action and Limit Level
Appendix
4.1  Noise Monitoring Graphical Presentations
Appendix
4.2  Air Quality Monitoring Graphical Presentations
Appendix
4.3  Water Quality Monitoring Graphical Presentations
Appenidx 4.3a  Additional Dissolved Oxygen
Monitoring Results
Appendix 4.4  Real-time Noise Monitoring Results and Graphical Presentations
Appendix 5.1  Event Action Plans
Appendix 6.1  Complaint Log
Appendix 7.1  Construction Programme of
Individual Contracts
Construction Activities for the
Reported Period
Table I     Principle Work Activities for Contract
no. HY/2009/11
December 2011 |
January 2012 |
February 2012 |
Reclamation works;
Geo-textile laying;
Slotted panel
fixing;
Drainage
Construction works;
Installation of berm
blocks;
Concreting the
slopes of Open Channel U;
Construction of
in-situ mass concrete cooping;
Construction of
granite facing stone; and
Construction of
Seawall Type 8 |
The major work
activities for Contract no. HY/2009/11 was confirmed substantial complete by
RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19 and the FEP-01/356/2009 was under application of surrender in this
reporting period. |
The major work
activities for Contract no. HY/2009/11 was confirmed substantial complete by
RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19 and the FEP-01/356/2009 was under application of surrender in this
reporting period. |
Table II    Principle Work Activities for Contract no.
HK/2009/01
December 2011 |
January 2012 |
February 2012 |
Dredging works
within HKCEC Water Channel from CH190 to CH260 for Type 1 & 2
Sediment was commences and substantially
completed;
Removal of rock
armours from CH150 to CH180 at the North bank of HKCEC Water
Channel was
commenced and substantially completed;
A trial for Type 3
sediment disposal was carried out;
Installation of
sheet pile for cooling water intake at Dome Promenade between
CH120 and CH170;
Installation of
precast RC outfall at Zone B1-3;
Trench excavation
for the 4 nos. of cooling water discharge pipes at B1-3;
Reclamation of
HKCEC3W (up to CH130) within HKCEC Water Channel;
Installation of
cross -harbour water mains nos. B13, A14/B14 and A15/ B15;
Thrust block
construction for A9/B9 and A11/B11 was commenced;
Concrete coating at
flange joint of cross-harbour water mains nos. A7B7/A8B8,
A8B8/A9B9 and
A9B9/A10B10;
Rockfilling and rock
protection to cross-harbour watermains;
Installation of pipe
pile at TST (Land Portion) was commenced and substantially completed;
Grouting works at
TST seafront along the pipe piles
Dredging of Type 2
sediment from CH50 to CH250 for subsequent cross-harbour
watermains
installation off Tsim Sha Tsui;
Mainlaying works at
Zone B1-5B, B1-6, B2-2, B4-2, B4-5, A1-5A, A3-2A, HKCEC,Zone B1-6, B2-2 and B1-5B; Zone A1-5A1 and A3-5B;
Way In/Out, A2-3B
and A5-5;
Coring and Grouting
works for external wall of cooling pumping stations Nos. P4 & P5 at Zone B4-5;
Coring works for
external wall of cooling pumping station No P1 at Zone B4-2;
Heading No. H3,H4, H5, H7 and H13; was substantially completed.
GI duct laying works
at ZoneA4-3A and Zone A4-3B;
Trench excavation,
pipe laying works and chamber construction for a 1000 dia.
watermains (CHF) at |
Dredging works
within HKCEC Water Channel from CH190 to CH260 for Type 3 sediment was
commended.
Removal of rock armours
from CH160 to CH260 at the north bank of HKCEC Water Channel was
substantially completed.
Installation of
sheet pile for cooling water intake at Dome Promenade between CH120 and CH170
was in progress.
Reclamation of
HKCEC3W (up to CH130) within HKCEC Water Channel has been substantially
completed.
Installation of 4
nos. of submersible cooling water discharge pipes at B1-3 was substantially
completed.
Thrust block
construction for A9B9, A11B11, A12B12 and A13B13 were completed.
Concrete coating at
flange at joint of cross-harbour watermains nos. A10B10/A11B11, A11B11/A12B12
and A12B12/A12B13 were completed.
Rockfilling and rock
protection to cross-harbour watermains was currently in progress.
Grouting works at
TST seafront along the pipe pile wall was commenced.
Installation of pipe
pile at TST (Sea Protection) was substantially completed.
Dredging of Type 3
sediment at designated disposal site was carried out.
Mainlaying works at
Zone B1-5B, B1-6, B2-2, A3-2A, A3-5B and were in progress.
Cable ducting works
at Zone B5-2 was commenced.
Mainlaying works and
subsequent reinstatement in Zone B4-5 was completed.
Mainlaying works and
subsequent carriageway reinstatement in Zone A1-5A1, A4-3A,
A4-3B and HKCEC Way
In/Out had been completed.
Mainlaying works and
subsequent carriageway reinstatement in Zone A2-3B and A2-4A was completed.
Coring and grouting
works for external wall of cooling pumping station No. P1 at Zone B4-2 was
completed.
