Contract
No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and
Testing Work (Stage 2) Environmental
Permit no. EP-356/2009, Further Evironmental permit nos.
fep-01/356/2009, fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 and
fep-05/356/2009 Quarterly Environmental Monitoring
and Audit Report
- September 2012 to November 2012 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
28 December 2012 |
2.2 Scope
of the Project and Site Description
2.3 Division of the Project
Responsibility
2.4 Project Organization and Contact
Personnel
2.5 Principal Work and Activities
4.2. Real Time Noise Monitoring Results
5.2. Real-time Noise Monitoring
5.6. Review
of the Reasons for and the Implications of Non-compliance
5.7. Summary
of action taken in the event of and follow-up on non-compliance
6. Complaints, Notification
of Summons and Prosecution
7. Cumulative Construction
Impact due to the Concurrent Projects.
lIST
OF TABLES
Table I Principal Work Activities
for Contract no. HY/2009/11
Table II Principal Work Activities
for Contract no. HK/2009/01
Table III Principal Work Activities
for Contract no. HK/2009/02
Table IV Principal Work Activities for Contract no. HY/2009/15
Table V Principal Work Activities for Contract no. HK/2010/06
Table VI Principal Work Activities for Contract no. HY/2009/19
Table 2.1 Schedule 2 Designated Projects under this
Project
Table 2.2 Details of Individual Contracts under the
Project
Table 2.3 Contact Details of Key Personnel
Table 2.4 Principal Work Activities for Contract no. HY/2009/11
Table 2.5 Principal Work Activities for Contract no. HK/2009/01
Table 2.6 Principal Work Activities for Contract no. HK/2009/02
Table 2.7 Principal Work Activities for Contract no. HY/2009/15
Table 2.8 Principal Work Activities for Contract no. HK/2010/06
Table 2.9 Principal Work Activities for Contract no. HY/2009/19
Table 3.1 Noise
Monitoring Stations
Table 3.2 Real
Time Noise Monitoring Station
Table 3.3 Air
Monitoring Stations
Table 3.4 Marine
Water Quality Stations for Water Quality Monitoring
Table 3.5 Marine
Water Quality Monitoring Frequency and Parameters
Table 3.6 Marine Water Quality
Stations for Enhanced Water Quality Monitoring
Table 3.7 Marine Water Quality
Stations for Additional DO Monitoring
Table 4.1 Noise
Monitoring Stations for Contract no.
HY/2009/11
Table 4.2 Noise Monitoring
Station for Contract nos. HK/2009/01 and HK/2009/02
Table 4.3 Noise
Monitoring Station for Contract nos. HY/2009/15
Table 4.5 Noise
Monitoring Station for Contract nos. HY/2009/19
Table 4.7 Air Monitoring Stations for
Contract no. HY/2009/11
Table 4.8 Air Monitoring Stations for Contract no. HK/2009/01
Table 4.9 Air Monitoring
Station for Contract no. HK/2009/02
Table 4.10 Air
Monitoring Station for Contract no. HY/2009/15
Table 4.11 Air
Monitoring Station for Contract no. HY/2009/19
Table 4.12 Water
Monitoring Stations for Contract no.
HY/2009/11
Table 4.13 Water
Monitoring Stations for Contract no. HK/2009/01
Table 4.14 Water
Monitoring Stations for Contract no. HK/2009/02
Table 4.15 Water
Monitoring Stations for Contract no. HK/2010/06
Table 4.16 Water
Monitoring Stations for Contract no. HY/2009/15
Table
4.17 Water Monitoring Stations for
Contract no. HY/2009/19
Table 4.18 Summary of Water Quality Monitoring Exceedances in
Reporting period
Table 4.18a Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting period
Table 4.19 Details
of Waste Disposal for Contract no. HY/2009/11
Table 4.20 Details of Waste Disposal for Contract no. HK/2009/01
Table 4.21 Details of Waste Disposal for Contract no. HK/2009/02
Table 4.22 Details of Waste Disposal for Contract no. HY/2009/15
Table 4.23 Details of Waste Disposal for Contract no. HK/2010/06
Table 4.24 Details
of Waste Disposal for Contract no. HY/2009/19
Table 5.1 Summary of Water Quality Monitoring Exceedances in
Reporting period
Table 5.1a Summary of Enhanced Dissolved Oxygen Monitoring
Exceedances in Reporting period
Table 6.1 Cumulative Statistics on Complaints
Table 6.2 Cumulative Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 3.1 Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix 2.1 Environmental
Mitigation Implementation Schedule
Appendix 3.1 Action
and Limit Level
Appendix 4.1 Noise
Monitoring Graphical Presentations
Appendix 4.2 Air
Quality Monitoring Graphical Presentations
Appendix 4.3 Water
Quality Monitoring Graphical Presentations
Appenidx 4.3a Additional Dissolved Oxygen
Monitoring Results
Appendix
4.4 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 5.1 Event
Action Plans
Appendix 6.1 Complaint
Log
Appendix 7.1 Construction Programme of Individual Contracts
Construction Activities for the
Reported Period
Table I Principal Work Activities for Contract
no. HY/2009/11
September 2012 |
October 2012 |
November 2012 |
The major
work activities for Contract no. HY/2009/11 was confirmed substantial complete
by RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19. |
The
Contractor HY/2009/11 had been submitted the surrender of Further
Environmental Permit (FEP-01/356/2009) to EPD on 22
October 2012 The major
work activities for Contract no. HY/2009/11 was confirmed substantial complete
by RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19. |
Nil |
Table II Principal Work Activities for Contract no.
