Contract
No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and
Testing Work (Stage 2) Environmental
Permit no. EP-356/2009, Further
Evironmental permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009,
fep-05/356/2009, Fep-06/356/2009 and FEP-07/356/2009 Quarterly Environmental Monitoring
and Audit Report
- September 2013 to November 2013 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
18 December
2013 |
2.2 Scope of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
2.5 Principal Work and Activities
4.2. Real Time Noise
Monitoring Results
5.2. Real-time Noise Monitoring
5.6. Review of the Reasons for and the Implications of
Non-compliance
5.7. Summary of action taken in the event of and follow-up
on non-compliance
6. Complaints,
Notification of Summons and Prosecution
7. Cumulative
Construction Impact due to the Concurrent Projects
lIST
OF TABLES
Table I Principal Work
Activities for Contract no. HK/2009/01
Table II Principal Work
Activities for Contract no. HK/2009/02
Table III Principal Work
Activities for Contract no. HY/2009/15
Table IV Principal Work Activities for Contract no. HK/2010/06
Table V Principal Work
Activities for Contract no. HY/2009/19
Table VI Principal Work Activities for Contract no. HK/2012/08
Table 2.1 Schedule 2 Designated
Projects under this Project
Table 2.2 Details of Individual
Contracts under the Project
Table 2.3 Contact Details of
Key Personnel
Table 2.4 Principal Work Activities for Contract no. HK/2009/01
Table 2.5 Principal Work Activities for Contract no. HK/2009/02
Table 2.6 Principal Work
Activities for Contract no. HY/2009/15
Table 2.7 Principal Work
Activities for Contract no. HK/2010/06
Table 2.8 Principal Work
Activities for Contract no. HY/2009/19
Table 2.9I Principal Work Activities for Contract no. HK/2012/08
Table 3.1 Noise Monitoring
Stations
Table 3.2 Real Time Noise
Monitoring Station
Table 3.3 Air Monitoring
Stations
Table 3.4 Marine Water Quality
Stations for Water Quality Monitoring
Table 3.5 Marine Water Quality
Monitoring Frequency and Parameters
Table
3.6 Marine Water Quality Stations for Enhanced Water
Quality Monitoring
Table
3.7 Marine Water Quality Stations for Additional DO
Monitoring
Table 4.1 Noise Monitoring Station for Contract nos. HK/2009/01
and HK/2009/02 and HK/2010/06
Table 4.2 Noise Monitoring
Station for Contract nos. HY/2009/15
Table 4.3 Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.4 Real Time Noise
Monitoring Station for Contract no. HY/2009/11 and HY/2009/19
Table 4.6 Air Monitoring Stations for Contract no. HK/2009/01
Table 4.7 Air Monitoring Station for Contract no. HK/2009/02
Table 4.8 Air Monitoring Station
for Contract no. HY/2009/15
Table 4.9 Air Monitoring Stations for Contract no. HY/2009/19
Table 4.10 Water Monitoring
Stations for Contract no. HY/2009/11
Table 4.11 Water Monitoring Stations for Contract no. HK/2009/01
Table 4.12 Water Monitoring Stations for Contract no. HK/2009/02
Table 4.13 Water Monitoring Stations for Contract no. HK/2010/06
Table 4.15 Water Monitoring Stations for
Contract no. HY/2009/19
Table 4.15a Summary of
Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting period
Table 4.16 Summary of Water Quality Monitoring Exceedances in Reporting
period
Table 4.17 Details of Waste Disposal for Contract no. HK/2009/02
Table 4.18 Details of Waste Disposal for Contract no. HK/2009/01
Table 4.19 Details of Waste Disposal for Contract no. HK/2009/02
Table 4.20 Details of Waste Disposal for Contract no. HY/2009/15
Table 4.21 Details of Waste Disposal for Contract no. HK/2010/06
Table 4.22 Details
of Waste Disposal for Contract no. HY/2009/19
Table 5.1 Summary of Water
Quality Monitoring Exceedances in Reporting period
Table 5.1a Summary of Enhanced
Dissolved Oxygen Monitoring Exceedances in Reporting period
Table 6.1 Cumulative Statistics
on Complaints
Table 6.2 Cumulative Statistics
on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 3.1 Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix
2.1 Environmental Mitigation
Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix
4.1 Noise Monitoring
Graphical Presentations
Appendix
4.2 Air Quality Monitoring
Graphical Presentations
Appendix
4.3 Water Quality Monitoring
Graphical Presentations
Appenidx 4.3a Additional Dissolved Oxygen
Monitoring Results
Appendix 4.4 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 7.1 Construction Programme of
Individual Contracts
Construction Activities for the
Reported Period
Table I Principal Work Activities for Contract
no. HK/2009/01
September 2013 |
October 2013 |
November 2013 |
Marine Works (at Wan Chai) Rockfilling
at Area 3 (East of Bottom
slab of Bay 8. Preparation work for blinding layer at Bay 9. Fabrication
work for steel bridge on the top of temporary open channel along Pre-drilling
for D-walls at Area 8 (interface wall, bulkhead). Installation of sleeve pipe
for predrilling work in order to remove the G75 rock before site
investigation. Ground
treatment work and guide wall construction. Formation for soil platform.