Pipe laying works at
Zone B4-2 was completed and GI ducting works was in progress.
Jacking pit
establishment for pipe laying works by heading method at Zone A1-5A1 has been
completed.
Mainlaying and
chamber construction works at the traffic island neat junction of
Trench excavation,
pipe laying works and chamber construction for a 1000 dis. Warermains (CHF)
at
Trench excavation
and pipe laying works for a 1000 dia. Watermains (CHE) at |
Marine Works
Dredging works
within HKCEC water Channel form CH190 to Ch260 for Type 2 sediment and Type 3 sediment.
Installation of
sheet pile for cooling water intake at Dome Promenade between CH120 and CH170
Reclamation of
HKCEC3W (up to CH140) within HKCEC Water Channel
Seawall
reinstatement and retaining wall construction at Wan Chai Lanfill in Zone
B1-3 Cross-harbour Watermains Installation
Rockfilling and rock
protection to cross-harbour watermains
Grouting works at
TST seafront along the pipe pile wall
Installation of pipe
pile at TST seafront for pre-splitting seawall blocks
Trench excavation
and installation of shoring system along the pipe pile wall at TST seafront
Dredging of Type 3
sediment from CH50 to CH250 for subsequent cross-habour watermains installation
off TST
Dredging works
underneath Avenue of Stars carried by telescopic excavator
Dredging works in
confined water by 9 in 1 barge
1.1.3 Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land)
Mainlaying works at
Zone B1-3, B1-5, B1-6, B2-2, B4-2, B4-4, B5-2, A1-1, A2-3C, A3-4B, A3-5B and
A4-2A, B4-4, A4-2A, A1-1, A1-4A, A2-3C and A3-4B
Mainlaying works and
subsequent carriageway reinstatement in Zone A5-5 and A3-2A
Cable ducting works
along
Heading No. H5, H7, H8 and H13 (mainlaying woks by trenchless method)
Mainlaying and
chamber construction works at the traffic island near junction of Trench excavation, pipe laying works and chamber construction
for a 1000 dia. watermains (CHF and CHE) at |
Table III    Principle Work Activities for Contract no.
HK/2009/02
December 2011 |
January 2012 |
February 2012 |
300mm thick topping
slab together with the make up slab below at northern portion commenced on 30 Nov 2011;
Concreting at Roof
Plinth, lift shaft up to +14.15mPD and Fire Service Pump room up to +14.15mPD of Passenger Terminal Building were completed;
E&M and ABWF of
ELS of Noise Barrier
2 commenced on 29 Nov 2011 and nearly completed.
Casting of
pedestrian pavement above seawall coping Bay 4 to Bay 8 was completed on 13 December 2011;
Casting of the bus
shelter footing at
Precast slab
installation at the existing movable ramp was in progress;
Saw cutting of
existing slabs for the construction NB1 footing was completed;
E&M of P7, P8
& P9
Approximate 50m
cooling water pipe was laid at Harbour Centre,
Jacking pit at
ex-pet garden for the heading construction of cooling mains across
Convention Avenue
commenced;
Approximate 50m
cable duct was laid at
Construction of wash
out chamber at Centre were completed;
Trench excavation
and cooling mains installation along
Installation of PVC
and G.I cable ducts was ongoing at
Installation of
submarine outfall pipe was completed;
Dredging for
submarine outfall pipe was ongoing;
Concreting the Base
Slab of Wan Shing Street at Bay 24 was completed;
Concreting the wall
shaft and roof slab completed of Bay 24 were completed;
Bay 21 to Bay 24 of
Wan Shing Street were handover to HEC;
Slab at +3.10mPD and
+3.77 mPD and wall below were completed for the WSD Salt Water Pumping Station;
Excavation and
lateral support for DSD receiving pits were completed;
D610 pipe pile wall
construction at landside cofferdam of salt water intake culvert;
12 out of 12 nos of
pre-bored H-pile for box culverts N1 was casted as of 21November 2011;
Temporary working
platform was completed and pile cap construction was in progress at Portion 1B for the New Ferry Pier |
300mm thick topping
slab at northern portion was substantially completed on 20 January 2012.
Concreting of
structural slab at existing movable ramp was completed on 18 January 2012.
ABWFs and E&M
works of
Installation of glass
wall bearing at G/F and 1/F commenced on 22 December 2012 and completed on 5
January 2012.
ELS of Noise Barrier
NB2 was completed on 15 January 2012.
Blinding of Noise
Barrier NB2 footing was completed on 29 December 2012.
Steel fixing of
Noise Barrier NB2 was in progress.
Pedestrian diversion
above seawall coping Bay 4 to Bay 8 was implemented on 6 January 2011.
Bladder Tank steel
fixing and formwork erection are in progress.
E&M of P7, P8
& P9 were in progress.
Sheet piling works
of the Jacking pit at ex-pet garden commenced on 19 December 2011for the
heading construction of cooling mains across
Approximate 30m
cooling water pipe was laid at Harbour Centre,
Approximate 10m
cable duct was laid at
Trench excavation
and cooling mains installation along
Installation of PVC
and G.I cable ducts was ongoing at
+5.17 mPD and wall
below were completed on 12 Jan 2012 for the WSD Salt Water Pumping Station.