HK/2009/01
September 2012 |
October 2012 |
November 2012 |
Marine Works (at Wan Chai) Rockfilling
for rock bund across HKCEC Water Channel from Ch220 to Ch230 Reclamation of
HKCEC3W within HKCEC Water Channel Installation
of pipe pile wall for demolition of existing seawall at Demolition
of Wan Chai West Ferry Pier Fabrication
of 3 nos. of precast concrete caisson seawall Cross-Harbour Watermains Installation (CHA
& CHB) and Marine Works (at TST) Rockfilling
and rock protection to cross-harbour watermains Thrust
block construction for A16 & B16 and A17 & B17 Site area
at Fresh Watermains, Cooling Watermains and Salt
Watermains (On Land) Mainlaying
works at Zone B1-5A, B2-1, B3-1, B4-3, B4-1A, B5-1(Switch Room), B5-3(Switch
Room), A1-1, A1-2, A1-3B, A2-2, A3-2A, A3-4B and Run-out of Renaissance Hotel
Mainlaying
works and subsequent reinstatement in Zone A4-2A and Zone A3-5B Mainlaying
works and part of the carriageway reinstatement in Zone A3-2A.Heading No. H1
would be carried out in the excavated trench as a jacking pit Mainlaying
works at Zone A3-4B Mainlaying
works at Run-out of Renaissance Hotel Excavation
works for Heading No. H6c (Mainlaying works by trenchless method) and pipe
laying works Heading
No. H1 Pipe
laying works for heading No. H6a Mainlaying
and chamber construction works at the traffic island near junction of Mainlaying
works at Trial pit
at Zone X1-6 of Pipe
Laying works including 9 nos. cooling mains and 2 nos. cross harbour
watermains at North Bank of HKCEC Water Channel Pipe
Laying works including 9 nos. cooling mains and 2 nos. cross harbour
watermains across E/D section within HKCEC Water Channel Pipe
Laying works including 9 nos. cooling mains and 2 nos. cross harbour
watermains across SCL section within HKCEC Water Channel Final
cleaning, CCTV inspection and pressure test for the 9 nos. cooling watermains
|
Marine Works (at Wan Chai) Rockfilling
for HKCEC3E (East of HKCEC) between CH290 and CH385 Installation
of pipe pile wall for demolition of existing seawall at Dredging
works for Type 3 sediment beneath Dredging
works for Type 2 sediment beneath Fabrication
of 3 nos. of precast concrete caisson seawall, 1 no. precast concrete box
culvert (namely Bay 100 and 2 nos. precast discharge outfall in precasting
yard at Cross-Harbour Watermains Installation (CHA
& CHB) and Marine Works (at TST) Rockfilling
and rock protection to cross-harbour watermains Thrust
block construction for A18B18 Platform
erection for crawler crane demobilization at TST landfall near Pressure
test for fresh watermains CHE and CHF Pressure
test for cross-harbour watermains CHA and CHB Fresh Watermains, Cooling Watermains and Salt
Watermains (On Land) Mainlaying
works at Zone B1-5A, B2-1, B3-1, B5-1(Switch Room), B5-3(Switch Room), A1-1,
A1-2, A1-4, A2-3D, A3-2A, A3-4B, C1-10 and Run-out of Renaissance Hotel Mainlaying
works and subsequent reinstatement in Zone B4-3 and Zone B4-1A Mainlaying
works and subsequent reinstatement in Zone A2-2 and TTA Zone A2-3D Pipe
laying works at Heading No. H6c has been completed and the road reinstatement
works at the jacking pit of Zone A1-3B and TTA Zone A1-4 Pipe
laying works for heading No. H6a. Excavation
works at Heading No. H1 Mainlaying
and chamber construction works at the traffic island near junction of Mainlaying
works at Final
cleaning, CCTV inspection and pressure test for the 9 nos. cooling watermains
E&M Electrical
works in cooling water pumping stations P5 Cable
works at Zone B1-5A, Zone B5-1(Switch Room) and B5-3(Switch Room) Power
energization to L.V. switchboard for cooling water pumping stations P1, P3
and P4 by HEC Power
supply to cooling water pumping stations P1 and P4 from L.V. switchboard Optical
fiber cabling works from cooling water pumping stations P1, P3, P4 and P5 to
relative stakeholders |
Marine Works (at Wan Chai) Rockfilling
for HKCEC3E (East of HKCEC) between CH290 and CH385 Grouting
works to pipe pile at Removal of
existing seawall and rock armour at Dredging
underneath Fabrication
of 3 nos. of precast concrete caisson seawall, 1 no. precast concrete box
culvert (namely Bay 10) and 2 nos. precast discharge outfall in precasting
yard at Cross-Harbour Watermains Installation (CHA
& CHB) and Marine Works (at TST) Rockfilling
and rock protection to cross-harbour watermains Thrust
block construction for A18B18 Connection
work between land pipeline and marine pipeline Reinstatement
works for the TST landfall Fresh Watermains, Cooling Watermains and Salt
Watermains (On Land) Mainlaying
works at Zone B1-5A, B2-1, B3-1, A1-1, A1-2, A1-4, A1-2A & A1-3A, A2-3D,
A3-2A, A3-4B, A3-3C, C1-6 and run-out of Renaissance Hotel Mainlaying
works at TTA Zone A2-3D and A1-4 Pipe
laying works at heading No. H1 and Zone A3-4B Mainlaying
works at Zone A3-3C Mainlaying
and chamber construction works at the traffic island near junction of Mainlaying
works at Final
cleaning, CCTV inspection and pressure test for the 9 nos. cooling watermains
E&M Electrical
works in cooling water pumping stations P5 Major
cabling works from existing LV Switch-board Room to Cooling Water Pumping
Station P5 Power
energization to L.V. switchboard for cooling water pumping stations P5 Full
commissioning for Cooling Water Pumping Stations P1 |
Table III Principal Work Activities for Contract no.