Plate load test. Cross-Harbour Watermains Installation (CHA
& CHB) and Marine Works (at TST) The stage
2 & 3 connection. The stage 4 capping works for XHWM. XHWM, Cooling Watermains, Salt Watermains and
Sewer (On Land) Design of
the additional anode between the new pipe and existing pipeline. Reinstatement
works at West Foyer of HKCEC. Planter reinstatement, kerbworks, hard paving.
All reinstatement works. Cooling
main works in Zone C1-2. Cooling main works along Salt
watermain laying works along west of Convention Avenue, J/O Convention Avenue
& Fenwick Per Street, Harbour Road in Zone A3-5C, A3-1, A3-5B, A2-4A,
A5-5 and A5-2. Salt watermain laying works along west of Temporary
ducting and cabling works at junction between Tunnel Works Installation
of pre-bored H-pile in CWB Stage 2 Atrium Link (from CH120 to CH220). 45 nos.
pre-bored H-piles had been excavated. 32 nos. pre-bored H-piles were grouted
i.e. 22 nos. drilled and 26 nos. grouted. Construction
of the Common D-wall. Filling of
the existing open water channel from CH100 to CH206. Demolition
of the Promenade Deck. ELS work
at bottom-up area. Fabrication of steel strutting members. Installation of
ELS. |
Marine
Works (at Wan Chai) Rock filling
up to +4.2 mPD for D-wall construction. Bottom
slab of Bay 8. Preparation work for blinding layer at Bay 9. Water leakage
was found and re-grouting. Fabrication
work for steel bridge on the top of temporary open channel along Pre-drilling
for D-walls at Area 8 (interface wall, bulkhead). Ground
treatment work and guide wall construction. XHWM,
Cooling Watermains, Salt Watermains and Sewer (On Land) Design of
the additional anode between the new pipe and existing pipeline. Reinstatement
works at HKCEC north & northwest. Reinstatement works at West Foyer of
HKCEC. Planter reinstatement, kerbworks, hard paving and all other minor
reinstatement works. Cooling
main works in Zone C1-2. Cooling main works along Salt
watermain laying works along west of Convention Avenue, J/O Convention Avenue
& Fenwick Per Street, Harbour Road in Zone A3-5C, A3-1, A3-5B, A2-4A,
A5-5 and A5-2. Salt watermain laying works along west of Relocation
works of fire hydrant in Zone X2-1. Temporary
ducting and cabling works at junction between Tunnel
Works Installation
of pre-bored H-pile in CWB Stage 2 Atrium Link (from CH120 to CH220). Construction
of the Common D-wall. Filling of
the existing open water channel from CH100 to CH206. Demolition
of the Promenade Deck. Installation of sheet pile for demolition of P5 Pump
house. ELS work
at bottom-up area. Fabrication of steel strutting members. Installation of
ELS. |
Marine
Works (at Wan Chai) Further
rock filling from HATS at East side in order to extend the work area. Concreting
at base slab of bay 8 and bay 9. Wall and roof slab construction work and he
box culvert. Fabrication
work for steel bridge on the top of temporary open channel along First
panel at temporary bulk head wall and C1/C2 interface wall Installation
of end plates to block the existing intakes P7 & P9. Outfall
construction for discharge pipes at Cooling
Watermains, Salt Watermains and Sewer (On Land) Design of
the additional anode between the new pipe and existing pipeline. Reinstatement
works at HKCEC north & northwest. Cooling
main laying works along Salt
watermain laying works along west of Convention Avenue, J/O Convention Avenue
& Fenwick Per Street, Harbour Road in Zone A3-5C, A3-1, A3-5B, A2-4A,
A5-5 and A5-2. Salt watermain laying works along west of Tunnel
Works Installation
of pre-bored H-pile in CWB Stage 2 Atrium Link (from CH120 to CH220). Installation
of pre-bored H-pile in CWB Stage 3. Construction
of the Common D-wall. Filling of
the existing open water channel from CH100 to CH206. Further filling to P7
& P9. Demolition
of the Promenade Deck. Installation of sheet pile for demolition of P5 Pump
house and the works for tie-back.