D610 pipe pile wall
construction at landside cofferdam of salt water intake culvert was in
progress.
Setting-up of pile
load test at WSD Seaside Cofferdam was completed on 17 January 2012.
Formwork removal for
remaining pile caps at Portion 1B for the New Ferry Pier was commenced on 20
January 2012.
Tower Crane
operation commenced on 16 January 2012 for the Ferry Pier construction.
Steel Mould
installation at Portion 1A and Welding
Steel for supporting Portion 2C of the New Ferry Pier was in progress.
Backfilling on the HDPE pipelines of Portion 2 between CH0 to CH150 was in
progress.
Steel deck support
for cooling main was completed on 30 December 2011 and cooling mains installation
was ongoing across WCR1.
Construction of
Temporary Decking Platform A for Vehicle Access of the New Wan Chai Ferry
Pier was completed on 30 December 2011.
Quad shore &
steel beam support installation commenced on 19 Jan 2012 in Box Culvert O;
Preparation works
for WCR2 diversion |
300mm thick topping
slab at southern portion andhelipad slab construction
Lighting
installation at Helipad
Removal of temporary
frame at existing movable ramp
Plate Support of
Safety Net at northern portion
ABWFs and E&M
works of Passenger Terminal Building (PTB)
Installation of
glass cladding at G/F and 1/F at PTB.
Roof waterproofing
test at PTB.
Concreting wall and
top slab of Bladder Tank
Concreting of Noise
Barrier NB2 upstand
Drilling holes for
anchor reinforcement fixing at Noise Barrier NB1
Erecting formwork of
Noise Barrier NB1
Mass concrete at
seawall coping Bay1 and Bay2.
Breaking up the
cover walkway footing of EVA at
E&M of P7, P8
& P9
+1.35mPD steel
platform of P7 was completed on 20 February 2012, P8 & P9 installation
Wet Well penstock
installation at P7, P8 & P9.
23 steel pipes of
WSD pipe jacking drive in TBM
Annulus chemical
grout surrounding the steel sleeve
Excavation and
lateral support of the Jacking pit at ex-pet garden for the cooling mains
construction across HHR.
Approximate 60m
cooling water pipe was laid at Harbour Centre,
Approximate 15m
cable duct was laid at
Casting of 800mm
thick slab @ +8.36mPD for the WSD Salt Water Pumping Station.
Excavation of 610
pipe pile wall landside cofferdam of salt water intake culvert
Pile load test at
WSD Seaside Cofferdam
Fabrication of
temporary water tank at Portion 1A was in progress. Installation of temporary
water tank for construction of pile caps & beams at Portion 1A
Formwork and
temporary working platform removal for pile caps at Portion 1B at New Wan
Chai Ferry Pier
Welding of steel
supports at Portion 2C of the New Ferry Pier
Backfilling on the
HDPE pipelines and diffuser section between CH0 & CH150
Cooling mains
installation across WCR1
Quad shore &
steel beam support installation at Box Culvert O
Installation of
Temporary Decking Platform "C" |
Table IV   Principle Work
Activities for Contract no. HY/2009/15
December 2011 |
January 2012 |
February 2012 |
Seawall block
construction and reclamation work at TS4;
Night time
protection works at CHT; and
Precautionary works
at Abutment A |
Seawall block
construction and reclamation work at TS4;
Night time
protection works at CHT; and
Precautionary works
at Abutment A |
Reclamation works at
TS4/ME4
Diaphragm wall
construction preparation works at TS4
Marine SI at TS2
ELS works at TS1 and
TPCWAE
Night time
protection works at CHT Cut off wall preparation works at |
Table V    Principle Work
Activities for Contract no. HK/2010/06
December 2011 |
January 2012 |
February 2012 |
Installation of
bored pile casing;
Excavation of bored
piles; and
Concreting of bored
piles |
Installation of
bored pile casing
Excavation of bored
piles
Concreting of bored
piles
Coring works |
Construction of
Pre-cast Unit in
Excavation of bored
piles
Concreting of bored
piles
Coring works |
Table VI   Principle Work
Activities for Contract no. HY/2009/19
December 2011 |
January 2012 |
February 2012 |
N/A |
N/A |
Marine bored piling |
Noise Monitoring
Three limit level exceedances at M1a on 29 November, 6 December 2011and 10 January 2012
during restricted hour.
No Action Level exceedance was recorded.
Real-time Noise Monitoring
Air Quality Monitoring
CMA1b: from 4 January 2012 to 5 January
2012
       from 10 January 2012 to 11
January 2012
       from 20 January 2012 to 21
January 2012
       from 26 January 2012 to 27
January 2012
from 13 February 2012 to 16
February 2012
CMA3a: from 16 January 2012 to 17
January 2012
 /span>from 13 February 2012 to 14 February 2012
CMA5a: from 18 February 2012 to
20 February 2012
Water Quality Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-356/2009 and Further Environmental
permit nos. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the Environmental Monitoring and
Audit (EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.4 of EM&A Manual and  /span>Environmental
Monitoring and Audit Requirements /span> under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
during the period from 28th November 2011 to 27th February
2012.