HK/2009/02
September 2012 |
October 2012 |
November 2012 |
Modification
work of PTI at Modification
work of bus station at Initial
testing of the pumping stations of P7 (GE/HC), P8 (SHK) and P9 (CRB) Reinstatement
at Cooling
mains installation at west of Gate 1 inside ex-pet garden and the steel
fixing of the damaged thrust box was casted Waterproofing
membrane at roof level of WSD Salt Water Pumping Station E&M
works at WSD Salt Water Pumping Station Cutting
opening and removing sheet pile of WSD receiving pit connecting to Wan Shing
Street Intake Culverts Concreting
of the inspection chamber (1st lift) at salt water intake culvert Bay 20 Stripping
of formwork and cement mortar of tie holes for wall shaft inside salt intake
culvert Bay 19b ~ Bay 24 Welding
for the 1st layer waling at salt water intake culvert Bay 9 to Bay 11 at WCR1
Concreting
of pile caps of Bay Concreting
of pile caps of Bay Cutting the
opening of sheet piles and saw cutting of D-wall & thrust wall between
Launching Pit and Jacking Pit Placing
concrete for surround the HDPE pipe at Submarine Sewage Outfall Seaside
Cofferdam Placing of
25.5° Placing of
Mild Steel Horizontal Bend at DSD Receiving Pit of pipeline A Fixing
brackets to the bend section at temporary steel bridge Laying
HDPE pipes and placing concrete surround for the pipes at Launching Pit &
TBM Jacking Pit Concreting
the base slab of Box Culvert N1 Bay 1 The wall
& top slab of Bay 2 and Bay 3 on UU bridge Welding
steel capping plate for pile cap of Box N1 Bay 4, steel re-bars for pile cap Welding
steel capping plate for pile cap of Box N1 Bay 5 TTA for
trial excavation and preparation works for Hung Hing Road Diversion Dewatering
for the construction new Ø Concreting
the columns at New Ferry Pier C8B to C Concreting
the column at New Ferry Pier C10D and hanger wall between Level Concreting
the slab at New Ferry Pier Level Deep
excavation works were ongoing. The excavation levels have reached -20mPD to
-23mPD on the eastern and western portion of the site
Rockfilling and placing bagged concrete for
the temporary seawall at WCR2 Reclamation of WCR2 |
Repairing of door hinge in the New
Public Toilet Modification
work of PTI at Modification
work of bus station at Reinstatement
at Modification
work of P7, P8 and P9 Cooling water pumping station Cooling
mains installation at west of Gate 1 inside ex-pet garden FS
inspection of WSD Pumping Station E&M
works at WSD Salt Water Pumping Station Modification
work of EVA at WSD Pumping Station Stripping
formwork and application of cement mortar for the tie bolt holes inside salt
water intake culvert Bay 19b ~ Bay 24 Concreting
for box-out of access chamber at Bay19b Concreting
of the base slab at salt water intake culvert Bay Remedial
work of wall and top slab of salt water intake A and B was completed Concreting
of base slab at salt water intake culvert jacking pit at WCR1 Welding
for the 2nd layer waling at salt water intake culvert Bay 9 to Bay 11 at WCR1
Concreting
of wall and top slab of Bay Concreting
of pile caps and wall together with top slab of Bay Concreting
of base slab of Bay 1 and Bay Cavity
grouting between the HDPE Pipes B and Concrete Sleeve Pipes at TBM Jacking
Pit Breaking
the extra cement grout at deformed area for removal of HDPE Pipe A from
tunnel and the re-splicing work. Laying
HDPE pipe A and pipe B at temporary steel bridge Vertical
bend installation of HDPE pipe A & pipe B and connection to short
pipe Concreting
the wall and top slab of box culvert N1 Bay 1 on UU bridge Concreting
the Inspection Manhole IM-03 & IM-04 at box culvert N1 Bay 2 and desilting
opening DO-01 & DO-02 Concreting
the pile caps of Bay 4 and Bay 5 of box culvert N1, backfill the area with
concrete outside the caps |
Repairing
of door hinges in the New Public Toilet. Modification
work of PTI at Modification
work of bus station at Pre-inspection
for P9 (SHK) Pumping Station.Reinstatement at Cooling
mains installation at west of Gate 1 inside ex-pet garden Cooling
main remedial works for the bending pipes Installation
of optic fiber and power cable E&M
works and ABWFs installation at WSD Salt Water Pumping Station Concreting
of boundary wall of EVA at WSD Pumping Station Concreting
of Inspection Manhole and Access Chamber of Salt Water Intake Culvert at Bay
19B & 20 Concreting
of the wall and top slab at salt water intake culvert Bay Concreting
of the blinding layer at salt water intake culvert Bay 9 - Bay 11 at WCR1 Concreting
of the wall and top slab at salt water intake culvert Bay 9 at WCR1 and steel
fixing of base slab at Bay 10 Cutting
the sheetpile wall at salt water intake culvert Bay 11 to jacking pit Concreting
of wall and top slab of Bay |
Table IV
Principal Work Activities for Contract
no. HY/2009/15
September 2012 |
October 2012 |
November 2012 |
TZ1
reclamation works Removal of
temporary reclamation at TS1 Dredging
for seawall foundation at TS2 Formation
of temporary seawall at TS2 Seawall
trench works at TS2 |
TZ1
reclamation works Formation
of temporary seawall at TS2 Seawall
trench works at TS2 |
TZ1 and
TS2 reclamation works
Formation of temporary seawall at TS2 |
Table V
Principal Work Activities for
Contract no. HK/2010/06
September 2012 |
October 2012 |
November 2012 |