Installation of ELS at first layer for Stage
1. |
Table II Principal Work Activities for Contract no.
HK/2009/02
September 2013 |
October 2013 |
November 2013 |
Modification of existing covered walkway along The outstanding VSD parts for P7 Cooling Water Pumping Station reinstalled
. The 60 days for T&C period of P7 cooling water system. The T&C
period of P9. The temporary EVA construction for P7, P8 and P9 Cooling Water Pumping
Stations. Rectification works for P8 discharge mains near Gate No.1 60-Day T&C for P9 Cooling Water Pumping Station. Installation of Aeration and Chlorination Pipes at Temporary discharge pipe near CHS Trench excavation and ELS installation for the Y-section connecting
with the existing DN600 watermains at Additional horizontal gate valve chamber under VO No.114 located at
CHS8A230m. The remaining ABWF works and boundary wall in WSD Salt Water Pumping
Station, including maintenance platform and external finishes. The base slab, wall and top slab at Bay 5. Blinding layer for The access shafts of inspection manholes IM-01 and IM-02 at Bay 5. Construction of stoplog chamber extension SLO-01, SLO-02 and SLO-03 at
Bay 6. The stoplog installation. Formwork erection and rebar fixing for the 6nos. Temporary Covered
Walkway in the vicinity of Ferry Pier.
Interface coring and shear pin installation for the Eastern Bulkhead
Wall. The road modification works along Pavement works at Trimming of lifted-in sheetpile in front of SPCA’s Guard Room. Breaking up the existing carriageway next to SPCA’s Main Vehicular
Access. 90.7% of seawall blocks installation at WCR4/TWCR4 (844nos. out of
936nos.). 95% of geotextile at WCR4/TWCR4 area |
Modification of existing covered walkway along 60-Day Trial Operation for P7 Cooling Water Pumping Station. Fire Certificate for all P7, P8 and P9 Cooling Water Pumping Stations. Leakage rectification works for P8 discharge mains near Gate No.1. The DN150 washout pipe testing under VO No.114 located at CHS8A230m.
All necessary fittings and ready for gate valve installation by WSD. Pressure test to Y-Section for connection with the existing DN600 pipe
at The remaining ABWF works and boundary wall in WSD Salt Water Pumping
Station, including maintenance platform and external finishes. Bulkhead Removal at Bay 5 and Bay 6. The guiderail installation at stoplog chambers at Bay 6. The remedial works at Bay 3 and Bay 6. Revised certified ELS design for modifying the existing ELS for the
construction of Manhole No. FRP-N-MH2. The 6nos. Temporary Covered Walkway in the vicinity of Ferry Pier . Installation of base plates for seatings at Observation Deck Level of
Ferry Pier. Remedial works for the Eastern Bulkhead Wall. The road modification works along Pavement works at Backfilling works at Sorted public fill at WCR4/TWCR4. Seawall blocks installation at WCR4/TWCR4. Geotextile at WCR4/TWCR4 area.. |
Modification of existing covered walkway along Modification of road junction between Mainline of P8 discharge mains was tested. The leakage portion near
Gate No.1 had been fixed. The 60-day trial operation for P7 Cooling Water Pumping Station. Rectification works of the special movement joint for P8 discharge
main at CHBH152m. Defected special
movement joint was delivered off site for repairing works. Backfilling between CHAI 80 and CHAI 160, and CHAG Installation of 3 standpipes and the Water Tightness Test of Salt
Water Intake Culvert. For DN800 pipe, horizontal gate valve installation. Beforehead, epoxy
coating and flange adaptor installation. The remaining ABWF works and boundary wall in WSD Salt Water Pumping
Station, including maintenance platform and external finishes. Stoplog installation at Bay 6 of Box Culvert N1. The remedial works at Bay 6 of Box Culvert N1. Modifying the existing ELS for the construction of Manhole No.
FRP-N-MH2. DSD had accepted the Box Culvert N1 Bay 1 to Bay 6. Another site inspection for stoplog removal
trial was conducted with DSD. The Wall of FRP-N-MH2 construction and beforehead, the Water infilling to Box Culvert N1 for subsequent waternightness test.