Section 1     Introduction  details the scope and structure of the
report.
Section 2     Project Background  summarizes
background and scope of the project, site description, project organization and
contact details of key personnel during the reporting period.
Section 3     Monitoring Requirements  summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4     Monitoring Results  summarizes the
monitoring results obtained in the reporting period.
Section 5     Compliance Audit  summarizes the auditing of
monitoring results, all exceedances environmental parameters.
Section 6     Complaints, Notification of summons and
Prosecution  summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section 7     Cumulative Construction Impact due to the
Concurrent Projects  summarizes the relevant cumulative
construction impact due to the concurrent activities of the concurrent Projects.
Section 8     Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass and “Central-Wan Chai
Bypass and Island Eastern Corridor Link (hereafter called “the Project  are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
The
Project is located mainly in Wan Chai North,
2.2.2.
The
study area encompasses existing developments along the Wan Chai,
2.2.3.
The scope of the Project comprises:
 -
Land formation for key transport infrastructure and
facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for
connection to the Trunk Road and for through traffic from Central to Wan Chai and
Causeway Bay. The land formed for the above transport infrastructure will provide
opportunities for the development of an attractive waterfront promenade for the
enjoyment of the public
 -
Reprovisioning / protection of the existing
facilities and structures affected by the land formation works mentioned above
 -
Extension, modification, reprovisioning or
protection of existing storm water drainage outfalls, sewerage outfalls and
watermains affected by the revised land use and land formation works mentioned
above
 -
Upgrading of hinterland storm water drainage system
and sewerage system, which would be rendered insufficient by the land formation
works mentioned above
 -
Provision of the ground level roads, flyovers,
footbridges, necessary transport facilities and the associated utility services
 -
Construction of the new waterfront promenade,
landscape works and the associated utility services
 -
The Trunk Road (i.e. CWB) within the study area and
the associated slip roads for connection to the Trunk Road.
2.2.4.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project.
Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1   Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits (FEP) such that the impact monitoring stations are sub-divided
accordingly to facilitate the implementation of EM&A programme and to
streamline the EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The
details of individual contracts are summarized in Table2.2.
Table
2.2  Details of Individual Contracts
under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II  Central –Wanchai Bypass at |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central  Wan Chai Bypass  North
Point Reclamation |
DP3 |
17 March 2010 (Under applicationof surrender) |
HY/2009/15 |
Central-Wanchai Bypass  Tunnel ( |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB)  Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For
the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in
Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table 2.3  Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
|
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project
Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental
Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo  Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
|
9124 2471 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Operation
Manager |
Mr. Lau Yee Ching |
9466 3918 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 3008 |
|||
Construction
Manager |
Mr. KK Yuen Mr. Andy Yu |
9498 1213 96484896 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak
|
9103 2370 |
|||
Chun Wo  CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Mak Kam Wing |
3658 3044 |
|||
Quality & Environmental Manager |
Mr. C.P. Ho |
3658 3000 |
|||
Environmental Officer |
Ms. |
3658 3064 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2528 5651 |
Site Manager |
Mr. P J Fan |
3557 6368 |
2566 2192 |
||
|
|
Construction Manager |
Mr. C K Kwok |
3557 6393 |
2566 2192 |
|
|
Construction Manager (East) |
Gene Cheung |
3557 6395 |
2566 2192 |
|
|
Construction Manager (West) |
Tony Chiu |
9090 0606 |
|
|
|
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Lee Wai Man |
9481 6024 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental
Engineer |
Mr. Simon Wong |
9281 4346 |
|||
Environmental Manager / Environmental
Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
During
this reporting period, the principle work activities for Contract no.
HY/2009/11 are summarized in Table2.4.
Table
2.4   Principle Work Activities for Contract
no. HY/2009/11
December 2011 |
January 2012 |
February 2012 |
Reclamation works;
Geo-textile laying;
Slotted panel
fixing;
Drainage
Construction works;
Installation of berm
blocks;
Concreting the
slopes of Open Channel U;
Construction of
in-situ mass concrete cooping;
Construction of
granite facing stone; and
Construction of
Seawall Type 8 |
The major work
activities for Contract no. HY/2009/11 was confirmed substantial complete by
RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19 and the FEP-01/356/2009 was under application of surrender in this
reporting period. |
The major work
activities for Contract no. HY/2009/11 was confirmed substantial complete by
RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19 and the FEP-01/356/2009 was under application of surrender in this
reporting period. |
2.5.2.
During
this reporting period, the principle work activities for Contract no.
HK/2009/01 are summarized in Table 2.5.