Pile head
breaking Sonic tube
trimming |
Pile head
breaking Sonic tube
trimming |
Pile head
breaking Platform
Disassembly
Bored Pile cutting |
Table
VI
Principal Work Activities for Contract
no. HY/2009/19
September 2012 |
October 2012 |
November 2012 |
Marine bored
piling Construction
works for Box Culvert T |
Marine
bored piling Construction
works for Box Culvert T Construction
of 1500f drainage
pipe |
Marine
bored piling Construction
works for Box Culvert T |
Noise Monitoring
Real-time Noise Monitoring
Air Quality Monitoring
CMA1b: from 6 and 24 September 2012 to 7 and 25 September 2012
CMA2a: from 22 October 2012 to 24 October 2012
from 8 and 14 November 2012 to 9 and 15 November 2012
CMA3a: from 18 September 2012 to 19 September 2012
CMA4a: from 24 September 2012 to 25 September 2012
from 29 September 2012
to 3 October 2012
CMA5a: from 31 August and 24 September 2012 to 1 and 26 September 2012
from 8 November 2012 to 9 November 2012
CMA6a: from 31 August 2012 to 1 September 2012
Water Quality Monitoring
2 Nov 2012
Mid-Flood tide
3 Nov 2012
Mid-Ebb tide
5 Nov 2012
Mid-Flood tide
6 Nov 2012
Mid-Ebb tide
Complaints, Notifications of
Summons and Successful Prosecutions
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-356/2009 and Further Environmental
permit nos. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the Environmental Monitoring and
Audit (EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.4 of EM&A Manual and “Environmental
Monitoring and Audit Requirements” under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
during the period from September 2012 to November 2012
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements – summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results – summarizes the monitoring results
obtained in the reporting period.
Section 5 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
The
Project is located mainly in Wan Chai North,
2.2.2.
The
study area encompasses existing developments along the Wan Chai,
2.2.3.
The scope of the Project comprises:
·
Land formation for key transport infrastructure and
facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for
connection to the Trunk Road and for through traffic from Central to Wan Chai and
Causeway Bay. The land formed for the above transport infrastructure will provide
opportunities for the development of an attractive waterfront promenade for the
enjoyment of the public
·
Reprovisioning / protection of the existing
facilities and structures affected by the land formation works mentioned above
·
Extension, modification, reprovisioning or
protection of existing storm water drainage outfalls, sewerage outfalls and
watermains affected by the revised land use and land formation works mentioned
above
·
Upgrading of hinterland storm water drainage system
and sewerage system, which would be rendered insufficient by the land formation
works mentioned above
·
Provision of the ground level roads, flyovers,
footbridges, necessary transport facilities and the associated utility services
·
Construction of the new waterfront promenade,
landscape works and the associated utility services
·
The Trunk Road (i.e. CWB) within the study area and
the associated slip roads for connection to the Trunk Road.
2.2.4.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits (FEP) such that the impact monitoring stations are sub-divided
accordingly to facilitate the implementation of EM&A programme and to
streamline the EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The
details of individual contracts are summarized in Table2.2.
Table
2.2 Details of Individual Contracts
under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II – Central –Wanchai Bypass at |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central – Wan Chai Bypass – North
Point Reclamation |
DP3 |
17 March 2010 (Under applicationof surrender) |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel ( |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer’s Representative for
WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
|
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project
Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental
Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
|
2162 9909 |
2587 1878 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Sub-Agent |
Mr Terry
Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 3008 |
|||
Construction
Manager |
Mr. KK Yuen |
9498 1213 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy
Mak |
9103 2370 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658 3000 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Chan Wai Hung |
2823 7813 |
2865 5229 |
Site Manager |
P J Fan |
3557 6368 |
2566 2192 |
||
|
|
Contractor’s Representative |
Mr. David Lau |
3557 6368 |
2566 2192 |
|
|
Head of Construction Manager |
Roger Cheung |
3557 6371 |
2566 2192 |
|
|
Senior Construction Manager |
Gene Cheung |
3557 6395 |
2566 2192 |
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|
||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental Officer |
Mr. Lee Wai Man |
9481 6024 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
During
this reporting period, the principal work activities for Contract no.