Remedial works to stop leakage at Backfilling for Remaining connection between FRP-N-MH2 and SLO-03. Excavation to the formation level for the Temporary Covered Walkway
footing (GL5) in the vicinity of Ferry Pier.
Sand replacement test. Re-grouting works for the Eastern Bulkhead Wall. Proof drilling for re-grouting works for the Eastern Bulkhead Wall. Pavement works at All road markings and traffic sign installation. Implementation of HHR Flyover Diversion (Stage 1). WCR4/TWCR4 Reclamation: Public fill at WCR4/TWCR4. Seawall blocks installation at WCR4/TWCR4. Geotextile at WCR4/TWCR4 area. |
Table III
Principal Work Activities for
Contract no. HY/2009/15
September 2013 |
October 2013 |
November 2013 |
Construction of EVA |
Construction of EVA |
Construction of EVA Maintenance dredging |
Table IV Principal
Work Activities for Contract no. HK/2010/06
September 2013 |
October 2013 |
November 2013 |
Sheet
piling works |
Sheet
piling works |
Sheet
piling works |
Table V Principal Work Activities for Contract no.
HY/2009/19
September 2013 |
October 2013 |
November 2013 |
D-wall and Barrette Construction Construction works for Box Culvert T1 Backfill works for Box Culvert U1 Removal of marine platform Construction of pile cap, pier & cross head (Marine) Installation of dewatering well Laying of 1500f pipe Launching of segments Extraction of temporary pile from marine section Construction of bridge truss TA1 |
D-wall and Barrette Construction Removal of strut at ELS Construction works for Box Culvert T1 Removal of marine platform Construction of pile cap, pier & cross head (Marine) ELS and Cut & Cover Tunnel Installation of dewatering well Laying of 1500f pipe Launching of segments Extraction of temporary pile from marine section Construction of bridge truss TA1 Demolition of parapet at IEC link Construction of King Post at ELS |
D-wall and Barrette Construction Removal of strut at ELS will commence Construction works for Box Culvert T1 Removal of marine platform Construction of pile cap, pier & cross head (Marine) ELS, EVB and Cut & Cover Tunnel Installation of dewatering well Laying of 1500f pipe Launching of segments Extraction of temporary pile from marine section Construction of bridge truss TA1 Demolition of parapet at IEC link Construction of King Post at ELS |
Table VI Principal
Work Activities for Contract no. HK/2012/08
September 2013 |
October 2013 |
November 2013 |
Site preparation works Site survey ELS for box culvert La at Dredging Demolition of the existing |
Site preparation works Site survey ELS for box culvert La at Dredging Preparation works for abandoning watermains at |
Site preparation works Site survey ELS for box culvert La at Dredging Preparation works for abandoning watermains at Seawall rock mound formation |
Noise Monitoring
M2b: From 3 September 2013 to 6 September 2013
M6: From 3 September 2013 to 6 September 2013
Real-time Noise Monitoring
Air Quality Monitoring
CMA3a: from 16 October 2013 to 17 October 2013
CMA5a: from 14 November 2013 to 15 November 2013.
Water Quality Monitoring
xxxiii.
Total 17 DO exceedances, 45 turbidity exceedances
and 15 SS exceedances were recorded during mid-flood while 21 DO exceedance, 29
turbidity exceedances and 8 SS exceedances were recorded during mid-ebb in the
reporting period. All the exceedances were concluded as non-project-related. The
details of the recorded exceedances can be referred to the Section 5.4.
Complaints, Notifications of
Summons and Successful Prosecutions
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-356/2009 and Further Environmental
permit nos. FEP-02/356/2009,
FEP-03/356/2009,
FEP-04/356/2009, FEP-05/356/2009, FEP-06/356/2009 and FEP-07/356/2009 to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.4 of EM&A Manual and “Environmental
Monitoring and Audit Requirements” under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
during the period from September 2013 to November 2013.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements – summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results – summarizes the monitoring results
obtained in the reporting period.
Section 5 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
The
Project is located mainly in Wan Chai North,
2.2.2.
The
study area encompasses existing developments along the Wan Chai,
2.2.3.