Table 2.5   Principle Work
Activities for Contract no. HK/2009/01
December 2011 |
January 2012 |
February 2012 |
Dredging works
within HKCEC Water Channel from CH190 to CH260 for Type 1 & 2
Sediment was commences and substantially completed;
Removal of rock
armours from CH150 to CH180 at the North bank of HKCEC Water
Channel was
commenced and substantially completed;
A trial for Type 3
sediment disposal was carried out;
Installation of
sheet pile for cooling water intake at Dome Promenade between
CH120 and CH170;
Installation of
precast RC outfall at Zone B1-3;
Trench excavation
for the 4 nos. of cooling water discharge pipes at B1-3;
Reclamation of
HKCEC3W (up to CH130) within HKCEC Water Channel;
Installation of
cross -harbour water mains nos. B13, A14/B14 and A15/ B15;
Thrust block
construction for A9/B9 and A11/B11 was commenced;
Concrete coating at
flange joint of cross-harbour water mains nos. A7B7/A8B8,
A8B8/A9B9 and
A9B9/A10B10;
Rockfilling and rock
protection to cross-harbour watermains;
Installation of pipe
pile at TST (Land Portion) was commenced and substantially completed;
Grouting works at
TST seafront along the pipe piles
Dredging of Type 2
sediment from CH50 to CH250 for subsequent cross-harbour
watermains
installation off Tsim Sha Tsui;
Mainlaying works at
Zone B1-5B, B1-6, B2-2, B4-2, B4-5, A1-5A, A3-2A, HKCEC,Zone B1-6, B2-2 and B1-5B; Zone A1-5A1 and A3-5B;
Way In/Out, A2-3B
and A5-5;
Coring and Grouting
works for external wall of cooling pumping stations Nos. P4 & P5 at Zone B4-5;
Coring works for
external wall of cooling pumping station No P1 at Zone B4-2;
Heading No. H3,H4, H5, H7 and H13; was substantially completed.
GI duct laying works
at ZoneA4-3A and Zone A4-3B;
Trench excavation,
pipe laying works and chamber construction for a 1000 dia.
watermains (CHF) at |
Dredging works
within HKCEC Water Channel from CH190 to CH260 for Type 3 sediment was
commended.
Removal of rock
armours from CH160 to CH260 at the north bank of HKCEC Water Channel was
substantially completed.
Installation of
sheet pile for cooling water intake at Dome Promenade between CH120 and CH170
was in progress.
Reclamation of
HKCEC3W (up to CH130) within HKCEC Water Channel has been substantially
completed.
Installation of 4
nos. of submersible cooling water discharge pipes at B1-3 was substantially
completed.
Thrust block
construction for A9B9, A11B11, A12B12 and A13B13 were completed.
Concrete coating at
flange at joint of cross-harbour watermains nos. A10B10/A11B11, A11B11/A12B12
and A12B12/A12B13 were completed.
Rockfilling and rock
protection to cross-harbour watermains was currently in progress.
Grouting works at
TST seafront along the pipe pile wall was commenced.
Installation of pipe
pile at TST (Sea Protection) was substantially completed.
Dredging of Type 3
sediment at designated disposal site was carried out.
Mainlaying works at
Zone B1-5B, B1-6, B2-2, A3-2A, A3-5B and were in progress.
Cable ducting works
at Zone B5-2 was commenced.
Mainlaying works and
subsequent reinstatement in Zone B4-5 was completed.
Mainlaying works and
subsequent carriageway reinstatement in Zone A1-5A1, A4-3A,
A4-3B and HKCEC Way
In/Out had been completed.
Mainlaying works and
subsequent carriageway reinstatement in Zone A2-3B and A2-4A was completed.
Coring and grouting
works for external wall of cooling pumping station No. P1 at Zone B4-2 was
completed.
Pipe laying works at
Zone B4-2 was completed and GI ducting works was in progress.
Jacking pit
establishment for pipe laying works by heading method at Zone A1-5A1 has been
completed.
Mainlaying and
chamber construction works at the traffic island neat junction of
Trench excavation,
pipe laying works and chamber construction for a 1000 dis. Warermains (CHF)
at
Trench excavation
and pipe laying works for a 1000 dia. Watermains (CHE) at |
Marine Works
Dredging works
within HKCEC water Channel form CH190 to Ch260 for Type 2 sediment and Type 3 sediment.
Installation of sheet
pile for cooling water intake at Dome Promenade between CH120 and CH170
Reclamation of
HKCEC3W (up to CH140) within HKCEC Water Channel
Seawall
reinstatement and retaining wall construction at Wan Chai Lanfill in Zone
B1-3 Cross-harbour Watermains Installation
Rockfilling and rock
protection to cross-harbour watermains
Grouting works at
TST seafront along the pipe pile wall
Installation of pipe
pile at TST seafront for pre-splitting seawall blocks
Trench excavation
and installation of shoring system along the pipe pile wall at TST seafront
Dredging of Type 3
sediment from CH50 to CH250 for subsequent cross-habour watermains installation
off TST
Dredging works
underneath Avenue of Stars carried by telescopic excavator
Dredging works in
confined water by 9 in 1 barge
1.1.3 Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land)
Mainlaying works at
Zone B1-3, B1-5, B1-6, B2-2, B4-2, B4-4, B5-2, A1-1, A2-3C, A3-4B, A3-5B and
A4-2A, B4-4, A4-2A, A1-1,
A1-4A, A2-3C and A3-4B
Mainlaying works and
subsequent carriageway reinstatement in Zone A5-5 and A3-2A
Cable ducting works
along
Heading No. H5, H7, H8 and H13 (mainlaying
woks by trenchless method)
Mainlaying and
chamber construction works at the traffic island near junction of Trench excavation, pipe laying works and chamber construction
for a 1000 dia. watermains (CHF and CHE) at |
2.5.3.