HY/2009/11 are summarized in Table2.4.
Table
2.4 Principal Work Activities for
Contract no. HY/2009/11
September 2012 |
October 2012 |
November 2012 |
The major
work activities for Contract no. HY/2009/11 was confirmed substantial complete
by RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19. |
The
Contractor HY/2009/11 had been submitted the surrender of Further
Environmental Permit (FEP-01/356/2009) to EPD on 24 October 2012 The major
work activities for Contract no. HY/2009/11 was confirmed substantial complete
by RSS on 4 January 2012. The construction site was handed over to contractor
HY/2009/19. |
Nil |
2.5.2.
During
this reporting period, the principal work activities for Contract no.
HK/2009/01 are summarized in Table 2.5.
Table
2.5 Principal Work Activities for
Contract no. HK/2009/01
September
2012 |
October 2012 |
November
2012 |
Marine
Works (at Wan Chai) Rockfilling
for rock bund across HKCEC Water Channel from Ch220 to Ch230 Reclamation of
HKCEC3W within HKCEC Water Channel Installation
of pipe pile wall for demolition of existing seawall at Demolition
of Wan Chai West Ferry Pier Fabrication
of 3 nos. of precast concrete caisson seawall Cross-Harbour
Watermains Installation (CHA & CHB) and Marine Works (at TST) Rockfilling
and rock protection to cross-harbour watermains Thrust
block construction for A16 & B16 and A17 & B17 Site area
at Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land) Mainlaying
works at Zone B1-5A, B2-1, B3-1, B4-3, B4-1A, B5-1(Switch Room), B5-3(Switch
Room), A1-1, A1-2, A1-3B, A2-2, A3-2A, A3-4B and Run-out of Renaissance Hotel
Mainlaying
works and subsequent reinstatement in Zone A4-2A and Zone A3-5B Mainlaying
works and part of the carriageway reinstatement in Zone A3-2A.Heading No. H1
would be carried out in the excavated trench as a jacking pit Mainlaying
works at Zone A3-4B Mainlaying
works at Run-out of Renaissance Hotel Excavation
works for Heading No. H6c (Mainlaying works by trenchless method) and pipe
laying works Heading
No. H1 Pipe
laying works for heading No. H6a Mainlaying
and chamber construction works at the traffic island near junction of Mainlaying
works at Trial pit
at Zone X1-6 of Pipe
Laying works including 9 nos. cooling mains and 2 nos. cross harbour
watermains at North Bank of HKCEC Water Channel Pipe
Laying works including 9 nos. cooling mains and 2 nos. cross harbour
watermains across E/D section within HKCEC Water Channel Pipe
Laying works including 9 nos. cooling mains and 2 nos. cross harbour
watermains across SCL section within HKCEC Water Channel Final
cleaning, CCTV inspection and pressure test for the 9 nos. cooling watermains
|
Marine
Works (at Wan Chai) Rockfilling
for HKCEC3E (East of HKCEC) between CH290 and CH385 Installation
of pipe pile wall for demolition of existing seawall at Dredging
works for Type 3 sediment beneath Dredging
works for Type 2 sediment beneath Fabrication
of 3 nos. of precast concrete caisson seawall, 1 no. precast concrete box
culvert (namely Bay 100 and 2 nos. precast discharge outfall in precasting
yard at Cross-Harbour
Watermains Installation (CHA & CHB) and Marine Works (at TST) Rockfilling
and rock protection to cross-harbour watermains Thrust
block construction for A18B18 Platform
erection for crawler crane demobilization at TST landfall near Pressure
test for fresh watermains CHE and CHF Pressure
test for cross-harbour watermains CHA and CHB Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land) Mainlaying
works at Zone B1-5A, B2-1, B3-1, B5-1(Switch Room), B5-3(Switch Room), A1-1,
A1-2, A1-4, A2-3D, A3-2A, A3-4B, C1-10 and Run-out of Renaissance Hotel Mainlaying
works and subsequent reinstatement in Zone B4-3 and Zone B4-1A Mainlaying
works and subsequent reinstatement in Zone A2-2 and TTA Zone A2-3D Pipe
laying works at Heading No. H6c has been completed and the road reinstatement
works at the jacking pit of Zone A1-3B and TTA Zone A1-4 Pipe
laying works for heading No. H6a. Excavation
works at Heading No. H1 Mainlaying
and chamber construction works at the traffic island near junction of Mainlaying
works at Final
cleaning, CCTV inspection and pressure test for the 9 nos. cooling watermains
E&M Electrical
works in cooling water pumping stations P5 Cable
works at Zone B1-5A, Zone B5-1(Switch Room) and B5-3(Switch Room) Power
energization to L.V. switchboard for cooling water pumping stations P1, P3
and P4 by HEC Power
supply to cooling water pumping stations P1 and P4 from L.V. switchboard Optical
fiber cabling works from cooling water pumping stations P1, P3, P4 and P5 to
relative stakeholders |
Marine
Works (at Wan Chai) Rockfilling
for HKCEC3E (East of HKCEC) between CH290 and CH385 Grouting
works to pipe pile at Removal of
existing seawall and rock armour at Dredging
underneath
Fabrication of 3 nos. of precast concrete
caisson seawall, 1 no. precast concrete box culvert (namely Bay 10) and 2
nos. precast discharge outfall in precasting yard at Cross-Harbour
Watermains Installation (CHA & CHB) and Marine Works (at TST) Rockfilling
and rock protection to cross-harbour watermains Thrust
block construction for A18B18 Connection
work between land pipeline and marine pipeline Reinstatement
works for the TST landfall Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land) Mainlaying
works at Zone B1-5A, B2-1, B3-1, A1-1, A1-2, A1-4, A1-2A & A1-3A, A2-3D,
A3-2A, A3-4B, A3-3C, C1-6 and run-out of Renaissance Hotel Mainlaying