The scope of the Project comprises:
·
Land formation for key transport infrastructure and
facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for
connection to the Trunk Road and for through traffic from Central to Wan Chai and
Causeway Bay. The land formed for the above transport infrastructure will provide
opportunities for the development of an attractive waterfront promenade for the
enjoyment of the public
·
Reprovisioning / protection of the existing
facilities and structures affected by the land formation works mentioned above
·
Extension, modification, reprovisioning or
protection of existing storm water drainage outfalls, sewerage outfalls and
watermains affected by the revised land use and land formation works mentioned
above
·
Upgrading of hinterland storm water drainage system
and sewerage system, which would be rendered insufficient by the land formation
works mentioned above
·
Provision of the ground level roads, flyovers,
footbridges, necessary transport facilities and the associated utility services
·
Construction of the new waterfront promenade,
landscape works and the associated utility services
·
The Trunk Road (i.e. CWB) within the study area and
the associated slip roads for connection to the Trunk Road.
2.2.4.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits (FEP) such that the impact monitoring stations are sub-divided accordingly
to facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The
details of individual contracts are summarized in Table2.2.
Table
2.2 Details of Individual Contracts
under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II – Central –Wanchai Bypass at |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central – Wan Chai Bypass – North
Point Reclamation |
DP3 |
17 March 2010 (Completed) |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel ( |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2012/08 |
Wan Chai
Development Phase II Central- Wan Chai Bypass at
Wan Chai West |
DP1,DP2,
DP3 |
5 March 2013 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer’s Representative for
WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
Chun Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture
Board Representative |
|
2162 9909 |
2587 1878 |
Deputy Site
Agent |
Mr Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr Terry
Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 3008 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy
Mak |
9103 2370 |
|||
Environmental
Supervisor |
Fan Chun
Wai |
6487 4488 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project
Manager |
Mr. David
Lau |
3658-3022 |
2827 9996 |
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
9191 8856 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
K C Cheung |
3557 6399 |
2566 2192 |
Site Manager |
J H Chen |
3557 6368 |
|||
|
|
Contractor’s Representative |
Andrew Wong |
3557 6358 |
|
|
|
Head of Construction Manager |
Roger Cheung |
3557 6371 |
|
|
|
Senior Construction Manager |
Gene Cheung |
3557 6395 |
|
Environmental Officer |
Mr. Daniel Sin |
3557 6347 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Eric
Yip |
2529 2068 |
|||
Environmental Officer |
Clement
Pang |
9735 9200 |
|||
Environmental
Supervisor |
Jacky
Cheung |
9779 2292 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leader JV |
Contractor under Contract no. HK/2012/08 |
Project Director |
Andrew Tse |
9137 1811 |
2877 1522 |
|
|
Project Manager |
Victor Wu |
9193 8871 |
|
|
|
Deputy Project Manager |
George Cheung |
9268 1918 |
|
|
|
Site Agent |
Paul Lui |
9095 7922 |
|
|
|
Environmental Officer |
James Ma |
9130 9549 |
|
|
|
Environmental Supervisor |
Ching Man, Chan |
6050 4919 |
|
|
Contractor under
Contract no. HY/2010/08 |
Project Director |
Cheung Kit Cheung |
3557 6399 |
2566 8061 |
|
|
Project Manager |
Chan Ying Lun |
9812 0592 |
|
|
|
Deputy Project Manager |
Chris Leung |
3467 4299 |
|
|
|
Site Agent |
Dave Chan |
3467 4277 |
|
|
|
Environmental Officer |
C.M. Wong |
3557 6464 |
|
|
|
Environmental Supervisor |
Louis Lam Tsz Kwan |
3557 6470 |
|
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
34652888 |
34652899 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
During
this reporting period, the principal work activities for Contract no.
HK/2009/01 are summarized in Table 2.4.
Table
2.4 Principal Work Activities for Contract no.
HK/2009/01
September
2013 |
October 2013 |
November
2013 |
Marine
Works (at Wan Chai) Rockfilling
at Area 3 (East of Bottom
slab of Bay 8. Preparation work for blinding layer at Bay 9. Fabrication
work for steel bridge on the top of temporary open channel along Pre-drilling
for D-walls at Area 8 (interface wall, bulkhead). Installation of sleeve pipe
for predrilling work in order to remove the G75 rock before site
investigation. Ground
treatment work and guide wall construction. Formation for soil platform.
Plate load test. Cross-Harbour
Watermains Installation (CHA & CHB) and Marine Works (at TST) The stage
2 & 3 connection. The stage 4 capping works for XHWM. XHWM, Cooling
Watermains, Salt Watermains and Sewer (On Land) Design of
the additional anode between the new pipe and existing pipeline. Reinstatement
works at West Foyer of HKCEC. Planter reinstatement, kerbworks, hard paving.