During
this reporting period, the principle work activities for Contract no.
HK/2009/02 are summarized in Table 2.6.
Table
2.6   Principle Work Activities for
Contract no. HK/2009/02
December 2011 |
January 2012 |
February 2012 |
300mm thick topping
slab together with the make up slab below at northern portion commenced on 30 Nov
2011;
Concreting at Roof
Plinth, lift shaft up to +14.15mPD and Fire Service Pump room up to +14.15mPD of
Passenger Terminal Building were completed;
E&M and ABWF of
ELS of Noise Barrier
2 commenced on 29 Nov 2011 and nearly completed.
Casting of
pedestrian pavement above seawall coping Bay 4 to Bay 8 was completed on 13 December 2011;
Casting of the bus
shelter footing at
Precast slab
installation at the existing movable ramp was in progress;
Saw cutting of
existing slabs for the construction NB1 footing was completed;
E&M of P7, P8
& P9
Approximate 50m
cooling water pipe was laid at Harbour Centre,
Jacking pit at
ex-pet garden for the heading construction of cooling mains across
Convention Avenue
commenced;
Approximate 50m
cable duct was laid at
Construction of wash
out chamber at Centre were
completed;
Trench excavation
and cooling mains installation along
Installation of PVC
and G.I cable ducts was ongoing at
Installation of
submarine outfall pipe was completed;
Dredging for
submarine outfall pipe was ongoing;
Concreting the Base
Slab of Wan Shing Street at Bay 24 was completed;
Concreting the wall
shaft and roof slab completed of Bay 24 were
completed;
Bay 21 to Bay 24 of
Wan Shing Street were handover to HEC;
Slab at +3.10mPD and
+3.77 mPD and wall below were completed for the WSD Salt Water Pumping
Station;
Excavation and
lateral support for DSD receiving pits were completed;
D610 pipe pile wall
construction at landside cofferdam of salt water intake culvert;
12 out of 12 nos of
pre-bored H-pile for box culverts N1 was casted as of 21November 2011;
Temporary working
platform was completed and pile cap construction was in progress at Portion
1B for the New Ferry Pier |
300mm thick topping
slab at northern portion was substantially completed on 20 January 2012.
Concreting of
structural slab at existing movable ramp was completed on 18 January 2012.
ABWFs and E&M
works of
Installation of glass
wall bearing at G/F and 1/F commenced on 22 December 2012 and completed on 5
January 2012.
ELS of Noise Barrier
NB2 was completed on 15 January 2012.
Blinding of Noise
Barrier NB2 footing was completed on 29 December 2012.
Steel fixing of
Noise Barrier NB2 was in progress.
Pedestrian diversion
above seawall coping Bay 4 to Bay 8 was implemented on 6 January 2011.
Bladder Tank steel
fixing and formwork erection are in progress.
E&M of P7, P8
& P9 were in progress.
Sheet piling works
of the Jacking pit at ex-pet garden commenced on 19 December 2011for the
heading construction of cooling mains across
Approximate 30m
cooling water pipe was laid at Harbour Centre,
Approximate 10m
cable duct was laid at
Trench excavation
and cooling mains installation along
Installation of PVC
and G.I cable ducts was ongoing at
+5.17 mPD and wall
below were completed on 12 Jan 2012 for the WSD Salt Water Pumping Station.
D610 pipe pile wall
construction at landside cofferdam of salt water intake culvert was in
progress.
Setting-up of pile
load test at WSD Seaside Cofferdam was completed on 17 January 2012.
Formwork removal for
remaining pile caps at Portion 1B for the New Ferry Pier was commenced on 20
January 2012.
Tower Crane
operation commenced on 16 January 2012 for the Ferry Pier construction.
Steel Mould
installation at Portion 1A and Welding
Steel for supporting Portion 2C of the New Ferry Pier was in progress.
Backfilling on the HDPE pipelines of Portion 2 between CH0 to CH150 was in
progress.
Steel deck support
for cooling main was completed on 30 December 2011 and cooling mains
installation was ongoing across WCR1.
Construction of
Temporary Decking Platform A for Vehicle Access of the New Wan Chai Ferry
Pier was completed on 30 December 2011.
Quad shore &
steel beam support installation commenced on 19 Jan 2012 in Box Culvert O;
Preparation works
for WCR2 diversion |
300mm thick topping
slab at southern portion andhelipad slab construction
Lighting
installation at Helipad
Removal of temporary
frame at existing movable ramp
Plate Support of
Safety Net at northern portion
ABWFs and E&M
works of Passenger Terminal Building (PTB)
Installation of
glass cladding at G/F and 1/F at PTB.
Roof waterproofing
test at PTB.
Concreting wall and
top slab of Bladder Tank
Concreting of Noise
Barrier NB2 upstand
Drilling holes for
anchor reinforcement fixing at Noise Barrier NB1
Erecting formwork of
Noise Barrier NB1
Mass concrete at
seawall coping Bay1 and Bay2.