works at TTA Zone A2-3D and A1-4 Pipe
laying works at heading No. H1 and Zone A3-4B Mainlaying
works at Zone A3-3C Mainlaying
and chamber construction works at the traffic island near junction of Mainlaying
works at Final
cleaning, CCTV inspection and pressure test for the 9 nos. cooling watermains
E&M Electrical
works in cooling water pumping stations P5 Major
cabling works from existing LV Switch-board Room to Cooling Water Pumping
Station P5 Power
energization to L.V. switchboard for cooling water pumping stations P5 Full
commissioning for Cooling Water Pumping Stations P1 |
2.5.3.
During
this reporting period, the principal work activities for Contract no.
HK/2009/02 are summarized in Table 2.6.
Table
2.6 Principal Work Activities for
Contract no. HK/2009/02
September
2012 |
October 2012 |
November
2012 |
Modification
work of PTI at Modification
work of bus station at Initial
testing of the pumping stations of P7 (GE/HC), P8 (SHK) and P9 (CRB) Reinstatement
at Cooling
mains installation at west of Gate 1 inside ex-pet garden and the steel
fixing of the damaged thrust box was casted Waterproofing
membrane at roof level of WSD Salt Water Pumping Station E&M
works at WSD Salt Water Pumping Station Cutting
opening and removing sheet pile of WSD receiving pit connecting to Wan Shing
Street Intake Culverts Concreting
of the inspection chamber (1st lift) at salt water intake culvert Bay 20 Stripping
of formwork and cement mortar of tie holes for wall shaft inside salt intake
culvert Bay 19b ~ Bay 24 Welding
for the 1st layer waling at salt water intake culvert Bay 9 to Bay 11 at WCR1
Concreting
of pile caps of Bay Concreting
of pile caps of Bay Cutting the
opening of sheet piles and saw cutting of D-wall & thrust wall between
Launching Pit and Jacking Pit Placing
concrete for surround the HDPE pipe at Submarine Sewage Outfall Seaside
Cofferdam Placing of
25.5° Placing of
Mild Steel Horizontal Bend at DSD Receiving Pit of pipeline A Fixing
brackets to the bend section at temporary steel bridge Laying
HDPE pipes and placing concrete surround for the pipes at Launching Pit &
TBM Jacking Pit Concreting
the base slab of Box Culvert N1 Bay 1 The wall
& top slab of Bay 2 and Bay 3 on UU bridge Welding
steel capping plate for pile cap of Box N1 Bay 4, steel re-bars for pile cap Welding
steel capping plate for pile cap of Box N1 Bay 5 TTA for
trial excavation and preparation works for Hung Hing Road Diversion Dewatering
for the construction new Ø Concreting
the columns at New Ferry Pier C8B to C Concreting
the column at New Ferry Pier C10D and hanger wall between Level Concreting
the slab at New Ferry Pier Level Deep
excavation works were ongoing. The excavation levels have reached -20mPD to
-23mPD on the eastern and western portion of the site
Rockfilling and placing bagged concrete for
the temporary seawall at WCR2 Reclamation of WCR2 |
Repairing
of door hinge in the New Public Toilet Modification
work of PTI at Modification
work of bus station at Reinstatement
at Modification
work of P7, P8 and P9 Cooling water pumping station Cooling
mains installation at west of Gate 1 inside ex-pet garden FS
inspection of WSD Pumping Station E&M
works at WSD Salt Water Pumping Station Modification
work of EVA at WSD Pumping Station Stripping
formwork and application of cement mortar for the tie bolt holes inside salt
water intake culvert Bay 19b ~ Bay 24 Concreting
for box-out of access chamber at Bay19b Concreting
of the base slab at salt water intake culvert Bay Remedial
work of wall and top slab of salt water intake A and B was completed Concreting
of base slab at salt water intake culvert jacking pit at WCR1 Welding
for the 2nd layer waling at salt water intake culvert Bay 9 to Bay 11 at WCR1
Concreting
of wall and top slab of Bay Concreting
of pile caps and wall together with top slab of Bay Concreting
of base slab of Bay 1 and Bay Cavity
grouting between the HDPE Pipes B and Concrete Sleeve Pipes at TBM Jacking
Pit Breaking
the extra cement grout at deformed area for removal of HDPE Pipe A from
tunnel and the re-splicing work. Laying
HDPE pipe A and pipe B at temporary steel bridge Vertical
bend installation of HDPE pipe A & pipe B and connection to short
pipe Concreting
the wall and top slab of box culvert N1 Bay 1 on UU bridge Concreting
the Inspection Manhole IM-03 & IM-04 at box culvert N1 Bay 2 and
desilting opening DO-01 & DO-02 Concreting
the pile caps of Bay 4 and Bay 5 of box culvert N1, backfill the area with
concrete outside the caps |
Repairing
of door hinges in the New Public Toilet. Modification
work of PTI at Modification
work of bus station at Pre-inspection
for P9 (SHK) Pumping Station.Reinstatement at Cooling
mains installation at west of Gate 1 inside ex-pet garden Cooling
main remedial works for the bending pipes Installation
of optic fiber and power cable E&M
works and ABWFs installation at WSD Salt Water Pumping Station Concreting
of boundary wall of EVA at WSD Pumping Station Concreting
of Inspection Manhole and Access Chamber of Salt Water Intake Culvert at Bay
19B & 20 Concreting
of the wall and top slab at salt water intake culvert Bay Concreting
of the blinding layer at salt water intake culvert Bay 9 - Bay 11 at WCR1 Concreting
of the wall and top slab at salt water intake culvert Bay 9 at WCR1 and steel
fixing of base slab at Bay 10 Cutting
the sheetpile wall at salt water intake culvert Bay 11 to jacking pit Concreting
of wall and top slab of Bay |
2.5.4.