All reinstatement works. Cooling
main works in Zone C1-2. Cooling main works along Salt
watermain laying works along west of Convention Avenue, J/O Convention Avenue
& Fenwick Per Street, Harbour Road in Zone A3-5C, A3-1, A3-5B, A2-4A,
A5-5 and A5-2. Salt watermain laying works along west of Temporary
ducting and cabling works at junction between Tunnel
Works Installation
of pre-bored H-pile in CWB Stage 2 Atrium Link (from CH120 to CH220). 45 nos.
pre-bored H-piles had been excavated. 32 nos. pre-bored H-piles were grouted
i.e. 22 nos. drilled and 26 nos. grouted. Construction
of the Common D-wall. Filling of
the existing open water channel from CH100 to CH206. Demolition
of the Promenade Deck. ELS work
at bottom-up area. Fabrication of steel strutting members. Installation of
ELS. |
Marine Works (at Wan Chai) Rock filling
up to +4.2 mPD for D-wall construction. Bottom
slab of Bay 8. Preparation work for blinding layer at Bay 9. Water leakage
was found and re-grouting. Fabrication
work for steel bridge on the top of temporary open channel along Pre-drilling
for D-walls at Area 8 (interface wall, bulkhead). Ground
treatment work and guide wall construction. XHWM, Cooling Watermains,
Salt Watermains and Sewer (On Land) Design of
the additional anode between the new pipe and existing pipeline. Reinstatement
works at HKCEC north & northwest. Reinstatement works at West Foyer of
HKCEC. Planter reinstatement, kerbworks, hard paving and all other minor
reinstatement works. Cooling
main works in Zone C1-2. Cooling main works along Salt
watermain laying works along west of Convention Avenue, J/O Convention Avenue
& Fenwick Per Street, Harbour Road in Zone A3-5C, A3-1, A3-5B, A2-4A,
A5-5 and A5-2. Salt watermain laying works along west of Relocation
works of fire hydrant in Zone X2-1. Temporary
ducting and cabling works at junction between Tunnel Works Installation
of pre-bored H-pile in CWB Stage 2 Atrium Link (from CH120 to CH220). Construction
of the Common D-wall. Filling of
the existing open water channel from CH100 to CH206. Demolition
of the Promenade Deck. Installation of sheet pile for demolition of P5 Pump
house. ELS work
at bottom-up area. Fabrication of steel strutting members. Installation of
ELS. |
Marine Works (at Wan Chai) Further
rock filling from HATS at East side in order to extend the work area. Concreting
at base slab of bay 8 and bay 9. Wall and roof slab construction work and he
box culvert. Fabrication
work for steel bridge on the top of temporary open channel along First
panel at temporary bulk head wall and C1/C2 interface wall Installation
of end plates to block the existing intakes P7 & P9. Outfall
construction for discharge pipes at Cooling Watermains, Salt
Watermains and Sewer (On Land) Design of
the additional anode between the new pipe and existing pipeline. Reinstatement
works at HKCEC north & northwest. Cooling
main laying works along Salt
watermain laying works along west of Convention Avenue, J/O Convention Avenue
& Fenwick Per Street, Harbour Road in Zone A3-5C, A3-1, A3-5B, A2-4A,
A5-5 and A5-2. Salt watermain laying works along west of Tunnel Works Installation
of pre-bored H-pile in CWB Stage 2 Atrium Link (from CH120 to CH220). Installation
of pre-bored H-pile in CWB Stage 3. Construction
of the Common D-wall. Filling of
the existing open water channel from CH100 to CH206. Further filling to P7
& P9. Demolition
of the Promenade Deck. Installation of sheet pile for demolition of P5 Pump
house and the works for tie-back.
Installation of ELS at first layer for Stage
1. |
2.5.2.
During
this reporting period, the principal work activities for Contract no.
HK/2009/02 are summarized in Table 2.5.