Breaking up the
cover walkway footing of EVA at
E&M of P7, P8
& P9
+1.35mPD steel
platform of P7 was completed on 20 February 2012, P8 & P9 installation
Wet Well penstock
installation at P7, P8 & P9.
23 steel pipes of
WSD pipe jacking drive in TBM
Annulus chemical
grout surrounding the steel sleeve
Excavation and
lateral support of the Jacking pit at ex-pet garden for the cooling mains
construction across HHR.
Approximate 60m
cooling water pipe was laid at Harbour Centre,
Approximate 15m
cable duct was laid at
Casting of 800mm
thick slab @ +8.36mPD for the WSD Salt Water Pumping Station.
Excavation of 610
pipe pile wall landside cofferdam of salt water intake culvert
Pile load test at
WSD Seaside Cofferdam
Fabrication of
temporary water tank at Portion 1A was in progress. Installation of temporary
water tank for construction of pile caps & beams at Portion 1A
Formwork and
temporary working platform removal for pile caps at Portion 1B at New Wan
Chai Ferry Pier
Welding of steel
supports at Portion 2C of the New Ferry Pier
Backfilling on the
HDPE pipelines and diffuser section between CH0 & CH150
Cooling mains
installation across WCR1
Quad shore &
steel beam support installation at Box Culvert O
Installation of
Temporary Decking Platform "C" |
2.5.4.
Major construction activities for Contract no.
HY/2009/15 was commenced on 10 November 2010. During this reporting period, the
principle work activities for Contract no. HY/2009/15 are summarized as below:
Table
2.7   Principle Work Activities for Contract no. HY/2009/15
December 2011 |
January 2012 |
February 2012 |
Seawall block
construction and reclamation work at TS4;
Night time
protection works at CHT; and
Precautionary works
at Abutment A |
Seawall block
construction and reclamation work at TS4;
Night time
protection works at CHT; and
Precautionary works
at Abutment A |
Reclamation works at
TS4/ME4
Diaphragm wall
construction preparation works at TS4
Marine SI at TS2
ELS works at TS1 and
TPCWAE
Night time
protection works at CHT Cut off wall preparation works at |
2.5.5.
Contract
no. HK/2010/06 was commenced on 22 March 2011. During this reporting period,
the principle work activities for Contract no. HK/2010/06 are summarized as
below:
Table
2.8   Principle Work Activities for Contract no. HK/2010/06
December 2011 |
January 2012 |
February 2012 |
Installation of
bored pile casing;
Excavation of bored
piles; and
Concreting of bored
piles |
Installation of
bored pile casing
Excavation of bored
piles
Concreting of bored
piles
Coring works |
Construction of
Pre-cast Unit in
Excavation of bored
piles
Concreting of bored
piles
Coring works |
Table 2.9  Principle Work Activities
for Contract no. HY/2009/19
December 2011 |
January 2012 |
February 2012 |
N/A |
N/A |
Marine bored piling |
2.5.7.
Implementation
status of the recommended mitigation measures during this reporting period is
presented in
Appendix 2.1.
Noise Monitoring Stations
3.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
3.1 and
Figure 3.1. Appendix 3.1 shows
the established Action/Limit Levels for the monitoring works.
Table 3.1  Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Real
time Noise Monitoring Stations
3.1.1.
The real-noise monitoring stations for the Project are
listed and shown in Table 3.2 and
Figure 3.1..
Appendix 3.1 shows the established Action/Limit Levels for the
monitoring works.
Table 3.2  Real Time Noise Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring
Parameters, Frequency and Duration
3.1.2.
The construction
noise level shall be measured in terms of the A-weighted equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700
and 1900 hours on normal weekdays. For all other time periods, Leq (5
minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.3.
Noise monitoring
shall be carried out at all the designated monitoring stations. The monitoring
frequency shall depend on the scale of the construction activities. The
following is an initial guide
on the regular monitoring frequency for each station on a weekly basis when
noise generating activities are underway:
 -
one
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.4.
If construction works are extended to
include works during the hours of 1900  0700 as well as public holidays and
Sundays, additional weekly impact monitoring shall be carried out during
respective restricted hours periods. Applicable permits under NCO shall be
obtained by the Contractor.
3.1.5.
Real
time noise shall be carried out at the designated monitoring stations. The
following is an initial guide on the regular monitoring frequency for each
station on a 24 hours daily basis when noise generating activities are
underway:
 -
One
set of measurements between 0700 and 1900 hours on normal weekdays.
 -
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
 -
One
set of measurements between 2300 and 0700 hours on next day on everyday.
3.1.6.
Noise
baseline level review was commenced in this reporting period. Detailed review
report showed in
Appendix 3.2.
3.1.7.
Real
time noise baseline level review at night time period (2300 to 0700) was
commenced in this reporting period. Detailed review report showed in
Appendix 3.3.
Monitoring Equipment
3.1.8.
As referred to in the Technical Memorandum  issued
under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
3.1.9.
Noise measurements shall not be made in fog, rain,
wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s.
The wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
Air Quality Monitoring
Stations
3.2.1.