Major construction activities for Contract no.
HY/2009/15 was commenced on 10 November 2010. During this reporting period, the
principal work activities for Contract no. HY/2009/15 are summarized as below:
Table
2.7 Principal Work Activities for Contract no. HY/2009/15
September
2012 |
October 2012 |
November
2012 |
TZ1
reclamation works Removal of
temporary reclamation at TS1 Dredging
for seawall foundation at TS2 Formation
of temporary seawall at TS2 Seawall
trench works at TS2 |
TZ1
reclamation works Formation
of temporary seawall at TS2 Seawall
trench works at TS2 |
TZ1 and
TS2 reclamation works Formation
of temporary seawall at TS2 |
2.5.5.
Contract
no. HK/2010/06 was commenced on 22 March 2011. During this reporting period,
the principal work activities for Contract no. HK/2010/06 are summarized as
below:
Table
2.8 Principal Work Activities for Contract no. HK/2010/06
September
2012 |
October 2012 |
November
2012 |
Pile head
breaking Sonic tube
trimming |
Pile head
breaking Sonic tube
trimming |
Pile head
breaking Platform
Disassembly Bored Pile
cutting |
Table 2.9 Principal Work Activities for Contract no. HY/2009/19
September
2012 |
October 2012 |
November
2012 |
Marine
bored piling Construction
works for Box Culvert T |
Marine
bored piling Construction
works for Box Culvert T Construction
of 1500f
drainage pipe |
Marine bored
piling Construction
works for Box Culvert T Construction
of 1500f
drainage pipe |
2.5.7.
Implementation
status of the recommended mitigation measures during this reporting period is
presented in Appendix 2.1.
Noise Monitoring Stations
3.1.1. The noise monitoring stations for the Project
are listed and shown in Table 3.1 and Figure 3.1. Appendix 3.1 shows the established Action/Limit
Levels for the monitoring works.
Table
3.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Real
time Noise Monitoring Stations
3.1.1.
The real-noise monitoring stations for the Project are
listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1 shows the established Action/Limit Levels for
the monitoring works.
Table
3.2 Real Time Noise
Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
North Point |
RTN2a |
Electric Centre |
Noise Monitoring
Parameters, Frequency and Duration
3.1.2. The construction noise level
shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period
between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq
(5 minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.3. Noise monitoring shall be carried
out at all the designated monitoring stations. The monitoring frequency shall
depend on the scale of the construction activities. The following is an initial
guide on the regular
monitoring frequency for each station on a weekly basis when noise generating
activities are underway:
·
one
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.4. If construction works are extended to include works
during the hours of 1900 – 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
3.1.5. Real time noise shall be carried out at the
designated monitoring stations. The following is an initial guide on the regular
monitoring frequency for each station on a 24 hours daily basis when noise
generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
Monitoring Equipment
3.1.6. As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
3.1.7. Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
Air Quality Monitoring
Stations
3.2.1.
The
air monitoring stations for the Project are listed and shown in Table
3.3 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels for the
monitoring works.
Table
3.3 Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to |
Wan Chai |
CMA6a |
WDII PRE Site Office * |
Wan Chai |
* Remarks: As per the ENPC
meeting in January 2011, the monitoring stations CMA3a - Future CWB site office
at Wanchai Waterfront Promenade and CMA6a - Future AECOM site office at Work
Area were renamed as remark.
Air Monitoring Parameters,
Frequency and Duration
3.2.2.
One-hour
and 24-hour TSP levels should be measured to indicate the impacts of
construction dust on air quality. The 24-hour TSP levels shall be measured by
following the standard high volume sampling method as set out in the Title 40
of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.
3.2.3.
All
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and any other local atmospheric factors affecting or
affected by site conditions, etc., shall be recorded down in detail.