Table
2.5 Principal Work Activities for Contract no.
HK/2009/02
September
2013 |
October 2013 |
November
2013 |
Modification of existing covered walkway along The outstanding VSD parts for P7 Cooling Water Pumping Station reinstalled
. The 60 days for T&C period of P7 cooling water system. The T&C
period of P9. The temporary EVA construction for P7, P8 and P9 Cooling Water Pumping
Stations. Rectification works for P8 discharge mains near Gate No.1 60-Day T&C for P9 Cooling Water Pumping Station. Installation of Aeration and Chlorination Pipes at Temporary discharge pipe near CHS Trench excavation and ELS installation for the Y-section connecting
with the existing DN600 watermains at Additional horizontal gate valve chamber under VO No.114 located at
CHS8A230m. The remaining ABWF works and boundary wall in WSD Salt Water Pumping
Station, including maintenance platform and external finishes. The base slab, wall and top slab at Bay 5. Blinding layer for The access shafts of inspection manholes IM-01 and IM-02 at Bay 5. Construction of stoplog chamber extension SLO-01, SLO-02 and SLO-03 at
Bay 6. The stoplog installation. Formwork erection and rebar fixing for the 6nos. Temporary Covered
Walkway in the vicinity of Ferry Pier.
Interface coring and shear pin installation for the Eastern Bulkhead
Wall. The road modification works along Pavement works at Trimming of lifted-in sheetpile in front of SPCA’s Guard Room. Breaking up the existing carriageway next to SPCA’s Main Vehicular
Access. 90.7% of seawall blocks installation at WCR4/TWCR4 (844nos. out of
936nos.). 95% of geotextile at WCR4/TWCR4 area |
Modification of existing covered walkway along 60-Day Trial Operation for P7 Cooling Water Pumping Station. Fire Certificate for all P7, P8 and P9 Cooling Water Pumping Stations. Leakage rectification works for P8 discharge mains near Gate No.1. The DN150 washout pipe testing under VO No.114 located at CHS8A230m.
All necessary fittings and ready for gate valve installation by WSD. Pressure test to Y-Section for connection with the existing DN600 pipe
at The remaining ABWF works and boundary wall in WSD Salt Water Pumping
Station, including maintenance platform and external finishes. Bulkhead Removal at Bay 5 and Bay 6. The guiderail installation at stoplog chambers at Bay 6. The remedial works at Bay 3 and Bay 6. Revised certified ELS design for modifying the existing ELS for the
construction of Manhole No. FRP-N-MH2. The 6nos. Temporary Covered Walkway in the vicinity of Ferry Pier . Installation of base plates for seatings at Observation Deck Level of
Ferry Pier. Remedial works for the Eastern Bulkhead Wall. The road modification works along Pavement works at Backfilling works at Sorted public fill at WCR4/TWCR4. Seawall blocks installation at WCR4/TWCR4. Geotextile at WCR4/TWCR4 area.. |
Modification of existing covered walkway along Modification of road junction between Mainline of P8 discharge mains was tested. The leakage portion near
Gate No.1 had been fixed. The 60-day trial operation for P7 Cooling Water Pumping Station. Rectification works of the special movement joint for P8 discharge
main at CHBH152m. Defected special
movement joint was delivered off site for repairing works. Backfilling between CHAI 80 and CHAI 160, and CHAG Installation of 3 standpipes and the Water Tightness Test of Salt
Water Intake Culvert. For DN800 pipe, horizontal gate valve installation. Beforehead, epoxy
coating and flange adaptor installation. The remaining ABWF works and boundary wall in WSD Salt Water Pumping
Station, including maintenance platform and external finishes. Stoplog installation at Bay 6 of Box Culvert N1. The remedial works at Bay 6 of Box Culvert N1. Modifying the existing ELS for the construction of Manhole No.
FRP-N-MH2. DSD had accepted the Box Culvert N1 Bay 1 to Bay 6. Another site inspection for stoplog removal
trial was conducted with DSD. The Wall of FRP-N-MH2 construction and beforehead, the Water infilling to Box Culvert N1 for subsequent waternightness test.
Remedial works to stop leakage at Backfilling for Remaining connection between FRP-N-MH2 and SLO-03. Excavation to the formation level for the Temporary Covered Walkway
footing (GL5) in the vicinity of Ferry Pier.
Sand replacement test. Re-grouting works for the Eastern Bulkhead Wall. Proof drilling for re-grouting works for the Eastern Bulkhead Wall. Pavement works at All road markings and traffic sign installation. Implementation of HHR Flyover Diversion (Stage 1). WCR4/TWCR4 Reclamation: Public fill at WCR4/TWCR4. Seawall blocks installation at WCR4/TWCR4. Geotextile at WCR4/TWCR4 area. |
2.5.3.
Major construction activities for Contract no.