The
air monitoring stations for the Project are listed and shown in Table
3.3 and
Figure 3.1.
Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table 3.3  Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to |
Wan Chai |
CMA6a |
WDII PRE Site Office * |
Wan Chai |
* Remarks: As per the ENPC meeting in January 2011,
the monitoring stations CMA3a - Future CWB site office at Wanchai Waterfront
Promenade and CMA6a - Future AECOM site office at Work Area were renamed as
remark.
Air Monitoring Parameters,
Frequency and Duration
3.2.2.
One-hour
and 24-hour TSP levels should be measured to indicate the impacts of
construction dust on air quality. The 24-hour TSP levels shall be measured by
following the standard high volume sampling method as set out in the Title 40
of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.
3.2.3.
All
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and any other local atmospheric factors affecting or
affected by site conditions, etc., shall be recorded down in detail.
3.2.4.
For
regular impact monitoring, the sampling frequency of at least once in every
six-days, shall be strictly observed at all the monitoring stations for 24-hour
TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least
three times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5
High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
 -
0.6
- 1.7 m3 per minute adjustable flow range;
 -
equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
 -
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
 -
capable
of providing a minimum exposed area of 406 cm2;
 -
flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
 -
equipped
with a shelter to protect the filter and sampler;
 -
incorporated
with an electronic mass flow rate controller or other equivalent devices;
 -
equipped
with a flow recorder for continuous monitoring;
 -
provided
with a peaked roof inlet;
 -
incorporated
with a manometer;
 -
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
 -
easily
changeable filter; and
 -
capable
of operating continuously for a 24-hour period.
3.2.6
Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
Laboratory Measurement /
Analysis
3.2.7
A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
3.2.8
An alternative non-HOKLAS accredited laboratory was set-up for carrying out the laboratory analysis,
the laboratory equipment was
approved by the ER on 8 February 2011 and the
measurement procedures were
witnessed by the IEC. Any measurement performed by the laboratory was be demonstrated to the satisfaction of
the ER and IEC. IEC shall regularly audit to the measurement performed by the
laboratory to ensure the accuracy of measurement results.
3.2.9
Filter paper of size 8" x 10" shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
3.2.10
After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
3.2.11
All the collected samples shall be kept in a good
condition for 6 months before disposal.
impact monitoring for
odour patrol
3.2.12 Odour patrols
along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai Public
Cargo Working Area when there is temporary reclamation in Causeway Bay Typhoon
Shelter and/or in the ex-Wan Chai
Public Cargo Working Area, or when there is dredging of the odorous sediment
and slime at the south-western corner of the Causeway Bay Typhoon Shelter.
Odour patrols will be carried out at bi-weekly intervals during July, August and
September by a qualified person of the ET who shall:
 -
be
at least 16 years of age;
 -
be
free from any respiratory illnesses; and
 -
not
be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30
min
 -
before
and during odour patrol
3.2.13 Odour patrol shall be conducted by
independent trained personnel / competent persons patrolling and sniffing
around the shore as shown in
Figure 3.1 to detect any odour at the
concerned hours (afternoon is preferred for higher daily temperature).
3.2.14 The qualified person will use the nose
(olfactory sensor) to sniff odours at different locations. The main odour
emission sources and the areas to be affected by the odour nuisance will be identified.
3.2.15 The perceived odour intensity is to be
divided into 5 levels which are ranked in the descending order as follows:
 -
0 -
Not detected. No odour perceived or an odour so weak that it cannot be easily
characterized or described;
 -
1 -
Slight Identifiable odour, and slight chance to have odour nuisance;
 -
2 -
Moderate Identifiable odour, and moderate chance to have odour nuisance;
 -
3 -
Strong Identifiable, likely to have odour nuisance;
 -
4 -
Extreme Severe odour, and unacceptable odour level.
3.2.16 The findings including odour intensity,
odour nature and possible odour sources, and also the local wind speed and
direction at each location will be recorded. In addition, some relevant
meteorological and tidal data such as daily average temperature, and daily
average humidity, on that surveyed day will be obtained from the Hong Kong
Observatory Station for reference. The Action and Limit levels for odour patrol
are shown in
Appendix 3.1.
3.3.1.
The
EIA Report has identified that the key water quality impact would be associated
with the dredging works during the construction phase. Marine water quality monitoring for dissolved
oxygen (DO), suspended solid (SS) and turbidity is therefore recommended to be
carried out at selected WSD flushing water intakes. The impact monitoring should be carried out
during the proposed dredging works to ensure the compliance with the water
quality standards.
3.3.2.
The updated EM&A Manual for EP-356/2009 (Version
in March 2011) is approval by EPD on 29 April 2011. As such, the Action Level
and Limit Level for the wet season (April  September) will be effected and
applied to the water quality monitoring data from 30 April 2011.
Water Quality Monitoring Stations
3.3.3.
It
is proposed to monitor the water quality at 9 WSD salt water intakes and 14
cooling water intakes along the seafront of the
Table
3.4   Marine Water Quality
Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
|
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
RW1 |
Wan Chai (Reprovision) |
836188.8 |