3.2.4.
For
regular impact monitoring, the sampling frequency of at least once in every
six-days, shall be strictly observed at all the monitoring stations for 24-hour
TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least
three times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5 High
volume samplers (HVSs) in compliance with the following specifications shall be
used for carrying out the 1-hour and 24-hour TSP monitoring:
·
0.6
- 1.7 m3 per minute adjustable flow range;
·
equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
capable
of providing a minimum exposed area of 406 cm2;
·
flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
equipped
with a shelter to protect the filter and sampler;
·
incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
equipped
with a flow recorder for continuous monitoring;
·
provided
with a peaked roof inlet;
·
incorporated
with a manometer;
·
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
easily
changeable filter; and
·
capable
of operating continuously for a 24-hour period.
3.2.6 Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be
traceable to the internationally recognized primary standard and be calibrated
annually. The concern parties such as IEC shall properly document the
calibration data for future reference. All the data should be converted into
standard temperature and pressure condition.
Laboratory Measurement /
Analysis
3.2.7 A clean
laboratory with constant temperature and humidity control, and equipped with
necessary measuring and conditioning instruments to handle the dust samples
collected, shall be available for sample analysis, and equipment calibration
and maintenance. The laboratory should be HOKLAS accredited.
3.2.8 An
alternative non-HOKLAS
accredited laboratory was set-up for carrying out the laboratory
analysis, the laboratory equipment was approved by the ER on 8
February 2011 and
the measurement procedures were witnessed by the IEC. Any measurement performed by
the laboratory was be demonstrated to the satisfaction of the ER and IEC. IEC shall regularly
audit to the measurement performed by the laboratory to ensure the accuracy of
measurement results.
3.2.9 Filter
paper of size 8" x 10" shall be labelled before sampling. It shall be
a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled
chamber for over 24-hours and be pre-weighed before use for the sampling.
3.2.10 After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper shall then be returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
3.2.11 All the
collected samples shall be kept in a good condition for 6 months before
disposal.
impact monitoring for
odour patrol
3.2.12 Odour patrols along the
shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai Public Cargo Working
Area when there is temporary reclamation in Causeway Bay Typhoon Shelter and/or in the ex-Wan Chai Public Cargo
Working Area, or when there is dredging of the odorous sediment and slime at
the south-western corner of the Causeway Bay Typhoon Shelter. Odour patrols
will be carried out at bi-weekly intervals during July, August and September by
a qualified person of the ET who shall:
·
be
at least 16 years of age;
·
be
free from any respiratory illnesses; and
·
not
be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30
min
·
before
and during odour patrol
3.2.13 Odour patrol shall be conducted by independent
trained personnel / competent persons patrolling and sniffing around the shore
as shown in Figure 3.1 to detect any odour at
the concerned hours (afternoon is preferred for higher daily temperature).
3.2.14 The qualified person will use the nose (olfactory
sensor) to sniff odours at different locations. The main odour emission sources
and the areas to be affected by the odour nuisance will be identified.
3.2.15 The perceived odour intensity is to be divided into
5 levels which are ranked in the descending order as follows:
·
0 -
Not detected. No odour perceived or an odour so weak that it cannot be easily
characterized or described;
·
1 -
Slight Identifiable odour, and slight chance to have odour nuisance;
·
2 -
Moderate Identifiable odour, and moderate chance to have odour nuisance;
·
3 -
Strong Identifiable, likely to have odour nuisance;
·
4 -
Extreme Severe odour, and unacceptable odour level.
3.2.16 The findings including odour intensity, odour
nature and possible odour sources, and also the local wind speed and direction
at each location will be recorded. In addition, some relevant meteorological
and tidal data such as daily average temperature, and daily average humidity,
on that surveyed day will be obtained from the Hong Kong Observatory Station
for reference. The Action and Limit levels for odour patrol are shown in Appendix 3.1.
3.3.1. The EIA Report has identified that the key water
quality impact would be associated with the dredging works during the
construction phase. Marine water quality
monitoring for dissolved oxygen (DO), suspended solid (SS) and turbidity is
therefore recommended to be carried out at selected WSD flushing water
intakes. The impact monitoring should be
carried out during the proposed dredging works to ensure the compliance with
the water quality standards.
3.3.2. The
updated EM&A Manual for EP-356/2009 (Version in March 2011) is approval by
EPD on 29 April 2011. As such, the Action Level and Limit Level for the wet
season (April – September) will be effected and applied to the water quality
monitoring data from 30 April 2011.
Water Quality Monitoring Stations
3.3.3. It is proposed to monitor the water quality at 9
WSD salt water intakes and 14 cooling water intakes along the seafront of the
Table
3.4
Marine Water Quality Stations for Water
Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
|
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
RW1 |
Wan Chai (Reprovision) |
836188.8 |
815911.1 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Wan |
835932.8 |
815888.2 |
C4w |
Wan |
835629.8 |
815889.2 |
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
C6 |
World Trade Centre |
837009.6 |
815999.3 |
C7 |
|
837193.7 |
816150.0 |
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
RC1 |
Proposed HKAPA Extension |
835487.7 |
815987.7 |
RC5 |
Sun Hung Kai Centre (Reprovision) |
836291.4 |