HY/2009/15 was commenced on 10 November 2010. During this reporting period, the
principal work activities for Contract no. HY/2009/15 are summarized as below:
Table
2.6 Principal Work Activities for Contract no. HY/2009/15
September
2013 |
October 2013 |
November
2013 |
Construction of EVA |
Construction of EVA |
Construction of EVA Maintenance dredging |
2.5.4.
Contract
no. HK/2010/06 was commenced on 22 March 2011. During this reporting period,
the principal work activities for Contract no. HK/2010/06 are summarized as
below:
Table
2.7 Principal Work Activities for Contract no. HK/2010/06
September
2013 |
October 2013 |
November
2013 |
Sheet
piling works |
Sheet
piling works |
Sheet
piling works |
2.5.5.
Contract no. HY/2009/19 was commenced on 24 March
2011. During this reporting period, the principal work activities for Contract
no. HY/2009/19 are summarized as below:
Table
2.8 Principal Work Activities for Contract no. HY/2009/19
September
2013 |
October 2013 |
November
2013 |
D-wall and Barrette Construction Construction works for Box Culvert T1 Backfill works for Box Culvert U1 Removal of marine platform Construction of pile cap, pier & cross head (Marine) Installation of dewatering well Laying of 1500f pipe Launching of segments Extraction of temporary pile from marine section Construction of bridge truss TA1 |
D-wall and Barrette Construction Removal of strut at ELS Construction works for Box Culvert T1 Removal of marine platform Construction of pile cap, pier & cross head (Marine) ELS and Cut & Cover Tunnel Installation of dewatering well Laying of 1500f pipe Launching of segments Extraction of temporary pile from marine section Construction of bridge truss TA1 Demolition of parapet at IEC link Construction of King Post at ELS |
D-wall and Barrette Construction Removal of strut at ELS will commence Construction works for Box Culvert T1 Removal of marine platform Construction of pile cap, pier & cross head (Marine) ELS, EVB and Cut & Cover Tunnel Installation of dewatering well Laying of 1500f pipe Launching of segments Extraction of temporary pile from marine section Construction of bridge truss TA1 Demolition of parapet at IEC link Construction of King Post at ELS |
2.5.6.
Contract no. HK/2012/08 was commenced on March 2013.
During this reporting period, the principal work activities for Contract no. HK/2012/08
are summarized as below:
Table
2.9I Principal Work Activities for Contract no. HK/2012/08
September
2013 |
October 2013 |
November
2013 |
Site preparation works Site survey ELS for box culvert La at Dredging Demolition of the existing |
Site preparation works Site survey ELS for box culvert La at Dredging Preparation works for abandoning watermains at |
Site preparation works Site survey ELS for box culvert La at Dredging Preparation works for abandoning watermains at Seawall rock mound formation |
2.5.7.
Implementation
status of the recommended mitigation measures during this reporting period is
presented in Appendix 2.1.
Noise Monitoring Stations
3.1.1. The noise monitoring stations for the Project
are listed and shown in Table 3.1 and Figure 3.1. Appendix 3.1 shows
the established Action/Limit Levels for the monitoring works.
Table
3.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Real
time Noise Monitoring Stations
3.1.1.
The real-noise monitoring stations for the Project are
listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1 shows the established Action/Limit Levels for
the monitoring works.
Table
3.2 Real Time Noise
Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
North Point |
RTN2a |
Electric Centre |
Noise Monitoring
Parameters, Frequency and Duration
3.1.2. The construction noise level
shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period
between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq
(5 minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10 and
L90 shall also be obtained for reference.
3.1.3. Noise monitoring shall be
carried out at all the designated monitoring stations. The monitoring frequency
shall depend on the scale of the construction activities. The following is an
initial guide on the
regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
·
one
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.4. If construction works are extended to include works
during the hours of 1900 – 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
3.1.5. Real time noise shall be carried out at the designated
monitoring stations. The following is an initial guide on the regular
monitoring frequency for each station on a 24 hours daily basis when noise
generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
Monitoring Equipment
3.1.6. As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level from
before and after the noise measurement agree to within 1.0 dB.
3.1.7. Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
Air Quality Monitoring
Stations
3.2.1.
The
air monitoring stations for the Project are listed and shown in Table
3.3 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels for the
monitoring works.
Table 3.3 Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to |
Wan Chai |
CMA6a |
WDII PRE Site Office * |
Wan Chai |
* Remarks: As per the ENPC meeting in January 2011, the monitoring stations CMA3a - Future CWB site office at Wanchai Waterfront Pr